Planning Ordering Materials and Scheduling Project Supervision Mobilization Delivering equipment, tools and materials to work site Bldg 010 Preparation 2 men Bldg 010 Insulation 2" Fiberglass insulation with all service jacket 453 sq.ft. of piping
Material
Unit Prices Labor
Units
$500.00 $
Notes: 1. Just the north discharge header will be insulated. 2. Piping is broken down into sf of insulation to apply. 3. Fiberglass insulation with general purpose covering is used.
Equipment
6,528
$
Total
$0.00
10,521
$
$500 -
Subtotal
$17,049
Contingency (10%) Bond (2.7%) Insurance (2.1%) General Conditions (9.0%) Overhead & Profit (6.8%)
$1,705 $460 $358 $1,534 $1,159
Total
$22,266
Project Assignment: Consultant Engineering: $20,000 Project FA Amount $43,337 Total Project cost with FA