Apartment Building Subsidence Remediated - Mainmark
Recommend Documents
from measured whole-building thermal response data are compared with UAs based on U- ...... CONTAM runs; John Schmelzer installed monitoring equipment and trained our Russian ... Armstrong, P.R., C.E. Hancock, and J.E. Seem. 1991.
Abslrucl: The aim of this study is to find out the motives that affect consumer ... on neoclassical economic theory that assumes people make rational economic decisiotls ... as a salesperson will be in knowing those differences and appealing to them.
Massachusetts waste site database, a total of 38 school sites have been built on ... Richard Desrosiers, Principal of Keith Middle School, New Bedford, for ...... Some have suggested rebuilding towards the south end of the site, where the ..... 72. N
regime as a consequence of the advancing then retreating evolution of the collisional system. ... evolved first as an advancing collisional wedge and then as.
Apr 17, 2013 - It is a mature oil field with around 58 years of production with 40 producing ... parts of the Lost Hills oil field in California(2) and it was up to 10 ft.
Oct 22, 2009 - With the rapid development of GPS technology ... slowly). Currently, in Vietnam, subsidence monitoring is deploying with theodolite ... and technology, nowadays, several companies using GPS technology for subsidence .... The GPS survey
Barker, R. W. 1960: Taxonomic notes on the species figured by. H.B. Brady in his .... Cibicides lobatulus (Walker & Jacob); Hayward & Buzas 1979, pi. 10, fig.
of surface subsidence in asymmetric parallel highway tunnels, Journal of ... This is a PDF file of an unedited manuscript that has been accepted for publication. ... note that during the production process errors may be discovered which ... b Departm
Abstract A constant-parameter coupled model for groundwater flow and aquitard ... related IBS module, is used in this paper to predict land subsidence that.
compression indicators were monitored to observe the deep and shallow layer ... layer compression indicator showed that most of the compression occurred in.
Apartment Building Subsidence Remediated - Mainmark
Above, left: Typical JOG site control centre with computer controls, slurry tanks and pumping equipment. Above, right: A
PROJECT PROFILE Z13 Y180
Apartment Building Subsidence Remediated 1.
2.
3.
4.
INDUSTRY
Commercial STRUCTURE
Apartment building PROBLEM
Earthquake remediation LOCATION
Christchurch, New Zealand DURATION / YEAR
20 days / 2013 TECHNOLOGY
Jet Grouting & JOG ComputerControlled Grouting BUSINESS UNIT
Mainmark New Zealand Above: 1. Technicians and engineers inspect the site. 2. Jet Grout injection from very confined spaces. 3. A larger machine Jet Grouting from a more spacious area. 4. Cement batching plant: high speed mixing equipment in front and cement silo behind. This plant can produce and deliver 24m3 of cement slurry per hour.
Summary A shallow, weak soil stratum under a heavy-weight concrete six-storey apartment block in Christchurch had caused the building to suffer differential settlement of up to 70mm after the recent earthquakes. It was rectified using Jet Grouting to strengthen the foundation ground and by using JOG Computer-Controlled Grouting to raise the building back precisely to its design levels.
Objectives Firstly to strengthen the entire foundation ground and secondly, to correct the settlement and precisely re-level the whole building.
Solution 1. Jet Grouting method. Installation of 22 Jet-Crete columns under the critical load points of the building to support and transfer loads down to the gravels. (These columns are sometimes called “soil- crete”, being a mix of cementitious grout and in-situ soil). 2. JOG Computer-Controlled Grouting levelling method. The computer-controlled grout levelling system was used to level the differential settlement of the structure. 20 injection ports were installed through the concrete foundations, down to the top of the Jet-Crete columns, where the high mobility grout was introduced.
PROJECT PROFILE Z13 Y180
Apartment Building Subsidence Remediated continued
It took 10 working days to set up, install the 22 columns and then remove the Jet-Crete equipment. A further 10 working days were required to install the JOG Computer-Controlled Grouting levelling equipment, level the building back to the agreed lift requirement and then remove the equipment. The building was brought back exactly as required with the foundation ground greatly strengthened to better protect the structure from future seismic activity.
Above, left: Typical JOG site control centre with computer controls, slurry tanks and pumping equipment. Above, right: Angular insertion of JOG injector.