ASME Certificate Holders (International/Nuclear). 1583. 1468. 1795. 2045. 50 .....
Zugversuch ASME SA-370, Flachzugprobe (15 mm). Re, 0,2%. Rm. A, 2“ (50 ...
ONE/TÜV/BV's shareholders
ONECIS
TÜV Nord
Insurance Company
Bureau Veritas
Boston, USA
Paris, France
Essen, Germany
1/3
1/3
1/3
Technische Inspektions GmbH Essen
OneTUVBV.ppt 08/05
The new One
The new One – the best one for you
ASME Section III Nuclear Components B31.PPT 09/03
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 1
ASME Code SECTION III NUCLEAR
SEC3.PPT 04/2008
Hierarchy of Standards in the USA and Canada • Settlements in USA / Canada • ASME - Boiler & Pressure Vessel Code
ASME B31.3
Construction-Code
Process Piping
Section I
Section III 1,2,3 Section IV
Power Boilers
Nuclear Power
Section VIII 1,2,3
Heating Boilers Pressure Vessels
Section X
Section XII
Fiber Plastics
Transport Tanks
ASME B31.1 Power Piping
Referenced Code
ASME B31.1
Section II
Section V
Section IX
Power Piping
Materials
NDE
Welding
"Inservice"-Code
Section VI
Section VII
Section XI
Heating Boilers
Power Boilers
Nuclear Power
Standards, Recommendations
ANSI
ASTM
AWS
ASNT
• National Board Inspection Code NBIC SEC0.PPT 08/05
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 2
ASME Certificate Holders (International/Nuclear) 80
2500
45 20
70
2000 95 17
61
60
International
83 15 68 14
1500
50
51
50
50
1000
Nuclear
40 2005
2006
2007
2008
ASME "Nuclear Certificates" ASME Code Section III (Nuclear Components) N
Nuclear Components Vessels, Piping Systems, Valves, Pumps, etc.
NA
Nuclear Installer Assembly of Components
NPT
Nuclear Parts Welded Parts of Nuclear Components
NV
Nuclear Safety Valves
N3
Storage and Transport Containment of Nuclear Fuel
NS
Nuclear Supports Certificate of Accreditation
QSC
Quality System Certificate Material Manufacturers \SEC0.PPT 05/03
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 3
Efforts of an ASME Authorization
ASME Code Books QA Manual and Procedures
70%
Qualification of Procedures and Personnel Representative Demo Item Drawing, Calculation, Part List, Purchase Orders, Material Test Reports
Min. 6 Months of Preparation Demonstration of the QA- System in a Survey Issuance of Certificates and Stamps
The new One The new One – the best one for you
Classification
B31.PPT 09/03
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 4
Code Section III Regulations Owner
Setting of Standards for new plants
Regulatory Authorities: NRC
PSAR (preliminary Safety Analysis Report) settling Codes, Editions and Addenda
Construction Code Inservice Code ASME Code Section III-1 ASME Code Section XI
Referenced Codes NQA-1 Quality Assurance Requirements QAI-1 Qualifications for Authorized Inspections ASME Code Sections II, V, IX, XI ANSI, AWS, ASNT
SEC3.PPT 10/95
ASME Code Nuclear - Structure
Rules for Construction of Nuclear Facility Components Subsection NCA General Requirements for Division 1 and Division 2
Division 1 Subsection NB Class 1 Components
Division 2
Division 3
Code for Concrete Containments
Containments for Transportation and Storage of Spent Nuclear Fuel and High Level Radioactive Material and Waste
Subsection NC Class 2 Components
Subsection CC Subsection ND Class 3 Components
Concrete Containments and Division 2 Appendices
Subsection NE Class MC Supports
Subsection WA Subsection NF Supports
Subsection NG Core Support Structures
Subsection NH
General Requirements for Division 3
Subsection WB Class TP (Type B) Containment
Subsection WC Class SC Storage Containments
Class 1 Components in Elevated Temperature Service
Appendices
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
SEC III.PPT 04 / 2008
Page 5
ASME Code Section III Structure
NCA NCA-1000 NCA-2000 NCA-3000 NCA-4000 NCA-5000 NCA-8000
Scope of Section III Classification of Components and Supports Responsibilities and Duties Quality Assurance Authorized Inspection Certificates, Nameplates, Code Symbol Stamping, and Data Reports NCA-9000 Glossary
SEC3.PPT 01 / 2008
ASME Code Section III Structure
NB, NC, ND, NE, NF, NG, NH NX-1000 Introduction NX-2000 Material NX-2500 Examination and Repair of Pressure-Retaining Material (by MM) NX-3000 Design NX-4000 Fabrication and Installation NX-5000 Examination (by Manufacturer of Item) NX-6000 Testing NX-7000 Overpressure Protection NX-8000 Nameplates, Stamping, and Reports
SEC3.PPT 01 / 2008
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 6
Code Section III Stamping Example
Safety Valve Pressure Vessel
Restrictor Pump Component Support: NSNS-Certification
Welded Head Line Valve Shop Assembly Pipe: CMTR (material)
Field Weld Elbow smls: CMTR (material)
Piping System SEC3.PPT 10/95
NCA-9000: Glossary - Code Items
Appurtenance. An item intended to be attached to a completed and stamped component which has work performed on it requiring verification by an Inspector. Assembly. A grouping of Code items joined by mechanical means, welding, or brazing. Component. A vessel, concrete reactor vessel, concrete containment, pump, pressure relief valve, line valve, storage tank, piping system, or core support structure that is designed, constructed, and stamped in accordance with the rules of this Section.
Containment System. An item which forms a structure that encloses a nuclear power system or that may be connected to other containment items and which is designed to provide a pressure containing barrier for the primary purpose of containing, within leakage limits, or of channeling, for containment or for controlled disposal, radioactive or hazardous effluents released from the system. Core Support Structures. Those structures or parts of structures which are designed to provide direct support or restraint of the core (fuel and blanket assemblies) within the reactor pressure vessel.
SEC3NCA.PPT 9/96
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 7
NCA-9000: Glossary - Code Items
Item. A product constructed under a Certificate of Authorization (NCA-3120) or material (NCA-1220). Part. An item which is attached to or becomes a portion of a component or component support before completion and stamping of the component or component support. Parts have work performed on them requiring verification by an Inspector. Piping Subassembly. A section of piping system consisting of fittings and pipes or tubes which are fabricated as subassemblies in a shop or in the field before being installed in a nuclear power system.
Piping Support. A metal element which transmits loads between the nuclear power plant piping and the building structure. Piping System. A piping system is an assembly of piping, piping supports, components, and, if applicable, component supports of one or more Code Classes, with a defined function as described in the Design Specification for the piping system.
SEC3NCA.PPT 9/96
NCA-9000: Glossary - Code Items Construction. An all-inclusive term comprising materials, design, fabrication, examination, testing, inspection, and certification required in the manufacture and installation of an item. Fabrication. Those actions required to manufacture components, parts, and appurtenances. These actions may include forming, machining, assem-bling, welding, brazing, heat treating, examination, testing, inspection, and certification. Fabrication does not include design.
Installation. Those actions required to place and attach components to their supports and join items of a nuclear power system by welding or mechanical means. Repair. The process of physically restoring a nonconformance to a condition such that an item complies with Code requirements. Verification. A review to ensure that activities have been performed and documented in accordance with applicable requirements.
SEC3NCA.PPT 9/96
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 8
Code Section III Terms and Certification
Component
Part
Welded Head Pressure
Material
Vessel
NPT Authorization CMTR Plate
N Authorization Material Organisation Source Material Billet
Approved Supplier
The new One
The new One – the best one for you
Material ASME Code Section II and Section III, NXNX-2000 B31.PPT 09/03
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 9
NCA-9000 Material
Material. Metallic materials manufactured to an SA, SB, SFA, or any other material specification permitted in Section III and which are manufactured, identified, and certified in accordance with the requirements of Section III.
Source Material. Metallic products used for conversion to or qualification as material by a Certificate Holder or Material Organization. Unqualified Source Material. Source material not producted by a Certificate Holder, Material Organization, or approved supplier in accordance with the requirement of Section III, NCA3800.
SEC3NCA.PPT 9/96
Section III NCA-3800 Material Supply Example 1
ASME accreditation
N
N type Certificate Holder
QSC accredited M.O.
NCA-4000
NCA-3850
CMTR Material
Analysis source material
control
Approved Supplier
SEC3NCA.PPT 02-05
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 10
Section III NCA-3800 Material Supply Example 2
ASME accreditation
N
N type Certificate Holder
QSC accredited M.O.
NCA-4000
NCA-3850
qualified CMTR Material
Material Organization NCA-3850
control Analysis source material
Approved Supplier SEC3NCA.PPT 02-05
NCA-9000 Material
Material. Metallic materials manufactured to an SA, SB, SFA, or any other material specification permitted in Section III and which are manufactured, identified, and certified in accordance with the requirements of Section III.
Source Material. Metallic products used for conversion to or qualification as material by a Certificate Holder or Material Organization. Unqualified Source Material. Source material not producted by a Certificate Holder, Material Organization, or approved supplier in accordance with the requirement of Section III, NCA3800.
SEC3NCA.PPT 9/96
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 11
NCA-3855 Unqualified Source Material Example
How to utilize Unqualified Source Material? 1) Unqualified Source Material Certification of
Material Manufacturer
Marking
-Heat Analysis -Melting -Heat Treatment -No weld repair
Not qualified
2) Unqualified Source Material with CMTR (NCA-3855.5) N type Certificate Holder Marking
MTR
CMTR
Analysis and full Testing of each piece of material
Heat Analysis ProductMelting Analysis Heat Treatment Test Results No weld repair NDE Reports QS Statement
Sec3 NCA.PPT 01/2008
Hierarchie der Standards • Verordnungen in USA / Canada • ASME - Boiler & Pressure Vessel Code Construction-Code Section I
Section III
Section IV
Section VIII
Section X
Dampfkessel
Nuclear Power
Heizkessel
Druckbehälter
Fiber Plastics
Reference Code
ASME B31.1
ASME B31.3
Kraftw. Rohrleit.
Rohrleitungen
ASME B31.1
Section II
Section V
Section IX
Power Piping
Material
ZfP
Schweißen
"Inservice"-Code
Normen, Empfehlungen
Section VI
Section VII
Section XI
Heizkessel
Dampfkessel
Nuclear Power
ANSI
ASTM
AWS
ASNT
• National Board Inspection Code NBIC SEC0.PPT 05-03
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 12
Section III-1, NB-2000 Material NB-2100
General Requirement for Material
NB-2200
Material Test Coupons and Specimens for Ferritic Steel Material
NB-2300
Fracture Toughness Requirements for Material
NB-2400
Welding Material
NB-2500
Examination and Repair of Pressure Retaining Material
NB-2600
Material Organizations´ Quality System Programs
NB-2700
Dimensional Standards SEC3NB.PPT 01/2008
Goodplate Mfgr.
MTR No. 123
Material Test Report Empfänger:Rusty Tank Comp. Essen Auftrag Nr. 0816 Erzeugnis: ASME SA-516M Gr. 415 Edition 2001 Addenda 2002 - ASTM A-516M-90 Gr.415 Nenndicke: 15 [mm] 1 Stck. Größe:
15,00 x 3700 x 3850 [mm]
Kennzeichnung: GPM SA-516M Gr. 415
Masse: 4026 [kg] 15 [mm]
Walztafel Nr. 987654 Schmelze Nr. 123456
Zustand: wie gewalzt Herstellung: Vakuumentgast Chemische Zusammensetzung der Schmelze in % C Si Mn P S N Cu 0,20 0,20 0,70 0,02 0,02 0,08 0,20 V: 0,00 Nb: 0,02 Ti: 0,00
Ni 0,30
Cr 0,20
Mo 0,10
AL 0,025
charpy impact Test acc. to SA - 370 bei -52° C; 64J 86J 72J
Zugversuch ASME SA-370, Flachzugprobe (15 mm) Re, 0,2% 285 [N/mm²]
Rm 512 [N/mm²]
A, 2“ (50 mm) 29 %
Goodplate Mfgr AG, Zuffenhausen, Germany
Feinkornstahl nach ASME SA-20 21. Januar 2003 SEC2.PPT 10/2007
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 13
Example NCA-3860
Goodplate Mfgr.CMTR No. 001
Certified Material Test Report
page 1/2
Purchaser: Rusty Tank Comp. Essen, Order Nr. 0815 1 Ea Carbon Steel Plate ½“ x 146“ x 152“mm ( T x W x L ) Material: ASME SA-516 Gr. 60 , Section II A and Section III Subsection NB (Class 1), Edition 98 Addenda 99 Marking: GPM SA-516 Gr.60
CLASS 1
Pl. 987654
Heat# 123456
Condition of plate and test specimen: as rolled, no heat treatment performed Chemical Composition in % C Si Mn P 0,20 0,20 0,70 0,02
S 0,02
N 0,08
Cu 0,20
Ni 0,30
Cr 0,20
Mo 0,10
AL 0,025
V 0,00
Nb 0,02
Charpy impact Test acc. to SA - 370 at -62° F; Energy: 64, 86, 72 ft-lb, Lateral Expansion 45, 55, 54 mils Tension Test ASME SA-370 Yield (0,2%) Tensile 41336 psi 74259 psi
A, 4*D0 29%
Fine Grain Practice to ASME SA-20
Ultrasonic Examination: 100% Angle Beam Examination according to SA-577 and NB-2532.2 after rolling to size: Acceptable, UT Report attached on page 2/2 Visual Examination: no defects Welded repairs were not performed. The material was manufactured under our ASME Quality System Certificate of Accreditation No. 1234 Exp. 31. December 2002. We certify that the contents of this report are correct and that all test results and operations performed by Goodplate Mfgr. Or our subcontractors are in compliance with the material specification and the specific applicable material requirements of Section III, Subsection NB. Goodplate Mfgr AG, Zuffenhausen, Germany
QA Manager: Gutfried
25. März 2000 SEC2.PPT 09/2007
The new One
The new One – the best one for you
Fabrication NXNX-4000 B31.PPT 09/03
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 14
Section III - 1 NB-4000 Fabrication and Installation
NB-4100
GENERAL REQUIREMENTS
NB-4200 FORMING, FITTING, AND ALIGNING NB-4210 CUTTING, FORMING, AND BENDING NB-4220 FORMING TOLERANCES NB-4230 FITTING AND ALIGNING NB-4240 REQUIREMENTS FOR WELD JOINTS IN COMPONENTS NB-4250 WELDING END TRANSITIONS - MAXIMUM ENVELOPE NB-4300 WELDING QUALIFICATIONS NB-4310 GENERAL REQUIREMENTS NB-4320 WELDING QUALIFICATIONS, RECORDS, AND IDENTIFYING STAMPS NB-4330 GENERAL REQUIREMENTS FOR WELDING PROCEDURE QUALIFICATION TESTS NB-4350 SPECIAL QUALIFICATION REQUIREMENTS FOR TUBE-TO-TUBESHEET WELDS NB-4360 QUALIFICATION REQUIREMENTS FOR WELDING SPECIALLY DESIGNED WELDED SEALS
SEC3NB.PPT 01/2008
Section III - 1 NB-4000 Fabrication and Installation
NB-4400 RULES GOVERNING MAKING, EXAMINING, AND REPAIRING WELDS NB-4410 PRECAUTIONS TO BE TAKEN BEFORE WELDING NB-4420 RULES FOR MAKING WELDED JOINTS NB-4430 WELDING OF ATTACHMENTS NB-4450 REPAIR OF WELD METAL DEFECTS NB-4500
BRAZING
NB-4600
HEAT TREATMENT
NB-4700
MECHANICAL JOINTS
SEC3NB.PPT 01/2008
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 15
Section IX - Contents
Part QW - Welding Article I
Welding General Requirements
QW-100 ff
Article II
Welding Procedure Qualifications
QW-200 ff
Article III
Welding Performance Qualifications
QW-300 ff
Article IV
Welding Data
QW-400 ff
Article V
Standard WPS (SWPS)
QW-500 ff
Add 2000
Part QB - Brazing APPENDICES (Welding and Brazing Forms, and list of SWPSs)
SEC9.PPT 8-00
The new One
The new One – the best one for you
NDE Section V and Section III, NXNX-5000 B31.PPT 09/03
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 16
Section III Div. 1 - NB-5000 Examination
NB-5100
GENERAL REQUIREMENTS FOR EXAMINATION
NB-5200
REQUIRED EXAMINATION OF WELDS FOR FABRICATION AND PRESERVICE BASELINE
NB-5300
ACCEPTANCE STANDARDS
NB-5400
FINAL EXAMINATION OF VESSELS
NB-5500
QUALIFICATIONS AND CERTIFICATION OF NONDESTRUCTIVE EXAMINATION PERSONNEL
SEC3NB.PPT 11-00
Section III - 1 NB-5500 NB-5500
QUALIFICATIONS AND CERTIFICATION OF NONDESTRUCTIVE EXAMINATION PERSONNEL
NB-5510
GENERAL REQUIREMENTS
NB-5520
PERSONNEL QUALIFICATION, CERTIFICATION, AND VERIFICATION
NB-5530
RECORDS
SEC3NB.PPT 11-00
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 17
Section III - 1 NB-5500 NDE Personnel NB-5510 GENERAL REQUIREMENTS NB-5520 PERSONNEL QUALIFICATION, CERTIFICATION, AND VERIFICATION NB-5521 Qualification Procedure (a) Personnel performing nondestructive examinations shall be qualified in accordance with the recommended guidelines of SNT-TC-1A 1992 Edition. The Employer's written practice, required by paragraph 5 of SNT-TC-1A, shall identify the requirements relative to the recommended guidelines. The recommended guidelines of SNT-TC-1A shall be considered as minimum requirements, except as modified in (1) through (5) below. (1) Qualification of Level III shall be by examination. (..) (2) The written practice shall be referenced in the Employer's Quality Program. (3) The number of hours of training and experience for nondestructive examination personnel (..) (4) For visual examination, the Jaeger Number 1 letters shall be used (5) Level I individual specifics (..) (6) Personnel performing the volumetric preservice examination using the ultrasonic method shall meet the requirements of Section XI, Appendix VII, and Appendix VIII when required by Appendix I.
SEC3NB.PPT 01/2008
Section III - 1 NB-5500 NDE Personnel NB-5522 Certification of Personnel (a) The Employer retains responsibility for the adequacy of the program and is responsible for certification of Levels I, II, and III nondestructive examination personnel. (b) When ASNT is the outside agency administering the Level III basic and method examinations [NB-5521(a) (1) (a) ], the Employer may use a letter from ASNT as evidence on which to base the certification. (c) When an outside agency is the examining agent for Level III qualification of the Employer's personnel, the examination results shall be included with the Employer's record.
NB-5523 Verification of Nondestructive Examination Personnel Certification The Certificate Holder has the responsibility to verify the qualification and certification of nondestructive examination personnel employed by Material Organizations and qualified by them in accordance with NCA-3820 and subcontractors who provide nondestructive examination services to them.
SEC3NB.PPT 11-00
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 18
The new One
The new One – the best one for you
Quality Assurance
B31.PPT 09/03
Quality Assurance NCA 4000 Construction of Class 1, 2, 3, CS, MC, CB, CC Items
Material Organisations Manufacturer or Supply of Material
NCA 3800
NCA 4000
NCA-3850 Quality System Program Requirements NQA -1 + Modified and supplemented in NCA - 4120 (b) and NCA - 4134
(incl. NCA-3855 Source Material and Services, NCA-3856 Identification and Marking)
CS=Core Support, MC=Metal Containment, CB, CC=Concrete SEC3NCA 02/05
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 19
Quality Assurance NCA 4000
Quality Assurance Program
Basic Req.
NQA -1 Suppl. Req.
Modification and Supplements by NCA - 4134
1) Organization
compl.
1s -1 compl.
None
2) Quality Assurance Program
compl.
2s –1, 2s -3 compl.
NDE- Personnel Qualification NX - 5520 Control of QA - Program Liaison to AIA
3) Design Control
compl.
3s -1 compl.
Modif. / Suppl. (Verification in compliance with design Spec.)
4) Procurement Document Control
compl.
4s -1 compl.
None
5) Instruction, Procedures, and Drawings
compl.
None
None
6) Document Control
compl.
6s -1 compl.
None
Sec 3 NCA.PPT 05/02
Quality Assurance NCA 4000 Quality Assurance Program
Basic Req.
NQA -1 Suppl. Req.
Modification and Supplements by NCA - 4134
7) Control of Purchased Items and Services
7 compl.
7s -1 with exception Para. 8.3 not applicable Para. 4.0 Para. 8.2, 1 (b); (c)
None
8) Identification and Control of items
8 compl.
8s -1 compl.
Modif. / Supplements • Welding Material Control • Checklist for Material Characteristic
9) Control of Process 10) Inspection
9 compl.
9s -1 compl.
Modif. / Supplements
10 compl.
10s -1 with exception Para. 3.1
Modif. / Supplements • Traveler • Hold Points etc.
11) Test Control
11 compl.
11s -1 compl.
None
12) Control of Measuring and Test Equipment
12 compl.
12s -1 compl.
Modif. / Supplements
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Sec 3 NCA.PPT 05/02
Page 20
Quality Assurance NCA 4000 Quality Assurance Program 13) Handling, Storage, and Shipping
NQA -1 Basic Reg. Suppl. Reg. 13 compl. 13s -1 compl.
Modification and Supplements by NCA - 4134 None
14) Inspection and test 14 compl. status
None
Modif. / Suppl.
15) Control of Nonconforming Items
15s -1
None
16) Corrective Action
16 compl.
Modif. / Suppl.
17) Quality Assurance Records
17 compl.
with exception Para. 2.7, 2.8, 4.4 not applicable
Modif. / Suppl. • Lifetime Records • Nonpernament Records etc.
18) Audits
18 compl.
18s -1
Modif. / Suppl. Audit frequency at least once annually
Sec 3 NCA.PPT 05/02
NCA- 4000 Quality Assurance (cont'd.) TABLE NCA-4134.17-1 LIFETIME QUALITY ASSURANCE RECORD Record 1. 2. 3. 4. 5. 6. 7. 8. 9.
Index to lifetime records (NCA-4134.17) Code Data Reports (NCA-8400) Design Specification (NCA-3250) [Note (2)] Design output documents, Division 1 (NCA-3350 and NCA-3550) [Note (2)] Design Report, Division 2 Overpressure Protection Report (NB-7200, NC-7200, or ND-7200) Construction Specification (NCA-3340) As-built drawings (NCA-3454) Certified Material Test Reports (CMTR) and documentation providing traceability to location used, if required (NX-4122)
Record 10. Records of post-tensioning sequence, procedure, and loads 11. Heat treatment records [Note (1)] 12. Qualification test reports such as for concrete design mixes (CC-2460) and safety valves (NB-7700) 13. Structural integrity test reports (CC-6260) 14. Final hydrostatic and pneumatic test results (NCA-5280) 15. Final nondestructive examination reports; final radiographs as specified by the Owner for Section XI applications 16. Repair records when required by Code (NX-4130) 17. Weld procedures 18. Construction Report (NCA-3454)
GENERAL NOTE: Nonconformance reports that affect those records listed shall be incorporated into the record or be retained with the records. NOTES: (1) Either heat treatment charts or certified summaries of time and temperature data may be provided. These data may be included as part of the CMTR. (2) For supports designed by load rating, the Load Capacity Data Sheet is the design output document to be maintained as a lifetime quality assurance record. For standard supports designed by analysis and supplied with a Certified Design Report Summary, the Certified Design Report Summary is the design output document to be maintained as a lifetime quality assurance record. SEC3NCA.PPT 01/2008
(c) ONE/TÜV/BV - Nuclear Milano, June 2009
Page 21
NCA- 4000 Quality Assurance (cont'd.) TABLE NCA-4134.17-2 NONPERMANENT QUALITY ASSURANCE RECORDS Record
Retention Period
1. QA Program Manual 2. Design procurement and QA procedures (NCA-4134.5) 3. Installation and NDE procedures (NX-5112) 4. Personnel qualification records (NX-5520 and NX-4322) 5. Purchase orders 6. Audit and survey reports (NCA-4121 and NCA-4134.18) 7. Final radiographs not covered in Table NCA-4134.17-1, Record 15 8. Calibration records (NCA-4134.12) 9. Process sheets, travelers, or checklists (NCA-4134.10) 10. Rebar splice test reports (CC-4330) 11. Joint-welder identification records when such records are used in lieu of physical marking of welds (NX-4322)
3 years after superseded or invalidated 3 years after superseded or invalidated 10 years after superseded or invalidated 3 years after superseded or invalidated 10 years after superseded or invalidated 3 years after completion of report 10 years after completion Until recalibrated 10 years after completion 10 years after completion of report 10 years after completion of report
GENERAL NOTE: Nonconformance reports, which affect those records listed and are not incorporated into the record, shall be retained for the retention period applicable to the record the nonconformance report affects.