Dec 4, 2017 - Redgate Subdivision (park and trails). 2018-2027. 107,700. -. 107,700. -. 107,700. 10,770. 96,930. 92,084.
County of Prince Edward 2017 Development Charges Background Study
For Public Circulation and Comment
December 1, 2017
Contents Page 1.
Introduction ........................................................................................................ 1-1 1.1 Purpose of this Document....................................................................... 1-1 1.2 Summary of the Process......................................................................... 1-2
2.
Current County of Prince Edward D.C. Policy ................................................... 2-1 2.1 By-law Enactment ................................................................................... 2-1 2.2 Services Covered ................................................................................... 2-1 2.3 Timing of D.C. Calculation and Payment ................................................ 2-2 2.4 Redevelopment Credit ............................................................................ 2-2 2.5 Exemptions ............................................................................................. 2-2
3.
Anticipated Development in the County of Prince Edward ................................ 3-1 3.1 Requirements of the Act ......................................................................... 3-1 3.2 Basis of Population, Household and Non-Residential Gross Floor Area Forecast ......................................................................................... 3-1 3.3 Summary of Growth Forecast ................................................................. 3-2
4.
The Approach to the Calculation of the Charge ................................................. 4-1 4.1 Services Potentially Involved .................................................................. 4-1 4.2 Increase in Need for Service ................................................................... 4-1 4.3 Local Service Policy ................................................................................ 4-2 4.4 Capital Forecast ...................................................................................... 4-2 4.5 Treatment of Credits ............................................................................... 4-7 4.6 Eligible Debt and Committed Excess Capacity ....................................... 4-7 4.7 Existing Reserve Funds .......................................................................... 4-7 4.8 Deductions .............................................................................................. 4-8 4.8.1 Reduction Required by Level of Service Ceiling .......................... 4-8 4.8.2 Reduction for Uncommitted Excess Capacity .............................. 4-9 4.8.3 Reduction for Benefit to Existing Development ............................ 4-9 4.8.4 Reduction for Anticipated Grants, Subsidies and Other Contributions .............................................................................. 4-10 4.8.5 The 10% Reduction.................................................................... 4-10 4.9 D.C. By-Law Spatial Applicability .......................................................... 4-11
5.
D.C. Eligible Cost Analysis by Service .............................................................. 5-1 5.1 Service Levels and 10-Year Capital Costs for County-wide D.C. Calculation .............................................................................................. 5-1 5.1.1 Marinas and Boat Launches ........................................................ 5-1 5.1.2 Parks and Recreation Services .................................................... 5-2 5.1.3 Library Services ........................................................................... 5-2 5.1.4 Administration (Studies) ............................................................... 5-3 5.1.5 Homes for the Aged ..................................................................... 5-3 5.1.6 Waste Diversion Services ............................................................ 5-4 5.1.7 Municipal Parking Services .......................................................... 5-4 5.2 Service Levels and 20-Year Capital Costs for County-wide D.C. Calculation ............................................................................................ 5-13
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
5.2.1 Transportation Services ............................................................... 5-13 5.2.2 Fire Protection Services ............................................................... 5-13 6.
D.C. Calculation................................................................................................. 6-1
7.
D.C. Policy Recommendations and D.C. By-law Rules ..................................... 7-1 7.1 D.C. By-law Structure ............................................................................. 7-1 7.2 D.C. By-law Rules ................................................................................... 7-2 7.2.1 Payment in any Particular Case ................................................... 7-2 7.2.2 Determination of the Amount of the Charge ................................. 7-2 7.2.3 Application to Redevelopment of Land (Demolition and Conversion) .................................................................................. 7-3 7.2.4 Exemptions (full or partial) ........................................................... 7-3 7.2.5 Phase in Provision(s) ................................................................... 7-4 7.2.6 Timing of Collection...................................................................... 7-4 7.2.7 Indexing ....................................................................................... 7-4 7.2.8 D.C. Spatial Applicability .............................................................. 7-5 7.3 Other D.C. By-law Provisions ................................................................. 7-5 7.3.1 Categories of Services for Reserve Fund and Credit Purposes ...................................................................................... 7-5 7.3.2 By-law In-force Date..................................................................... 7-5 7.3.3 Minimum Interest Rate Paid on Refunds and Charged for Inter-Reserve Fund Borrowing ..................................................... 7-5 7.4 Other Recommendations ........................................................................ 7-5
8.
Asset Management Plan ................................................................................... 8-1 8.1 Introduction ............................................................................................. 8-1
9.
By-law Implementation ...................................................................................... 9-1 9.1 Public Consultation ................................................................................. 9-1 9.1.1 Public Meeting of Council ............................................................. 9-1 9.1.2 Other Consultation Activity ........................................................... 9-1 9.2 Anticipated Impact of the Charge on Development ................................. 9-2 9.3 Implementation Requirements ................................................................ 9-2 9.3.1 Notice of Passage ........................................................................ 9-3 9.3.2 By-law Pamphlet .......................................................................... 9-3 9.3.3 Appeals ........................................................................................ 9-4 9.3.4 Complaints ................................................................................... 9-4 9.3.5 Credits .......................................................................................... 9-4 9.3.6 Front-Ending Agreements ............................................................ 9-4 9.3.7 Severance and Subdivision Agreement Conditions ..................... 9-5
Appendix A – Background Information on Residential and Non-residential Growth Forecast ............................................................................................................A-1 Appendix B – Level of Service .....................................................................................B-1 Appendix C – Long-term Capital and Operating Cost Examination............................. C-1 Appendix D – Proposed D.C. By-law........................................................................... D-1 Appendix E – Local Service Policy ...............................................................................E-1 Appendix F – Implementation Policy Review ............................................................... F-1 Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
List of Acronyms and Abbreviations A.M.P. D.C. D.C.A. E.S.A. G.F.A. mm N.F.P.O.W. O.M.B. O.Reg. para. P.P.U. R.S.O. sq.ft. s.s.
Asset Management Plan Development Charge Development Charges Act Environmentally Safe Area Gross floor area Millimeters No fixed place of work Ontario Municipal Board Ontario Regulation Paragraph Persons per unit Revised Statute of Ontario Square foot Subsection
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 1-1
1. Introduction 1.1
Purpose of this Document
This background study has been prepared pursuant to the requirements of the Development Charges Act (D.C.A.), 1997 (s.10), and accordingly, recommends new development charges (D.C.) and policies for the County of Prince Edward. The County retained Watson & Associates Economists Ltd. (Watson) to undertake the D.C. Background Study process in 2017. Watson worked with senior staff from the County in preparing this D.C. analysis and the policy recommendations. This D.C. Background Study, containing the proposed D.C. By-Law, will be distributed to members of the public in order to provide interested parties with sufficient background information on the legislation, the study’s recommendations and an outline of the basis for these recommendations. This report has been prepared, in the first instance, to meet the statutory requirements applicable to the County’s D.C. Background Study, as summarized in Chapter 4 and applied in Chapters 5 and 6. It also addresses the forecast amount, type and location of growth (Chapter 3), the requirement for “rules” governing the imposition of the charges (Chapter 7), asset management plan requirements under the D.C.A. (Chapter 8), and the proposed by-law to be made available as part of the approval process (Appendix D). In addition, the report is designed to set out sufficient background on the legislation, the County’s current D.C. policy (Chapter 2) and the policies underlying the proposed bylaw, to make the exercise understandable to interested parties. Finally, the D.C. Background Study addresses post-adoption implementation requirements (Chapter 9) which are critical to the successful application of the new policy. The chapters in the report are supported by Appendices containing the data required to explain and substantiate the calculation of the charge. A full discussion of the statutory requirements for the preparation of a background study and calculation of a D.C. is provided herein.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 1-2
1.2
Summary of the Process
Subsequent to the issuance of this report publicly, a public meeting required under Section 12 of the D.C.A., will be held. Its purpose is to present the study to the public and to solicit public input on the proposed D.C. by-law. The meeting will also be held to answer any questions regarding the study’s purpose and methodology. Figure 1-1 outlines the process undertaken to date and the proposed schedule to be followed with respect to the D.C. by-law adoption process. In accordance with the legislation, the D.C. Background Study will be posted on the County’s website no later than 60 days prior to by-law passage, and the study and proposed D.C. by-law will be made available for public review at least two weeks prior to the statutory public meeting. Following the statutory public meeting, the process to be followed in finalizing the report and recommendations includes: •
consideration of responses received prior to, at or immediately following the public meeting;
•
Council determination if any further public meetings are required on the matter;
•
finalization of the study and Council consideration of the by-law (prior to expiry of By-law 3205-2013, on March 6, 2018); and
•
imposition of the new development charges.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 1-3 Figure 1-1 Schedule of Key D.C. Process Dates Process Steps 1.
Project initiation meetings with senior staff
2.
Data collection, staff interviews, methodology review, preparation of D.C. calculations Preparation of draft D.C. Background Study and review of draft findings with senior staff Presentation of Draft D.C. Background Study and proposed D.C. By-law to Council D.C. Background Study and proposed D.C. By-law available to public (60 days prior to by-law passage)
3. 4. 5.
Dates July - August, 2017 August – November, 2017 November 20, 2017 November 30, 2017 December 4, 2017
6.
Presentation of D.C. Background Study to Stakeholders
December 5, 2017
7.
Statutory notice of Public Meeting advertisement placed in newspaper(s)
20 clear days prior to public meeting
8.
Public Meeting of Council
9.
January, 2018
Council considers adoption of D.C. Background Study and passage of by-law
10. Newspaper notice given of by-law passage 11. Last day for by-law appeal 12. County makes available D.C. pamphlet
Watson & Associates Economists Ltd.
At least 60 days after D.C. Background Study available to public By 20 days after passage 40 days after passage by 60 days after in force date
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 2-1
2. Current County of Prince Edward D.C. Policy 2.1
By-law Enactment
On March 5, 2013, the County of Prince Edward passed By-Law 3205-2013 under the D.C.A., 1997. The By-law came into effect on the day after passage and imposes uniform County-wide D.C.s by service for all permissible municipal services, with the exception of Water and Wastewater Services which are imposed under a Municipal Act Capital Charge. By-Law 3205-2013 was subsequently amended by By-Law 3069-2015 to add D.C.s for wind and solar and clarify definitions within the by-law, and By-Law 3759-2016 to extend the partial D.C. exemption for residential developments within the municipal water and wastewater service and for non-residential developments within the County.
2.2
Services Covered
The following services are included under By-law 3205-2013, as amended: County-Wide Services • • •
Services Related to Highways Fire Protection Services Outdoor Recreation Services
• •
Indoor Recreation Services Library Services
• •
Administration Services Homes for the Aged Services
•
Marinas and Boat Launch Services
The By-law provides for mandatory annual indexing of the charges on March 6th. Table 2-1 provides the charges currently in effect for residential and non-residential development types, as well as a breakdown of the charges by service.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 2-2 Table 2-1 County of Prince Edward Schedule of Current Development Charges RESIDENTIAL Service
Single and Single and Semi-Detached Semi-Detached Apartments - 2 Bedrooms + Dwelling Dwelling (>2 bedrooms) (=< 2 bedrooms)
NON-RESIDENTIAL
Apartments Other Multiples Other Multiples Bachelor and 1 (>2 bedrooms) (=< 2 bedrooms) Bedroom
Wind and Solar Energy Facilities
(per ft² of Gross Floor Area)
Municipal Wide Services: Services Related to Highways
2,971
2,087
2,385
1,645
2,641
2,087
2,971
2.46
Fire Protection Services
401
282
323
223
356
282
401
0.33
Outdoor Recreation Services
338
238
271
187
300
238
-
0.05
1,224
861
983
678
1,087
861
-
0.18
Library Serbvices
231
162
186
128
205
162
-
0.03
Administration
828
582
665
459
736
582
828
0.79
53
37
42
29
47
37
-
0.05
350
245
281
194
311
245
-
-
6,396
4,494
5,136
3,543
5,683
4,494
4,200
3.89
Indoor Recreation Services
Marinas and Boat Lauches Homes for the Aged Total Municipal Wide Services
2.3
Timing of D.C. Calculation and Payment
D.C. s are calculated, payable, and collected by the County at the time a building permit is issued for development.
2.4
Redevelopment Credit
The County’s current By-law provides D.C. credits where as a result of the redevelopment of land, a building or structure existing on land was or is to be demolished in whole or in part, or converted form one principal use to another principal use. A credit will only be issued where a building or structure existing on the same land within 5 years prior to the date of payment of D.C.s. D.C.s are payable for the dwelling units or additional non-residential floor area created in excess of what was demolished. In no case shall the net charge be less than zero.
2.5
Exemptions
The County’s D.C. By-Law includes statutory exemptions from payment of D.C.s with respect to: •
Industrial additions of up to and including 50% of the existing gross floor area of the building – for industrial additions which exceed 50% of the existing gross floor area, only the portion of the addition in excess of 50% is subject to the payment of D.C.s;
•
Land used for Municipal or Board of Education purposes; and
•
Residential development that results in only the enlargement of an existing dwelling unit, or that results only in the creation of up to two additional dwelling units (as specified by O.Reg. 82/98).
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 2-3 The By-Law also provides non-statutory exemptions from payment of D.C.s with respect to: • •
A non-residential farm building as defined in the Building Code Act; A place of worship;
• •
New Industrial development (excluding wind and solar energy facilities); Park Model Trailer conforming to National Standard of Canada CAN CSAZ241.0-92 or similar standard that is up to a maximum size of 50 square metres; A temporary building or structure;
• •
A reduction of 30% in D.C.s is allowed for the affordable housing, as defined in the by-law, for any residential dwelling unit for which the purchase price is at least 25% less than the average purchase price for the same type of residential dwelling unit in the County of Prince Edward and for any residential dwelling unit where the monthly rent is at or below the maximum affordable monthly rent amount established by the Residential Rental Standers board for the Province of Ontario; and
•
Reduction of D.C.s to Encourage Growth in Specific Areas • 50% reduction for residential development occurring in fully or partially serviced areas •
50% reduction for all non-residential development.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 3-1
3. Anticipated Development in the County of Prince Edward 3.1
Requirements of the Act
Chapter 4 provides the methodology for calculating a D.C. as per the D.C.A. Figure 4-1 presents this methodology graphically. It is noted in the first box of the schematic that in order to determine the D.C. that may be imposed, it is a requirement of section 5(1) of the D.C.A. that, “the anticipated amount, type and location of development, for which D.C.s can be imposed, must be estimated.” The growth forecast contained in this chapter (with supplemental tables in Appendix A) provides for the anticipated development for which the County of Prince Edward will be required to provide services, over a 10-year (2018 – 2028), 20-year (2018 – 2038), and buildout time horizon.
3.2
Basis of Population, Household and Non-Residential Gross Floor Area Forecast
The D.C. growth forecast has been derived based on extensive discussions with County staff regarding historical and anticipated development trends, phasing, land availability and market demand. In compiling the growth forecast, the following reports were also consulted to help assess residential and non-residential development potential for Prince Edward County over the forecast period, including: •
Prince Edward County, 2013 D.C. Background Study;
•
Prince Edward County, 2013 D.C. Statutory Review and Growth Options Study;
•
2001, 2006, 2011, and 2016 residential Census data;
• •
2001, 2006, and 2011 Census employment data; A review of residential and non-residential land supply;
•
A review of historical residential (permanent and seasonal) and nonresidential development activity over the past 10 years; and
•
Ontario Ministry of Agriculture, Food and Rural Affairs (O.M.A.F.R.A) EMSI Analyst, 2011-2017 (Q1 2017 employment data set).
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 3-2
3.3
Summary of Growth Forecast
A detailed analysis of the residential and non-residential growth forecast is provided in Appendix A. The discussion provided herein summarizes the anticipated growth for the County and describes the basis for the forecast. The results of the residential growth forecast analysis are summarized in Figure 3-1 below, and Schedule 1 in Appendix A. Figure 3-1 Household and Population Forecast Model DEMAND
SUPPLY
Residential Units in the Development Process Historical Housing Construction Intensification
Employment Market by Local Municipality, Economic Outlook Local , Regional and Provincial
Forecast of Residential Units Designated Lands
Servicing Capacity
Occupancy Assumptions
Gross Population Increase
Decline in Existing Population
Net Population Increase
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 3-3 As identified in Table 3-1 and Schedule 1, Prince Edward County’s population is anticipated to reach approximately 26,214 by 2028, 27,430 by 2038, and 34,900 by buildout. 1 This represents an increase of 1,330 persons, 2,545 persons, and 10,015 persons over the 10-year, 20-year, and buildout forecast period, respectively. The County’s seasonal population 2 is forecast to increase to 10,205 in 2028, 12,125 in 2038, and 18,860 by buildout. The County’s total population (permanent and seasonal population) is forecast to reach 35,730 by 2028, 38,835 by 2038, and 52,840 by buildout. Provided below is a summary of the key assumptions and findings regarding Prince Edward County’s D.C. growth forecast. 1. Unit Mix (Appendix A – Schedules 1 through 7) •
The unit mix for the County was derived from the 2013 Growth Options Study, a review of historical development activity, a review of designated urban land supply, (as per Schedule 6 & 7) and discussions with planning staff regarding anticipated development trends for the County.
•
Based on the above, the 20-year (2018-2038) household growth forecast is comprised of a housing unit mix of approximately 76% low density (single detached and semi-detached), 14% medium density (multiples except apartments) and 10% high density (bachelor, 1 bedroom and 2+ bedroom apartments).
2. Geographic Location of Residential Development (Appendix A – Schedule 2) •
Schedule 2 summarizes the anticipated amount, type, and location of development for Prince Edward County by development location. The percentage of forecast housing growth between 2018 and 2038 by settlement area and remaining rural area is provided on the following page.
1
Population excludes Census undercount of approximately 4% Seasonal population defined as population in units which are not permanently occupied on a year-round basis (i.e. cottages and resort-related residential units). Seasonal population estimated using an average PPU (persons per unit) of 3.66.
2
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 3-4 Housing Growth (Units)
%
Picton (Fully Serviced)
346
21%
Wellington (Fully Serviced)
560
34%
Urban Sub Total (Fully Serviced)
906
55%
Bloomfield (Water Only)
37
2%
Rossmore (Water Only)
16
1%
Concsecon/Carrying Place (Water Only)
14
1%
Ameliasburg (Water Only)
7
< 1%
Urban Subtotal (Water Only)
74
4%
Rural
652
40%
Total County-wide forecast
1,632
100%
3. Seasonal Development and Population (Appendix A – Schedule 2) • Seasonal development activity within Prince Edward County over the 20year forecast period is allocated in Schedule 2, and is comprised of 1,270 new seasonal units.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 3-5 Table 3-1 County of Prince Edward Residential Growth Forecast Summary Housing Units
Incremental
Forecast
Historical
Year
Population1
Population Excluding Institutional Population¹
Institutional Population
Seasonal Population
Total Permanent and Seasonal Singles & SemiPopulation¹ Detached
Multiple Dwellings2
Apartments
3
Total Households
Other
Seasonal Households
Total Households + Seasonal Households
Personal Per Unit (PPU) with Seasonal
Person Per Unit (PPU)
Mid 2001
24,901
611
24,290
4,795
29,085
8,745
270
735
120
9,870
1,310
11,180
2.52
2.66
Mid 2006
25,496
741
24,755
5,636
30,391
9,115
325
735
120
10,295
1,540
11,835
2.48
2.63
Mid 2011
25,258
653
24,605
5,966
30,571
9,340
345
710
155
10,550
1,630
12,180
2.39
2.56
Mid 2016
24,735
635
24,100
7,148
31,248
9,465
340
755
165
10,725
1,953
12,678
2.31
2.51
Early 2018
24,886
654
24,231
7,475
31,706
9,575
349
755
165
10,844
2,043
12,887
2.29
2.51
Early 2028
26,214
689
25,524
10,205
35,729
10,215
494
802
165
11,676
2,788
14,464
2.25
2.52
Early 2038
27,430
721
26,709
12,125
38,834
10,820
581
909
165
12,476
3,313
15,789
2.20
2.51
Buildout
34,900
918
33,982
18,860
52,842
13,422
1,108
1,247
165
15,942
5,153
21,095
2.19
2.55
Mid 2001 - Mid 2006
595
130
465
841
1,306
370
55
0
0
425
230
655
-0.05
-0.03
Mid 2006 - Mid 2011
-238
-88
-150
330
180
225
20
-25
35
255
90
345
-0.08
-0.07
Mid 2011 - Mid 2016
-523
-18
-505
1,182
677
125
-5
45
10
175
323
498
-0.09
-0.05
Mid 2016 - Early 2018
151
19
131
327
458
110
9
0
0
119
90
209
0
0
Early 2018 - Early 2028
1,328
35
1,293
2,730
4,023
640
145
47
0
832
745
1,577
0
0
Early 2018 - Early 2038
2,544
67
2,477
4,650
7,127
1,245
232
154
0
1,632
1,270
2,902
0
0
Early 2018 - Buildout 10,014 263 Source: Watson & Associates Economists Ltd., 2017. 1. Population excludes Census Undercount of approximately 4%. 2. Includes townhomes and apartments in duplexes. 3. Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
9,751
11,385
21,136
3,847
759
492
0
5,098
3,110
8,208
0
0
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 3-6 4. Planning Period •
Short- and longer-term time horizons are required for the D.C. process. The D.C.A. limits the planning horizon for certain services, such as parks, recreation and libraries, to a 10-year planning horizon. Roads, fire and other hard services utilize a longer forecast period.
5. Population in New Units (Appendix A – Schedules 3 through 8) • The number of housing units to be constructed in Prince Edward County during the planning periods is presented on Figure 3-2. Over the 20-year term (2018-2038) forecast period, the County is anticipated to average approximately 146 new permanent and seasonal housing units per year. •
Population in new units is derived from Schedules 3, 4, and 5, which incorporates historical development activity, anticipated units (see unit mix discussion) and average persons per unit by dwelling type for new units.
•
Schedule 8 summarizes the average number of persons per unit (P.P.U.) for new housing units by age and type of dwelling, based on 2011 custom Census data for Prince Edward County. The 20-year average P.P.U.s by dwelling type are as follows: • •
Low density: Medium density:
2.56 1.47
•
High density:
1.35
6. Existing Units and Population Change (Appendix A – Schedules 3 through 5) •
•
Existing households as of 2018 are based on the 2016 Census households, plus estimated residential units constructed between 2016 and 2017, assuming a 6-month lag between construction and occupancy (see Schedule 3). The decline in average occupancy levels for existing housing units is calculated in Schedules 3 through 5, by aging the existing population over the forecast period. The forecast population decline in existing households over the 2018 to 2038 forecast period is estimated at approximately 1,295.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 3-7 Figure 3-2 County of Prince Edward Annual Housing Forecast 300
246
250
Housing Units
200
188 176
174
174
174
174 164
150
164
164
164
164 149
145 140
100
135
131
86 83
78
50
0
Years Historical
Watson & Associates Economists Ltd.
Low Density
Medium Density
High Density
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Seasonal
Historical Average
149
149
149
149
Page 3-8 7. Employment (Appendix A – Schedules 10 through 12) •
•
1
Employment projections are largely based on the activity rate method, which is defined as the number of jobs in Prince Edward County divided by the number of residents. Key employment sectors include primary, industrial, commercial/ population-related, institutional and work-at-home, which are considered individually below. The County’s 2011 1 employment base by place of work is outlined in Schedule 10. The 2011 employment base is comprised of the following sectors: • 420 primary (approx. 6%); • •
1,185 work-at-home employment (approx. 18%); 888 industrial (approx. 14%);
• •
2,198 commercial (approx. 34%); and 1,785 institutional (approx. 28%).
•
The 2011 employment base by usual place of work, including work at home, is approximately 6,475 jobs.
•
The County’s 2018 employment base is estimated at 7,215 based on a review of non-residential development and employment growth trends between 2011 and 2017. Prince Edward County’s employment base is anticipated to reach 7,980 by 2028, 8,750 by 2038, and 11,085 at buildout.
•
Schedule 10b, Appendix A, summarized the employment forecast, excluding work at home employment, which is the basis for the D.C.A. employment forecast. The impact on the County’s services from work at home employees has already been included in the population forecast. Accordingly, work at home employees have been removed from the D.C.A. employment forecast calculations.
•
Total employment for Prince Edward County (excluding work at home employment) is anticipated to reach approximately 6,590 by 2028, 7,265 by 2038, and 9,240 at buildout. This represents an employment increase of approximately 615, 1,290, and 3,265 additional jobs over the 10-year, 20-year, and buildout periods, respectively.
2011 employment based on Statistics Canada custom employment data.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 3-9 8. Non-Residential Sq.ft. Estimates ((Gross Floor Area (G.F.A.), Appendix A – Schedule 10b) •
Square footage estimates were calculated in Schedule 10b based on the following employee density assumptions: • •
•
•
1,100 sq.ft. per employee for industrial; 500 sq.ft. per employee for commercial; and
• 700 sq.ft. per employee for institutional employment. The County-wide incremental non-residential G.F.A. increase is anticipated to be approximately 403,000 sq.ft. over the 10-year forecast period, 853,000 sq.ft. over the 20-year forecast period, and 2,143,000 sq.ft. over the buildout forecast period. In terms of percentage growth, the 20-year incremental G.F.A. forecast by sector is broken down as follows: • industrial – approx. 42%; • •
commercial – approx. 44%; and institutional – approx. 14%.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 4-1
4. The Approach to the Calculation of the Charge This chapter addresses the requirements of s.s.5(1) of the D.C.A., 1997 with respect to the establishment of the need for service which underpins the D.C. calculation. These requirements are illustrated schematically in Figure 4-1.
4.1
Services Potentially Involved
Table 4-1 lists the full range of municipal service categories which are provided within the County. A number of these services are defined in s.s.2(4) of the D.C.A., 1997 as being ineligible for inclusion in D.C.s. These are shown as “ineligible” on Table 4-1. In addition, two ineligible costs defined in s.s.5(3) of the D.C.A. are “computer equipment” and “rolling stock with an estimated useful life of [less than] seven years...” In addition, certain roads and stormwater management services covered separately under subdivision and consent agreements are excluded from D.C. calculations as local services. Moreover, the capital costs of water and wastewater services related to development are recovered for under a separate Municipal Act Capital Charges By-law. Services which are potentially eligible for inclusion in the County’s D.C. are indicated with a “Yes”. The D.C.A allows municipalities to define services for inclusion in the by-law. In discussions with County staff it was determined that services previously defined as Outdoor Recreation Services, and Indoor Recreation Services, would be combined more broadly and defined as Parks and Recreation Services. Moreover, new services have been considered in this D.C. Background Study for Waste Diversion Services and Municipal Parking Services.
4.2
Increase in Need for Service
The D.C. calculation commences with an estimate of “the increase in the need for service attributable to the anticipated development,” for each service to be covered by the By-Law. There must be some form of link or attribution between the anticipated development and the estimated increase in the need for service. While the need could conceivably be expressed generally in terms of units of capacity, s.s.5(1)3, which requires that municipal council indicate that it intends to ensure that such an increase in
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 4-2 need will be met, suggests that a project-specific expression of need would be most appropriate. In order for an increase in need for service to be included in the D.C. calculation, municipal council must indicate “...that it intends to ensure that such an increase in need will be met” (s.s.5(1)3). This can be done if the increase in service forms part of a Council-approved Official Plan, capital forecast or similar expression of the intention of Council (O.Reg. 82/98 s.3). The capital program contained herein reflects the County’s approved and proposed capital budgets and master servicing/needs assessments.
4.3
Local Service Policy
Some of the need for services generated by additional development consists of local services related to a plan of subdivision or consent agreement. As such, they will be required to be emplaced (or funded) directly by developers as a condition of subdivision agreements or consent conditions. This precludes these works from being included in the calculation of a development charge. The County’s general policy guidelines on D.C. and local service funding is detailed in Appendix E to this report.
4.4
Capital Forecast
Paragraph 7 of s.s.5(1) of the D.C.A. requires that, “the capital costs necessary to provide the increased services must be estimated.” The Act goes on to require two potential cost reductions and the Regulation sets out the way in which such costs are to be presented. These requirements are outlined below. These estimates involve capital costing of the increased services discussed above. This entails costing actual projects or the provision of service units, depending on how each service has been addressed. The capital costs include: a) b) c) d)
costs to acquire land or an interest therein (including a leasehold interest); costs to improve land; costs to acquire, lease, construct or improve buildings and structures; costs to acquire, lease or improve facilities including rolling stock (with a useful life of 7 or more years), furniture and equipment (other than computer equipment), materials acquired for library circulation, reference or information purposes; e) interest on money borrowed to pay for the above-referenced costs; f) costs to undertake studies in connection with the above-referenced matters; and g) costs of the D.C. background study. Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 4-3 Figure 4-1 The Process of Calculating a D.C. under the Act The Process of Calculating a Development Charge under the Act that must be followed Anticipated Development 1. Tax Base, User Rates, etc.
2. Ineligible Services
Estimated Increase in Need for Service 3. Subdivision Agreements and Consent Provisions
Non-Transit Services Historic Service Standard 4a.
Ceiling Re: Increased Need 4.
8. Specified Local Services
Transit Services Forward-looking Service Standard 4b.
Needs That Will Be Met 5.
D.C. Needs By Service Examination of the Long-term Capital and Operating Costs for Capital Infrastructure 6.
9.
Non-Transit Services “Financially Sustainable” 7a.
Asset Management Plan for All Capital Projects to be Funded by D.C.s 7. Transit Services “Detailed Requirements” 1
2
3
4
7b.
Less: Uncommitted Excess Capacity
10.
Less: Benefit To Existing Development
11.
Less: Grants, Subsidies and Other Contributions
12.
Less: 10% Where Applicable 13.
D.C. Net Capital Costs
Financing, Inflation and Investment Considerations
Costs for new development vs. existing development for the term of the by-law and the balance of the period
14. D.C. By-law(s) Spatial Applicability 16.
15. Amount of the Charge By Type of Development (including apportionment of costs residential and non-residential) 17.
Watson & Associates Economists Ltd.
Consideration of exemptions, phase-ins, etc.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 4-4 Table 4-1 Categories of Municipal Services To Be Addressed as Part of the Calculation Categories of Municipal Services
1. Services Related to a Highway
Eligibility for Inclusion in the D.C. Calculation 1.1 1.2
Arterial roads Collector roads
100 100
1.3 1.4 1.5
Local roads Intersections and Traffic signals Sidewalks and streetlights
100 100 100
n/a n/a n/a
2.1 2.2 2.3
100 100 90
Yes
2.4
Yes Yes n/a n/a
2.5 2.6 2.7 2.8
Transit vehicles Other transit infrastructure Municipal parking spaces indoor Municipal parking spaces outdoor Works Yards Rolling stock 1 Ferries Airport facilities
Local Service
3.1
100
Local Service Local Service
3.2 3.3
Main channels and drainage trunks Channel connections Retention/detention ponds
Yes Yes
4.1 4.2
100 100
Yes
4.3
Fire stations Fire pumpers, aerials and rescue vehicles Small equipment and gear
Ineligible
5.1
Yes
5.2
4. Fire Protection Services 5. Parks and Recreation Services
Maximum Potential D.C. Recovery %
Yes Yes/Local Service Local Service Yes Yes
2. Other Transportation Services
3. Storm Water Drainage and Control Services
Service Components
Acquisition of land for parks, woodlots and E.S.A.s Development of area municipal, district, and special purpose parks
1with
7+ year life time percentage as service component to which it pertains computer equipment excluded throughout
2same
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
90 100 100 90 90
100 100
100 0 90
Page 4-5 Categories of Municipal Services
Eligibility for Inclusion in the D.C. Calculation
Service Components
Maximum Potential D.C. Recovery %
Yes
5.3
Yes
5.4
Yes
7.1
Yes
7.2
Public library space (incl. furniture and equipment) Library materials
7. Electrical Power Services
Ineligible Ineligible Ineligible
8.1 8.2 8.3
Electrical substations Electrical distribution system Electrical system rolling stock1
0 0 0
8. Provision of Cultural, Entertainment and Tourism Facilities and Convention Centres
Ineligible
9.1
0
Ineligible
9.2
Cultural space (e.g. art galleries, museums and theatres) Tourism facilities and convention centres
9. Waste Water Services
Municipal Act Municipal Act Municipal Act
10.1 Treatment plants 10.2 Collection systems 10.3 Local systems
100 100 100
10. Water Supply Services
Municipal Act Municipal Act Municipal Act
11.1 Treatment plants 11.2 Distribution systems 11.3 Local systems
100 100 100
11. Waste Management Services
Yes
6. Library Services
Arenas, indoor pools, fitness facilities, community centres, etc. (including land) Parks and Recreation rolling stock1 and yards
90
90 90 90
0
Yes
12.1 Collection, transfer vehicles and equipment related to diversion 12.3 Landfills and incineration facilities and vehicles 12.3 Other waste diversion facilities
12. Police Services
n/a n/a n/a
13.1 Police detachments 13.2 Police rolling stock1 13.3 Small equipment and gear
100 100 100
13. Homes for the Aged
yes
14.1 Homes for the aged space
90
14. Day Care
n/a
15.1 Day care space
90
15. Health
n/a
16.1 Health department space
90
Ineligible
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
90 0 90
Page 4-6 Categories of Municipal Services
Eligibility for Inclusion in the D.C. Calculation
Service Components
Maximum Potential D.C. Recovery %
16. Social Services
n/a
17.1 Social service space
90
17. Ambulance
n/a n/a
18.1 Ambulance station space 18.2 Vehicles1
90 90
18. Hospital Provision
Ineligible
19.1 Hospital capital contributions
0
19. Provision of Headquarters for the General Administration of Municipalities and Area Municipal Boards
Ineligible Ineligible Ineligible
20.1 Office space (all services) 20.2 Office furniture 20.3 Computer equipment
0 0 0
20. Other Services
Yes
Yes
21.1 Studies in connection with acquiring buildings, rolling stock, materials and equipment, and improving land2 and facilities, including the D.C. background study cost 21.2 Interest on money borrowed to pay for growth-related capital
Eligibility for Inclusion in the DC Calculation
Yes No n/a Ineligible
0-100
0-100
Description Municipality provides the service - service has been included in the DC Calculation Municipality provides the service - service has not been included in the DC Calculation Municipality does not provide the service Service is ineligible for inclusion in the DC calculation
1with
7+ year life time percentage as service component to which it pertains computer equipment excluded throughout
2same
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 4-7
4.5
Treatment of Credits
Section 8 para. 5 of O.Reg. 82/98 indicates that a D.C. background study must set out, “the estimated value of credits that are being carried forward relating to the service.” s.s.17 para. 4 of the same Regulation indicates that, “...the value of the credit cannot be recovered from future D.C.s,” if the credit pertains to an ineligible service. This implies that a credit for eligible services can be recovered from future D.C.s. As a result, this provision should be made in the calculation, in order to avoid a funding shortfall with respect to future service needs. The County currently has no outstanding credit obligations.
4.6
Eligible Debt and Committed Excess Capacity
Section 66 of the D.C.A., 1997 states that for the purposes of developing a D.C. by-law, a debt incurred with respect to an eligible service may be included as a capital cost, subject to any limitations or reductions in the Act. Similarly, s.18 of O.Reg. 82/98 indicates that debt with respect to an ineligible service may be included as a capital cost, subject to several restrictions. In order for such costs to be eligible, two conditions must apply. First, they must have funded excess capacity which is able to meet service needs attributable to the anticipated development. Second, the excess capacity must be “committed,” that is, either before or at the time it was created, Council must have expressed a clear intention that it would be paid for by D.C.s or other similar charges. For example, this may have been done as part of previous D.C. processes. The County currently has outstanding debt payments related to the replacement and expansion of the Wellington Arena, which are included in the calculation of the D.C. for Parks and Recreation Services. Furthermore, capital costs for previous expansions to the provision of Fire facilities has been included as ‘committed excess capacity’ in the anticipated capital needs for Fire Protection Services.
4.7
Existing Reserve Funds
Section 35 of the D.C.A. states that: “The money in a reserve fund established for a service may be spent only for capital costs determined under paragraphs 2 to 8 of subsection 5(1).”
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 4-8 There is no explicit requirement under the D.C.A. calculation method set out in s.s.5(1) to net the outstanding reserve fund balance as part of making the D.C. calculation; however, s.35 does restrict the way in which the funds are used in future. The County’s projected uncommitted D.C. reserve fund balances, by service, as at December 31, 2017 are presented in Table 4-2. Projected balances account for required draws for completed D.C. eligible projects and anticipated D.C. collections to December 31, 2017. These balances have been applied against future spending requirements for all services. Table 4-2 County of Prince Edward Projected Uncommitted D.C. Reserve Funds Balances (December 31, 2017) Service Transportation Fire Protection Marinas and Boat Launches Parks and Recreation Library Administration (Studies) Homes for the Aged Waste Diversion Municipal Parking Total
4.8
Total 3,542,706 (675,308) 70,303 722,126 189,265 514,071 370,743 4,733,904
Deductions
The D.C.A., 1997 potentially requires that five deductions be made to the increase in the need for service. These relate to: • •
the level of service ceiling; uncommitted excess capacity;
• •
benefit to existing development; anticipated grants, subsidies and other contributions; and
•
a 10% reduction for certain services.
The requirements behind each of these reductions are addressed as follows:
4.8.1 Reduction Required by Level of Service Ceiling This is designed to ensure that the increase in need for services does “…not include an increase that would result in the level of service (for the additional development Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 4-9 increment) exceeding the average level of the service provided in the County over the 10-year period immediately preceding the preparation of the background study…” O.Reg. 82/98 (s.4) goes further to indicate that, “…both the quantity and quality of a service shall be taken into account in determining the level of service and the average level of service.” Moreover, the D.C.A., 1997 does not require this historical level of service calculation for transit services. As per subsection 5.2(3) of the D.C.A., “…the estimate for the increase in the need for a prescribed service (i.e. transit services) shall not exceed the planned level of service over the 10-year period immediately following the preparation of the background study…”. In many cases this can be done by establishing a quantity measure in terms of units as floor area, land area or road length per capita, and a quality measure in terms of the average cost of providing such units based on replacement costs, engineering standards or recognized performance measurement systems, depending on circumstances. When the quantity and quality factor are multiplied together, they produce a measure of the level of service, which meets the requirements of the Act, i.e. cost per unit. The average service level calculation sheets for each service component in the D.C. calculation are set out in Appendix B.
4.8.2 Reduction for Uncommitted Excess Capacity Paragraph 5 of s.s.5(1) requires a deduction from the increase in the need for service attributable to the anticipated development that can be met using the County’s “excess capacity,” other than excess capacity which is “committed” (discussed above in 4.5). “Excess capacity” is undefined, but in this case must be able to meet some or all of the increase in need for service, in order to potentially represent a deduction. The deduction of uncommitted excess capacity from the future increase in the need for service, would normally occur as part of the conceptual planning and feasibility work associated with justifying and sizing new facilities, e.g. if a road widening to accommodate increased traffic is not required because sufficient excess capacity is already available, then widening would not be included as an increase in need, in the first instance.
4.8.3 Reduction for Benefit to Existing Development This step involves a further reduction to the need, by the extent to which such an increase in service would benefit existing development. The level of services cap is related, but is not the identical requirement. Wastewater (sanitary), stormwater and Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 4-10 water trunks are highly localized to growth areas and can be more readily allocated in this regard than other services such as roads which do not have a fixed service area. Where existing development has an adequate service level which will not be tangibly increased by an increase in service, no benefit would appear to be involved. For example, where expanding existing library facilities simply replicates what existing residents are receiving, they receive very limited (or no) benefit as a result. On the other hand, where a clear existing service problem is to be remedied, a deduction should be made accordingly. In the case of services such as recreation facilities, community parks, libraries, etc., the service is typically provided on a municipal-wide system basis. For example, facilities of the same type may provide different services (i.e. leisure pool vs. competitive pool), different programs (i.e. hockey vs. figure skating) and different time availability for the same service (i.e. leisure skating available on Wednesday in one arena and Thursday in another). As a result, residents will travel to different facilities to access the services they want at the times they wish to use them, and facility location generally does not correlate directly with residence location. Even where it does, displacing users from an existing facility to a new facility frees up capacity for use by others and generally results in only a very limited benefit to existing development. Further, where an increase in demand is not met for a number of years, a negative service impact to existing development is involved for a portion of the planning period.
4.8.4 Reduction for Anticipated Grants, Subsidies and Other Contributions This step involves reducing the capital costs necessary to provide the increased services by capital grants, subsidies and other contributions made or anticipated by Council and in accordance with various rules such as the attribution between the share related to new vs. existing development O.Reg. 82/98, s.6. Where grant programs do not allow funds to be applied to growth-related capital needs, the proceeds can be applied to the non-growth share of the project exclusively. Moreover, Gas Tax revenues are typically used to fund non-growth-related works or the non-growth share of D.C. projects, given that the contribution is not being made in respect of particular growth-related capital projects.
4.8.5 The 10% Reduction Paragraph 8 of s.s.(1) of the D.C.A. requires that, “the capital costs must be reduced by 10 percent.” This paragraph does not apply to water supply services, wastewater services, stormwater drainage and control services, services related to a highway, Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 4-11 police, fire protection services, and transit services. The primary services that the 10% reduction does apply to include services such as parks and recreation, libraries, childcare/social services, ambulance, homes for the aged and health. The 10% is to be netted from the capital costs necessary to provide the increased services, once the other deductions have been made, as per the infrastructure cost sheets in Chapter 5.
4.9
D.C. By-Law Spatial Applicability
There are four basic choices to be addressed when considering the geographic application of a D.C.: 1. the entire municipality for all services (which is the most commonly-used approach); 2. part of the municipality for all services; balance of the municipality is exempt (because it is outside the service’s coverage area or can be served at little or no incremental cost); 3. different by-laws and charges in different municipal service areas (in order to recognize distinctly different servicing cost situations); and 4. a uniform municipal-wide charge with separate charge covering additional areaspecific services (e.g. the coverage area for specific works). Subsection 2(9) of the D.C.A. may prescribe services for which a D.C. by-law must apply on an area-specific basis. For prescribed services, Council shall pass different D.C. by-laws for different parts of the municipality, in accordance with the prescribed criteria. Currently the Province has not prescribed services under this subsection of the D.C.A. For services that are not prescribed under s.s. 2(9) of the D.C.A., the background study must give consideration of the use of more than one D.C. by-law to reflect different needs for services in different areas. Area-specific charges have been reviewed with County staff as part of the Implementation Policy Review, as contained in Appendix F. Recognizing the system-wide nature of services included in the County’s D.C. By-Law and current preference for uniform funding in other mechanisms (e.g. water and wastewater rates), in part to provide equity across constituents, no changes are currently recommended to the County’s uniform D.C. policies.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 5-1
5. D.C. Eligible Cost Analysis by Service This chapter outlines the basis for calculating D.C. eligible costs to be applied on a County-wide uniform basis for all services. The required calculation process set out in s.5(1) paragraphs 2 to 8 in the D.C.A., 1997, and described in Chapter 4, was followed in determining D.C. eligible costs. The nature of the capital projects and timing identified in this chapter reflects Council’s current intention. However, over time, municipal projects and Council priorities change and, accordingly, Council’s intentions may alter and different capital projects (and timing) may be required to meet the need for services required by new growth.
5.1
Service Levels and 10-Year Capital Costs for County-wide D.C. Calculation
This section evaluates the development-related capital requirements for select services over the 10-year planning period (2018-2027). For these services, each service component is evaluated on two format sheets: the average historical 10-year level of service calculation (see Appendix B), which “caps” the D.C. amounts; and the infrastructure cost calculation, which determines the potential D.C. recoverable cost.
5.1.1 Marinas and Boat Launches The County currently has 17 marina locations including boat launches, docks, washrooms, and boardwalks. In total, the inventory of Marina and Boat Launches assets provides a historic average level of service of approximately $63 per capita. The historical level of investment in Marinas and Boat Launches provides for a D.C.-eligible amount over the forecast period of approximately $254,000. The County will require funds related to the municipal cost share of two boardwalk projects. In total, the gross capital cost estimates for the municipal cost share of the increase in need for service, totals $427,000. After deductions of $102,000 for the benefit to development beyond the 10-year period, and $32,000 for the statutory 10% deduction, the net D.C. eligible costs total $288,000. Accounting for $70,000 related to D.C.s already collected towards these needs, the total D.C. eligible capital costs that have been included in the calculation of the charge is $222,000. The allocation of net growth-related costs for Marinas and Boat Launches between residential, and non-residential development is 87% and 13% respectively, reflective of the incremental growth in population and employment over the forecast period. Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 5-2
5.1.2 Parks and Recreation Services The County currently maintains approximately 151 acres of developed parkland, and 133 parkland amenities (including trails, playground equipment, changerooms, etc.). Furthermore, the County utilizes 184,000 sq.ft. of indoor recreation facility space in providing parks and recreation services. To assist in the provision of services through the aforementioned facilities, parks, and trails inventory, the County utilizes 16 vehicle and equipment items. The County’s level of service over the historic 10-year period averaged $1,347 per capita. In total, the maximum D.C.-eligible amount for Parks and Recreation Services over the 10-year forecast period is approximately $5.4 million based on the established level of service standards. The 10-year capital needs for Parks and Recreation Services to accommodate growth have a total gross capital cost of approximately $16.5 million. These capital needs are comprised of future parkland and trail development, additional indoor recreation space needs, and additional parks maintenance vehicles. Furthermore, the future debt payments related to the Wellington Arena/Replacement have also been included. Approximately $12.9 million has been deducted to reflect the benefit to the existing of the identified projects, and a further $291,000 has been deducted to account for a portion of the Wellington Arena debt payment related to an increase in level of service at the time of construction. The statutory 10% deduction applicable for recreation and parks services totals $287,000 and approximately $722,000 has been deducted from the D.C. recoverable capital costs recognizing the existing reserve fund balance. This results in net growth-related capital costs for inclusion in the D.C. calculation of approximately $2.4 million. As the predominant users of parks and recreation services tend to be residents of the County, the forecast growth-related costs have been allocated 95% to residential development and 5% to non-residential development.
5.1.3 Library Services Library services are provided by the County through the provision of approximately 20,400 sq.ft. of facility space and 58,000 library collection material items. The average level of service provided over the historical 10-year period based on this inventory is $199 per capita. When applied to anticipated growth over the 2018-2027 period, the per capita level of service produces a maximum D.C. eligible amount for Library Services of approximately $799,000.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 5-3 The gross capital costs included in the D.C. calculation for the 10-year forecast period total $1.5 million. The capital cost estimates include an Expansion to the Picton Library branch and a provision for additional collection items. Deductions for the benefit to existing development total $395,000 reflective of improvements to the existing space within the Picton Library branch and a change in the provision of services benefitting existing development. A further $399,000 has been deducted to reflect the expansion of the library for uses not related to Library Services. To the extent that this additional space is used for Library Services in the future, it may be eligible for inclusion in a future D.C. Background Study. Furthermore, deductions of approximately $65,000 for the required 10% statutory deduction have also been applied. There is a current reserve fund balance of $189,000, when applied results in a net D.C. recoverable capital cost of $393,000 which has been included in the D.C. calculation. Similar to Parks and Recreation Services, the predominant users of library services tend to be residents of the County, as such the forecast growth-related costs have been allocated 95% to residential development and 5% to non-residential development.
5.1.4 Administration (Studies) The D.C.A. permits the inclusion of studies undertaken to facilitate the completion of the County’s capital works program and the D.C. Background Study. The County has made provision for the inclusion of new studies undertaken to facilitate future D.C. processes, as well as other studies which benefit future growth, including, master plans (e.g. Recreation Master Plan) and planning studies (e.g. Secondary Plans, Official Plan Update, and Comprehensive Zoning By-law). The gross capital cost estimates for these studies total approximately $2.2 million over the 10-year forecast period. Approximately $817,000 has been deducted in recognition of the benefits to the existing population, and approximately $514,000 has been deducted for existing reserve fund balances. Applying the 10% statutory deduction, the net growth-related capital costs included in the calculation of the charge totals approximately $635,000. These costs have been allocated 87% to residential development, and 13% to nonresidential development based on the incremental growth in population to employment for the 10-year forecast period.
5.1.5 Homes for the Aged The County currently provides Homes for the Aged Services through the provision of 84 beds within 31,100 sq.ft. of facility space. The average level of service provided over Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 5-4 the historical 10-year period based on this inventory is $504 per capita. When applied to anticipated growth over the 2018-2027 period, the per capita level of service produces a maximum D.C. eligible amount for Homes for the Aged of approximately $2.0 million. The gross capital cost included in the D.C. calculation for the 10-year forecast period is $7.3 million for a 44-bed expansion to the existing facility. It is anticipated that the increase in service will benefit growth over the 20-year forecast period, and as such $1.2 million has been deducted to reflect the benefits to development beyond the 10year planning period. Deductions for the benefit to existing development total $4.6 million. Furthermore, deductions of approximately $459,000 for anticipated grants and $110,000 for the required 10% statutory deduction and have also been applied. There is a current reserve fund balance of $371,000 when applied to growth-related increase in need results in a net D.C. recoverable capital cost of $615,000 which has been included in the D.C. calculation. The D.C. eligible capital costs for Homes for the Aged Services have allocated entirely to residential development due to the nature of the demand for services.
5.1.6 Waste Diversion Services The County currently provides Waste Diversion Services through a contracted service arrangement. There are currently three transfer stations related to waste diversion, that provide an average level of service over the 10-year historical period of approximately $1 per capita. When applied to anticipated growth over the 2018-2027 period, the per capita level of service produces a maximum D.C. eligible amount for Waste Diversion Services of $5,000. The County does not currently anticipate any growth related capital needs over the 2017-2028 forecast period. However, the service has been included within the D.C. Background Study to provide a basis for consideration in future studies, should the County’s provision for this service change.
5.1.7 Municipal Parking Services The County currently provides Municipal Parking Services through the provision of 192 off-street parking spaces. The average level of service provided over the historical 10year period based on this inventory is $39 per capita. When applied to anticipated growth over the 2018-2027 forecast period, the per capita level of service produces a maximum D.C. eligible amount for Municipal Parking Services of $155,000. Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 5-5 The County anticipates adding 219 off-street parking spaces within five parking lots over the 2018-2027 forecast period. The gross capital costs included in the D.C. calculation for these needs totals $1.4 million. After deducting $1.2 million reflective of increases in current level of service and benefits to development beyond 2028, and $15,000 deduction for the statutory 10% deduction, approximately $139,000 in D.C. eligible capital costs have been included in the calculation of the charge. These costs have been allocated 87% to residential development, and 13% to nonresidential development based on the incremental growth in population to employment for the 10-year forecast period.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 5-6 Infrastructure Costs Covered in the D.C. Calculation – Marinas and Boat Launches Services Less:
Prj.No
1
2
Increased Service Needs Attributable to Anticipated Development
2018-2027 Tip of the Bay Boardwalk Easement (municipal cost share) Picton Bay Motel Boardwalk Easement (municipal cost share) Reserve Fund Adjustment
Total
Watson & Associates Economists Ltd.
Gross Capital Cost Timing (year) Estimate (2018$)
Post Period Benefit
Net Capital Cost
Less:
Grants, Subsidies and Benefit to Other Existing Contributions Development Attributable to New Development
Subtotal
Other (e.g. 10% Statutory Deduction)
Potential DC Recoverable Cost
Total
Residential Share
NonResidential Share
87%
13%
2018-2027
250,000
60,209
189,791
-
189,791
18,979
170,812
148,606
22,206
2018-2027
177,200
42,676
134,524
-
134,524
13,452
121,071
105,332
15,739
-
-
-
-
-
-
-
-
-
(70,303)
-
-
-
-
-
-
-
-
-
(70,303)
(61,163)
(9,139)
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
427,200
102,885
324,315
-
-
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
254,012
32,431
221,581
192,775
28,805
Page 5-7 Infrastructure Costs Covered in the D.C. Calculation – Parks and Recreation Services Less:
Prj.No
Increased Service Needs Attributable to Anticipated Development
Timing (year)
Gross Capital Cost Estimate (2018$)
Post Period Benefit
Other Deductions
Net Capital Cost
2018-2027
Less:
Grants, Subsidies and Benefit to Other Existing Contributions Development Attributable to New Development
Subtotal
Other (e.g. 10% Statutory Deduction)
Potential DC Recoverable Cost
Total
Residential Share
NonResidential Share
95%
5%
Parkland, Trails & Ammenities 1
Wellington Secondary Plan ( 4 ac.)
2018-2027
405,368
-
405,368
-
405,368
40,537
364,831
346,589
2
Redgate Subdivision (park and trails)
2018-2027
107,700
-
107,700
-
107,700
10,770
96,930
92,084
4,847
3
Macauley Village Local Park
2018-2027
107,700
-
107,700
-
107,700
10,770
96,930
92,084
4,847
4
Millenium Trail Urbanization
2021
613,800
-
613,800
460,350
153,450
15,345
138,105
131,200
6,905
5
Recreation Facilities Wellington Arena Replacement/Expansion (NPV of Debt Payments) Pool/Fitness Centre
2018-2027
1,492,930
-
1,201,474
677,385
524,089
524,089
497,884
26,204
2018-2027
13,778,200
-
13,778,200
11,711,470
2,066,730
206,673
1,860,057
1,767,054
93,003
2018-2027
33,500
-
33,500
33,500
3,350
30,150
28,643
1,508
(722,126)
(686,019)
(36,106)
6
291,456
18,242
Recreation Vehicles 7
Fairgrounds Service Vehicle
-
Reserve Fund Adjustment
Total
Watson & Associates Economists Ltd.
(722,126)
16,539,198
-
291,456
16,247,742
12,849,205
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
-
2,676,411
287,445
2,388,966
2,269,518
119,448
Page 5-8 Infrastructure Costs Covered in the D.C. Calculation – Library Services Less:
Prj.No
Increased Service Needs Attributable to Anticipated Development
Gross Capital Cost Timing (year) Estimate (2018$)
Post Period Benefit
Other Deductions
Net Capital Cost
2018-2027
Less:
Grants, Subsidies and Benefit to Other Existing Contributions Development Attributable to New Development
Subtotal
Other (e.g. 10% Statutory Deduction)
Potential DC Recoverable Cost
Total
Residential Share
NonResidential Share
95%
5%
Library Facilities 1
Picton Library Branch Expansion
2018
Library Materials 2
Provision for Additional Collection Items Reserve Fund Adjustment
Total
Watson & Associates Economists Ltd.
2018-2027
1,160,000
-
398,965
761,035
394,637
31,586
334,812
33,481
301,330
286,264
15,067
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
313,231
-
313,231
-
-
-
-
-
-
-
-
-
313,231 -
31,323 -
(189,265)
281,908 (189,265)
267,812 (179,801)
14,095 (9,463)
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1,473,231
-
398,965
1,074,266
394,637
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
31,586
458,778
64,804
393,974
374,275
19,699
Page 5-9 Infrastructure Costs Covered in the D.C. Calculation – Administration (Studies) Services Less:
Prj.No
Gross Capital Cost Timing (year) Estimate (2018$)
Increased Service Needs Attributable to Anticipated Development
Post Period Benefit
Net Capital Cost
2018-2027
Less:
Grants, Subsidies and Benefit to Other Existing Contributions Development Attributable to New Development
Subtotal
Other (e.g. 10% Statutory Deduction)
Potential DC Recoverable Cost
Total
Residential Share
NonResidential Share
87%
13%
1
Development Charge Study (2)
2022-2027
90,000
-
90,000
-
90,000
9,000
81,000
70,470
2
Recreation Master Plan
2018-2027
153,400
-
153,400
76,700
76,700
7,670
69,030
60,056
10,530 8,974
3
Traffic Study - County Wide (Master Plan)
2018
150,000
-
150,000
37,500
112,500
112,500
97,875
14,625
4
Servicing Study Wellington
2018
150,000
-
150,000
37,500
112,500
112,500
97,875
14,625
5
Servicing Study Picton
2018
30,639
-
30,639
7,660
22,979
22,979
19,992
2,987
6
Update County Official Plan (& 5 yr. Review)
2018
13,056
-
13,056
6,528
6,528
653
5,875
5,111
764
7
Bloomfield Secondary Plan Update
2020
258,500
-
258,500
64,625
193,875
19,388
174,488
151,804
22,683
8
Picton Master SWM Plan
9
Consecon/Carrying Place Secondary Plan
2018-2027
240,000
-
240,000
120,000
2020
191,000
-
191,000
47,750
100,000
20,000
2,000
18,000
15,660
2,340
143,250
14,325
128,925
112,165
16,760
10
West Lake Shoreline Management Plan
2018-2027
112,400
-
112,400
56,200
56,200
5,620
50,580
44,005
6,575
11
Wetlands Evaluation
2018-2027
224,800
-
224,800
112,400
112,400
11,240
101,160
88,009
13,151
12
Zoning Study
2018-2027
50,000
-
50,000
25,000
25,000
2,500
22,500
19,575
2,925
13
Salt Management Study
2019
50,000
-
50,000
25,000
25,000
25,000
21,750
3,250
14
Development Review Standards
2018
50,000
-
50,000
-
50,000
5,000
45,000
39,150
5,850
15
Compreshensive Zoning Bylaw
2018
300,000
-
300,000
150,000
150,000
15,000
135,000
117,450
17,550
16
Downtown(s) Parking Master Plan
2019
100,000
-
100,000
50,000
50,000
5,000
45,000
39,150
5,850
(514,071)
(447,242)
(66,829)
635,466
552,855
82,611
Reserve Fund Adjustment
Total
Watson & Associates Economists Ltd.
(514,071)
2,163,795
-
2,163,795
816,863
100,000
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
732,861
97,395
Page 5-10 Infrastructure Costs Covered in the D.C. Calculation – Homes for the Aged Services Less:
Prj.No
Increased Service Needs Attributable to Anticipated Development
1
Facility Expansion - Ph 1 (44 beds)
Gross Capital Cost Timing (year) Estimate (2018$)
Post Period Benefit
Net Capital Cost
2018-2027
Reserve Fund Adjustment
Total
Watson & Associates Economists Ltd.
2021
7,314,000
1,198,881
6,115,119
Less:
Grants, Subsidies and Benefit to Other Existing Contributions Development Attributable to New Development 4,561,285
458,560
Subtotal
1,095,274
109,527 -
Total
985,746 -
Residential Share
NonResidential Share
100%
0%
985,746 -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
7,314,000
1,198,881
6,115,119
4,561,285
-
Other (e.g. 10% Statutory Deduction)
Potential DC Recoverable Cost
(370,743)
(370,743)
458,560
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
724,531
109,527
615,004
(370,743)
615,004
-
-
Page 5-11 Infrastructure Costs Covered in the D.C. Calculation – Waste Diversion Services
Prj .No
Increased Service Needs Attributable to Anticipated Development
2018-2027
Total
Watson & Associates Economists Ltd.
Timing (year)
Less: Gross Grants, Subsidies and Capital Cost Post Period Net Capital Benefit to Other Contributions Estimate Benefit Cost Existing Attributable to New (2018$) Development Development
Less: Subtotal
Other (e.g. 10% Statutory Deduction)
Potential DC Recoverable Cost Residential Non-Residential Share Share
Total
87%
13%
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
-
Page 5-12 Infrastructure Costs Covered in the D.C. Calculation –Municipal Parking Services
Less:
Prj.No
1
Gross Capital Cost Timing (year) Estimate (2018$)
Increased Service Needs Attributable to Anticipated Development
2018-2027 Provision for Addition 219 Spaces (Mortimer, East Mary, Wellington, King St, Bridge St)
Total
Watson & Associates Economists Ltd.
2018-2027
1,357,800
Post Period Benefit
1,202,512
Net Capital Cost
155,288
Less:
Grants, Subsidies and Benefit to Other Existing Contributions Development Attributable to New Development -
Subtotal
155,288
Other (e.g. 10% Statutory Deduction)
15,529
Potential DC Recoverable Cost
Total
139,759
Residential Share
NonResidential Share
87%
13%
121,590
18,169
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1,357,800
1,202,512
155,288
-
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
-
155,288
15,529
139,759
121,590
18,169
Page 5-13
5.2
Service Levels and 20-Year Capital Costs for County-wide D.C. Calculation
5.2.1 Transportation Services The County has a current inventory of 700 kilometres of rural and urban arterial and collector roads and 3,989 m2 of bridges and culverts.62 bridges and culverts. This historic level of infrastructure investment equates to a level of service of $11,097 per capita. Furthermore, the County also provides services through the maintenance of 1,560 streetlights, traffic signals and pedestrian crossings, 78,600 m2 of public works facilities, and 82 public works vehicles. In total, average historic level of service provided is $11,950 per capita. When applied to the forecast population growth to 2037 (i.e. 7,127 incremental net-population growth), a maximum D.C.-eligible cost of approximately $87.1 million could be expected to meet the future increase in needs for service. The review of the County’s transportation needs for the forecast period identified $34.8 million in gross capital costs. These capital needs include various road extensions, widenings, intersection improvements and signalizations, and additional public works facility space and vehicles. Recognizing the benefit to existing development, approximately $16.5 million has been deducted. Furthermore, $2.8 million has been deducted in recognition of new roads servicing potential growth areas outside of the 20year forecast period. Approximately $3.5 million has been deducted from the potential D.C. recoverable costs for existing reserve fund balances, accounting for funds already secured towards these future needs. As a result, approximately $12.0 million in capital costs have been included in the D.C. calculation. The net growth-related costs for Transportation Services have been allocated between future residential and non-residential development on the basis of incremental population to employment growth over the forecast period (i.e. 85% residential, 15% non-residential).
5.2.2 Fire Protection Services The County currently has 47,000 sq.ft. of floor space within four fire stations and 4,300 sq.ft. of facility floor space within 14 locations. The County also maintains an inventory of 35 vehicles and provides 228 items of equipment for fire protection. In total, the inventory of Fire Protection Services assets provides a historic average level of service of approximately $655 per capita. The historical level of investment in Fire Protection
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 5-14 Services provides for a D.C.-eligible amount over the forecast period of approximately $4.7 million. The County will require funds for the replacement and expansion of two new fire stations, and an additional Fire Rescue Boat. Furthermore, $2.3 million has been included as committed excess capacity reflective of the D.C. eligible costs of previously constructed facilities. In total, the gross capital cost estimates for the increase in need for service, totals $5.5 million. After deductions of $3.0 million for the benefit to existing development, the net D.C. eligible costs total $2.5 million. Accounting for $675,000 related to the reserve fund deficit position, the total D.C. eligible capital costs included in the calculation of the charge are $3.2 million. The allocation of net growth-related costs for fire services between residential, and nonresidential development is 85% and 15% respectively, reflective of the incremental growth in population and employment over the forecast period.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 5-15 Infrastructure Costs Covered in the D.C. Calculation – Transportation Services Less: Increased Service Needs Attributable to Anticipated Development
Prj .No
Timing (year)
Gross Capital Post Period Cost Estimate Benefit (2018$)
Net Capital Cost
Benefit to Existing Development
2018-2037
Grants, Subsidies and Other Contributions Attributable to New Development
Potential DC Recoverable Cost
Total
Residential Non-Residential Share Share 85%
15%
Roads Bloomfield 1
Traffic Signals (Wellington St. and Hwy 62)
2018-2037
143,900
-
143,900
71,950
71,950
61,158
10,793
2
Pedestrial Crossing
2018-2037
143,900
-
143,900
71,950
71,950
61,158
10,793
Carrying Place 3
Intersection Improvements and Signalization (Cty Rd. 3 and Loyalist Prkwy)
2018-2037
371,000
-
371,000
185,500
185,500
157,675
27,825
4
Intersection Improvements (Cty Rd. 3 and Taft Rd.)
2018-2037
227,100
-
227,100
113,550
113,550
96,518
17,033
Picton 5
Intersection Improvements and Signalization (Bridge St. and Union St.)
2018-2037
324,400
-
324,400
48,660
275,740
234,379
41,361
6
Intersection Improvements and Signalization (Main St. and Johnson St.)
2018-2037
324,400
-
324,400
48,660
275,740
234,379
41,361
7
Intersection Improvements and Signalization (Talbot St. and Frank St.)
2018-2037
490,800
-
490,800
73,620
417,180
354,603
62,577
8
Picton Bypass (White Chapel to Loyalist Pkwy incl. intersections)
2018-2037
6,923,000
5,192,250
3,461,500
1,730,750
1,471,138
259,613
1,730,750
9
Downes Road Extension (to Picton Bypass) and Road Widening
2018-2037
636,600
-
636,600
31,830
604,770
514,055
90,716
10
Intersection Improvements and Signalization (Cty Rd 22 and Cty Rd 10)
2018-2037
324,400
-
324,400
48,660
275,740
234,379
41,361
11
Signalization (Church St and Union)
2018-2037
143,900
-
143,900
21,585
122,315
103,968
18,347
12
Signalization (Cty Rd 10 and Cty Rd 1)
2018-2037
143,900
-
143,900
21,585
122,315
103,968
18,347
13
New collector road (Finnegan road) between CR #49 and Trail (0.60 km)
2020
1,603,900
-
1,603,900
240,585
1,363,315
1,158,818
204,497
14
Wellings of Picton Inc. Site Access Road
2016
1,257,000
-
1,257,000
188,550
1,068,450
908,183
160,268
15
New Road, Talbot to Loyalist (with signals)
2018
2,926,000
2,750,440
1,463,000
1,287,440
1,094,324
193,116
16
New Sidewalks: both sides of Loyalist from Cold Storage Road
2018
138,000
-
138,000
69,000
69,000
58,650
10,350
26,018
175,560
Consecon 17
Intersection Improvements (Salem Rd. and Loyalist Prkwy.)
2018-2037
346,900
-
346,900
173,450
173,450
147,433
18
Intersection Improvements and Re-alignment (Cty Rd. 29 and Loyalist Prkwy.)
2018-2037
346,900
-
346,900
173,450
173,450
147,433
26,018
19
Traffic Signals (West End - Cty Rd. 1 and Loyalist Prkwy.)
2018-2037
143,900
-
143,900
71,950
71,950
61,158
10,793
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 5-16 Infrastructure Costs Covered in the D.C. Calculation – Transportation Services (Cont’d) Less: Increased Service Needs Attributable to Anticipated Development
Prj .No
Timing (year)
Gross Capital Post Period Cost Estimate Benefit (2018$)
Net Capital Cost
Benefit to Existing Development
2018-2037
20 21 22
Wellington Intersection Improvements and Signalization incl. Land Purchase (Belleville St. and Wellington Main St.) Traffic Signals (Wellington Main St. and Prince Edward Dr.) Signalization incl. Land Purchase (Wellington Main St. and Consecon Rd)
Potential DC Recoverable Cost
Grants, Subsidies and Other Contributions Attributable to New Development
Total
Residential Non-Residential Share Share 85%
15%
2018-2037
815,200
-
815,200
122,280
692,920
588,982
2018-2037
143,900
-
143,900
21,585
122,315
103,968
103,938 18,347
2018-2037
815,200
-
815,200
122,280
692,920
588,982
103,938 12,663
23
Consecon St. Upgrade and Sidewalk - Trail to Hersfield Property
2018-2037
159,200
-
159,200
74,778
84,422
71,759
24
Prince Edward Drive Extension - Empire Blvd. to New East/West Collector
2018-2037
318,300
-
318,300
193,328
124,972
106,226
18,746
25
New Road, Belleville St to Prince Edward drive (with signals)
6,132,000
3,504,000
2,628,000
2,233,800
394,200
26
New Road, East of Belleville St to Berkhout subdivisoon (with signals)
27
Pedestrian Crossing (2)
2025
7,008,000
2025
876,000
1,529,000
-
1,529,000
229,350
1,299,650
1,104,703
194,948
2018-2037
287,800
-
287,800
43,170
244,630
207,936
36,695
2018-2037
227,100
-
227,100
34,065
193,035
164,080
28,955
Rossmore /Fenwood 28
Intersection Improvements - left turn lane (Hwy 62 and Cty. Rd. 28) Rural Area
29
Traffic Signals (Cty Rd. 2. and Hwy 62)
2018-2037
143,900
-
143,900
71,950
71,950
61,158
10,793
30
Traffic Signals (Cty Rd. 1 and Hwy 62)
2018-2037
143,900
-
143,900
71,950
71,950
61,158
10,793
31
Intersection illumination HWY 62 & CR 14, HWY 62 & CR 1
2019
14,000
-
14,000
7,000
7,000
5,950
1,050
Public Works Facilities 32
North County Depot including land (12,800 sq.ft.)
2018-2037
2,105,400
-
2,105,400
2,066,887
38,513
32,736
5,777
33
Sand and Salt Dome
2018-2037
1,703,100
-
1,703,100
1,388,677
314,423
267,260
47,163
34
South County Depot including land (12,300 sq.ft.)
2018-2037
2,105,400
-
2,105,400
1,993,938
111,462
94,743
16,719
2018-2037
343,000
-
343,000
343,000
291,550
51,450
Public Works Vehicles 35
Provision for additional vehicles (3) (1 tandem plow)
-
Reserve Fund Adjustment Total
Watson & Associates Economists Ltd.
(3,542,706) (3,011,300) 34,822,300
2,782,310
32,039,990
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
16,524,272
-
11,973,012 10,177,061
(531,406) 1,795,952
Page 5-17 Infrastructure Costs Covered in the D.C. Calculation – Fire Protection Services
Prj .No
Increased Service Needs Attributable to Anticipated Development
Timing (year)
2018-2037
Less: Gross Grants, Subsidies and Capital Cost Post Period Net Capital Benefit to Other Contributions Benefit Cost Estimate Existing Attributable to New (2018$) Development Development
Potential DC Recoverable Cost
Total
Residential Non-Residential Share Share 85%
15%
Fire Stations 1
Rossmore Station (6,200 sq.ft.), including land
2018-2027
1,657,000
-
1,657,000
1,201,058
455,942
387,551
68,391
2 3
Wellington Station (6,200 sq.ft.) Committed Excess Capacity - Picton Fire Hall Committed Excess Capacity - Cty Rd 29 & Cty Rd 33 (4 single bays)
2018-2027 2018-2027
1,557,000 524,285
-
1,557,000 524,285
709,691 -
847,309 524,285
720,213 445,643
127,096 78,643
2018-2027
1,747,277
-
1,747,277
1,074,358
672,918
571,981
100,938
2018-2027
25,600
-
25,600
25,600
21,760
3,840
675,308
574,012
101,296
3,201,363
2,721,159
480,204
4
Fire Vehicles 5
Rescue Boat
-
Reserve Fund Adjustment
Total
Watson & Associates Economists Ltd.
5,511,162
-
5,511,162
2,985,107
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
-
Page 6-1
6. D.C. Calculation Tables 6-1 to 6-2 present the D.C. calculation for the growth-related capital costs identified in Chapter 5. Table 6-1 presents the D.C. calculation for County-wide services over the 20-year period (i.e. 2018-2037), and presented in Table 6-2 is the calculated D.C.s for County-wide services over the 10-year planning horizon (i.e. 20182027). Table 6-3 summarizes the calculation of maximum D.C.s by residential dwelling type, per square foot of gross floor area for non-residential development, and per 500kW of generating capacity for wind and solar energy facilities. For the residential calculations, charges are calculated on a per single detached unit (greater than two bedrooms) equivalent basis and converted to six forms of dwelling unit types: • • •
single and semi-detached dwelling (greater than 2 bedrooms); single and semi-detached dwelling (2 bedrooms or less); apartments (2 bedrooms and larger);
• •
apartments (bachelor and 1 bedrooms); other multiples (greater than 2 bedrooms); and
•
other multiples (2 bedrooms or less)
The D.C. for non-residential wind and solar energy facility development has been calculated based on the single and semi-detached dwelling (greater than 2 bedrooms) rate for Transportation Services, Fire Protection Services, and Administration Studies. For all other non-residential development, the D.C. for has been calculated on a per square foot of gross floor area basis. Tables 6-4 and 6-7 compare the County’s existing charges (inflated to 2018$ at 2.3%) to the charges proposed herein (Table 6-3), for single and semi-detached dwellings (greater than 2 bedrooms) and non-residential development respectively.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 6-2 Table 6-1 D.C. Calculation Municipal-Wide Services 2018 – 2037 2018 $ DC Eligible Cost Residential Non-Residential
SERVICE
$
$
2018 $ DC Eligible Cost SDU (>2BR) per ft² $
$
1. Transportation
10,177,061
1,795,952
3,344
2.11
2. Fire Protection
2,721,159
480,204
894
0.56
TOTAL
$12,898,219
$2,276,156
DC ELIGIBLE CAPITAL COST
$12,898,219
$2,276,156
20 Year Gross Population / GFA Growth (ft².) Cost Per Capita / Non-Residential GFA (ft².)
8,384 $1,538
$4,238
$2.67
852,400 $2.67
p.p.u
By Residential Unit Type Single and Semi-Detached Dwelling (>2 Bedrooms)
2.75
$4,238
Single and Semi-Detached Dwelling (=2 Bedrooms)
1.54
$2,371
Other Multiples (=2BR) per ft² $
$
192,775
28,805
114
0.07
2,269,518
119,448
1,347
0.30
5. Library
374,275
19,699
222
0.05
6. Administration (Studies)
552,855
82,611
328
0.21
7. Homes for the Aged
615,004
-
365
0.00
121,590
18,169
72
0.05
TOTAL
$4,126,017
$268,732
DC ELIGIBLE CAPITAL COST
$4,126,017
$268,732
4. Parks and Recreation
8. Waste Diversion 9. Municipal Parking
10 Year Gross Population / GFA Growth (ft².) Cost Per Capita / Non-Residential GFA (ft².) By Residential Unit Type
4,641 $889
$0.68
401,800 $0.67
p.p.u
Single and Semi-Detached Dwelling (>2 Bedrooms)
2.75
Single and Semi-Detached Dwelling (=2 Bedrooms)
1.54
$1,370
Other Multiples (=2 Dwelling (=2 Bedrooms) (=2 Bedrooms) Comparison Current - 50% reduction in Current - Rural serviced areas Service (2018$) (2018$)
Calculated (2018$)
Municipal Wide Services: Transportation
3,039
1,520
3,344
Fire Protection
410
205
894
54
27
114
1,598
799
1,347
236
118
222
Marinas and Boat Launches Parks and Recreation Library Administration (Studies)
847
424
328
Homes for the Aged
358
179
365
Waste Diversion
-
-
-
Municipal Parking Total Municipal Wide Services
6,543
3,272
72 6,686
*Current charges shown in 2018$ values (indexed at 2.3%)
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 6-4 Table 6-5 Comparison of Current and Calculated D.C.s Non-Residential Development per Square Foot of Gross Floor Area Non-Residential (per ft².) Comparison Current - 50% reduction in all Current - Rural areas (2018$) (2018$)
Service Municipal Wide Services: Transportation Fire Protection Marinas and Boat Launches Parks and Recreation Library Administration (Studies) Homes for the Aged Waste Diversion Municipal Parking Total Municipal Wide Services *Current charges shown in 2018$ values (indexed at 2.3%)
Watson & Associates Economists Ltd.
2.52 0.34 0.05 0.24 0.03 0.81 3.98
1.26 0.17 0.03 0.12 0.02 0.40 1.99
Calculated (2018$) 2.11 0.56 0.07 0.30 0.05 0.21 0.05 3.35
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 7-1
7. D.C. Policy Recommendations and D.C. By-law Rules This chapter outlines the D.C. policy recommendations and by-law rules. The rules provided are based on the review of methodology and implementation polices with senior County staff. Further background on the implementation policies can be found in Appendix F s.s.5(1)9 states that rules must be developed: “...to determine if a D.C. is payable in any particular case and to determine the amount of the charge, subject to the limitations set out in subsection 6.” Paragraph 10 of subsection 5(1) goes on to state that the rules may provide for exemptions, phasing in and/or indexing of D.C.s. s.s.5(6) establishes the following restrictions on the rules: 1. the total of all D.C.s that would be imposed on anticipated development must not exceed the capital costs determined under 5(1) 2-8 for all services involved; 2. if the rules expressly identify a type of development, they must not provide for it to pay D.C.s that exceed the capital costs that arise from the increase in the need for service for that type of development; however, this requirement does not relate to any particular development; 3. if the rules provide for a type of development to have a lower D.C. than is allowed, the rules for determining D.C.s may not provide for any resulting shortfall to be made up via other development; and 4. with respect to “the rules,” subsection 6 states that a D.C. by-law must expressly address the matters referred to above re s.s.5(1) para. 9 and 10, as well as how the rules apply to the redevelopment of land.
7.1
D.C. By-law Structure
It is recommended that: • •
the County impose a uniform County-wide D.C. for all municipal services herein; and one municipal D.C. by-law be used for all services.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 7-2
7.2
D.C. By-law Rules
The following sets out the recommended rules governing the calculation, payment and collection of D.C.s in accordance with subsection 6 of the D.C.A., 1997. It is recommended that the following provides the basis for the D.C.s:
7.2.1 Payment in any Particular Case In accordance with the D.C.A., 1997, s.2(2), a D.C. be calculated, payable and collected where the development requires one or more of the following: a) the passing of a zoning by-law or of an amendment to a zoning by-law under Section 34 of the Planning Act; b) the approval of a minor variance under Section 45 of the Planning Act; c) a conveyance of land to which a by-law passed under Section 50(7) of the Planning Act applies; d) the approval of a plan of subdivision under Section 51 of the Planning Act; e) a consent under Section 53 of the Planning Act; f) the approval of a description under Section 50 of the Condominium Act; or g) the issuing of a building permit under the Building Code Act in relation to a building or structure.
7.2.2 Determination of the Amount of the Charge The following conventions be adopted: 1) Costs allocated to residential uses will be assigned to different types of residential units based on the average occupancy for each housing type constructed during the 20-year period. Costs allocated to non-residential development will be based on the generating capacity for wind and solar energy facilities and on gross floor area constructed for all other non-residential uses. 2) Costs allocated to residential and non-residential uses are based upon a number of conventions, as may be suited to each municipal service circumstance. These are summarized in Chapter 5 herein.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 7-3
7.2.3 Application to Redevelopment of Land (Demolition and Conversion) If a development involves the demolition and replacement of a building or structure on the same site, or the conversion from one principal use to another, the developer shall be allowed a credit equivalent to: 1) the number of dwelling units demolished/converted multiplied by the applicable residential D.C. in place at the time the D.C. is payable; and/or 2) the gross floor area of the building demolished/converted multiplied by the current non-residential D.C. in place at the time the D.C. is payable. The credit can, in no case, exceed the amount of D.C.s that would otherwise be payable. Moreover, the applicant will need to provide evidence that the building was habitable prior to demolition to be eligible for redevelopment credits. Building permit applications received prior to March 6, 2018 will not need to provide evidence that the building was habitable prior to demolition.
7.2.4 Exemptions (full or partial) a) Statutory exemptions •
Industrial building additions of up to and including 50% of the existing gross floor area (defined in O.Reg. 82/98, s.1) of the building; for industrial building additions which exceed 50% of the existing gross floor area, only the portion of the addition in excess of 50% is subject to D.C.s (s.4(3));
•
Buildings or structures owned by and used for the purposes of any County, local board or Board of Education (s.3); and Residential development that results in only the enlargement of an existing dwelling unit, or that results only in the creation of up to two additional dwelling units (based on prescribed limits set out in s.2 of O.Reg. 82/98).
•
b) Non-statutory exemptions • •
A non-residential farm building; A place of worship;
• •
New Industrial development (excluding wind and solar energy facilities); A temporary building or structure;
•
A reduction of 30% in D.C.s is allowed for the affordable housing, as defined in the by-law, for any residential dwelling unit for which the purchase price is at
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 7-4 least 25% less than the average purchase price for the same type of residential dwelling unit in the County of Prince Edward and for any residential dwelling unit where the monthly rent is at or below the maximum affordable monthly rent amount established by the Residential Rental Standers board for the Province of Ontario; and •
Reduction of D.C.s to Encourage Growth in Specific Areas • 50% reduction for residential development occurring in fully or partially serviced areas unit December 31, 2018 •
50% reduction for all non-residential development until December 31, 2018.
The proposed non-statutory exemption for non-residential farm buildings has been narrowed from its current application within the County’s D.C. By-Law. Under the County’s current by-law, farm buildings are defined as in the Building Code Act. For clarity in the application of this exemption, the definition of farm building will be expanded to exclude: •
retail sales activities; including but not limited to restaurants, banquet facilities, hospitality and accommodation facilities, gift shops; services related to grooming, boarding or breeding of household pets; and marijuana and alcohol processing or production facilities.
By-Law 3205-2013, as amended, includes exemptions for Park Model Trailers. In discussion with senior staff from the County, this exemption has been removed.
7.2.5 Phase in Provision(s) The phase-in of D.C.s has not been proposed.
7.2.6 Timing of Collection The D.C.s for all services are payable upon issuance of a building permit for each dwelling unit, building or structure, subject to early or late payment agreements entered into by the County and an owner under s.27 of the D.C.A., 1997.
7.2.7 Indexing All D.C.s will be subject to mandatory indexing annually on the anniversary date of he By-law in accordance with provisions under the D.C.A. The D.C.s shall be adjusted for the change in index for the most recently available annual period.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 7-5
7.2.8 D.C. Spatial Applicability In accordance with the D.C.A., the County gave, consideration to the imposition of D.C.s on an area-specific basis, and is maintaining its current approach of imposing uniform County-wide D.C.s for all services. Further discussion on this matter is provided in Appendix F.
7.3
Other D.C. By-law Provisions
7.3.1 Categories of Services for Reserve Fund and Credit Purposes It is recommended that the County’s D.C. collections be contributed into nine (9) separate reserve funds, including: Transportation Services, Fire Protection Services, Marinas and Boat Launches, Parks and Recreation Services, Library Services, Administration Studies, Homes for the Aged, Waste Diversion Services, and Municipal Parking Services. It is further recommended that all D.C. exemptions granted over the life of the by-law be contributed into the applicable D.C. reserve funds from non-D.C. sources.
7.3.2 By-law In-force Date The proposed by-law under D.C.A., 1997 will come into force on March 6, 2018.
7.3.3 Minimum Interest Rate Paid on Refunds and Charged for Inter-Reserve Fund Borrowing The minimum interest rate is the Bank of Canada rate on the day on which the by-law comes into force (as per s.11 of O.Reg. 82/98).
7.4
Other Recommendations
It is recommended that Council: •
“Approve the capital project listing set out in Chapter 5 of the “County of Prince Edward 2017 Development Charges Background Study” dated December 1, 2017, subject to further annual review during the capital budget process;”
•
“Approve the “County of Prince Edward 2017 Development Charges Background Study” dated December 1, 2017;"
• •
“Determine that no further public meeting is required;” and “Approve the Development Charges By-Law as set out in Appendix D”.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 8-1
8. Asset Management Plan 8.1
Introduction
The recent changes to the D.C.A. (new section 10(c.2)) require that the background study must include an Asset Management Plan (A.M.P) related to new infrastructure. Section 10 (3) of the D.C.A. provides: The A.M.P. shall, (a) deal with all assets whose capital costs are proposed to be funded under the development charge by-law; (b) demonstrate that all the assets mentioned in clause (a) are financially sustainable over their full life cycle; (c) contain any other information that is prescribed; and (d) be prepared in the prescribed manner. At a broad level, the A.M.P. provides for the long-term investment in an asset over its entire useful life along with the funding. The schematic below identifies the costs for an asset through its entire lifecycle. For growth-related works, the majority of capital costs will be funded by the D.C. Non-growth related expenditures will then be funded from non-D.C. revenues as noted below. During the useful life of the asset, there will be minor maintenance costs to extend the life of the asset along with additional program related expenditures to provide the full services to the residents. At the end of the life of the asset, it will be replaced by non-D.C. financing sources.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 8-2
In 2012, the Province developed Building Together: Guide for Municipal Asset Management Plans which outlines the key elements for an A.M.P., as follows: State of local infrastructure: asset types, quantities, age, condition, financial accounting valuation and replacement cost valuation. Desired levels of service: defines levels of service through performance measures and discusses any external trends or issues that may affect expected levels of service or the municipality’s ability to meet them (for example, new accessibility standards, climate change impacts). Asset management strategy: the asset management strategy is the set of planned actions that will seek to generate the desired levels of service in a sustainable way, while managing risk, at the lowest lifecycle cost. Financing strategy: having a financial plan is critical for putting an A.M.P. into action. By having a strong financial plan, municipalities can also demonstrate that they have made a concerted effort to integrate the A.M.P. with financial planning and municipal budgeting, and are making full use of all available infrastructure financing tools. The above provides for the general approach to be considered by Ontario municipalities. At this time, there is not a mandated approach for municipalities hence leaving discretion to individual municipalities as to how they plan for the long-term Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 8-3 replacement of their assets. The County of Prince Edward has undertaken an A.M.P dated September 2014. However, the plan addresses only roads, bridges and culverts, and water and wastewater assets and does not include all assets categories that are included in the capital forecast needs of the D.C. Background Study. As a result, the asset management requirement for this D.C. Background Study must be undertaken in the absence of this information. In recognition to the schematic in Section 8.1, the following table (presented in 2018$) has been developed to provide the annualized expenditures and revenues associated with new growth. Note that the D.C.A. does not require an analysis of the non-D.C. capital needs or their associated operating costs so these are omitted from the table below. Furthermore, as all existing assets for the categories of assets included in the D.C. eligible capital costs are not included in the County’s A.M.P. (parks and recreation, library, etc. not included), the present infrastructure gap and associated funding plan has not been considered at this time. Hence the following does not represent a fiscal impact assessment (including future tax/rate increases) but provides insight into the potential affordability of the new assets: 1. The non-D.C. recoverable portion of the projects which will require financing from County financial resources (i.e. taxation, rates, fees, etc.). This amount has been presented on an annual debt charge amount based on 20-year financing. 2. Lifecycle costs for the 2017 D.C. capital works have been presented based on a sinking fund basis. The assets have been considered over their estimated useful lives. 3. Incremental operating costs for the D.C. services (only) have been included. 4. The resultant total annualized expenditures are $10.4 million. 5. Consideration was given to the potential new taxation and user fee revenues which will be generated as a result of new growth. These revenues will be available to finance the expenditures above. The new operating revenues are $8.4 million. This amount, totalled with the existing operating revenues of $63.7 million, provide annual revenues of $72.1 million by the end of the period. 6. In consideration of the above, the capital plan is deemed to be financially sustainable.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 8-4 Table 8-1 County of Prince Edward Asset Management – Future Expenditures and Associated Revenues (2018$) Sub-Total Expenditures (Annualized) Annual Debt Payment on Non-Growth Related Capital1 (2014 DC and 2016 updates) Annual Debt Payment on Post Period Capital2 Lifecycle: Annual Lifecycle - Town Wide Services Sub-Total - Annual Lifecycle Incremental Operating Costs (for D.C. Services) Total Expenditures
2037 (Total)
2,667,374 254,074 $1,816,225 $1,816,225
$1,816,225
$5,951,003 $10,434,602
Revenue (Annualized) Total Existing Revenue3 Incremental Tax and Non-Tax Revenue (User Fees, Fines, Licences, etc.) Total Revenues
$63,685,768 $8,374,816 $72,060,584
1
Non-Growth Related component of Projects including 10% mandatory deduction on soft services 2 Interim Debt Financing for Post Period Benefit 3
As per Sch. 10 of FIR
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 9-1
9. By-law Implementation 9.1
Public Consultation
This chapter addresses the mandatory, formal public consultation process (subsection 9.1.1), as well as the optional, informal consultation process (subsection 9.1.2). The latter is designed to seek the co-operation and involvement of those involved, in order to produce the most suitable policy. Section 9.2 addresses the anticipated impact of the D.C. on development, from a generic viewpoint.
9.1.1 Public Meeting of Council Section 12 of the D.C.A., 1997 indicates that before passing a D.C. by-law, Council must hold at least one public meeting, giving at least 20 clear days’ notice thereof, in accordance with the Regulation. Council must also ensure that the proposed by-law and background report are made available to the public at least two weeks prior to the (first) meeting. Any person who attends such a meeting may make representations related to the proposed by-law. If a proposed by-law is changed following such a meeting, the Council must determine whether a further meeting (under this section) is necessary. For example, if the by-law which is proposed for adoption has been changed in any respect, the Council should formally consider whether an additional public meeting is required, incorporating this determination as part of the final by-law or associated resolution. It is noted that Council’s decision, once made, is final and not subject to review by a Court or the O.M.B.
9.1.2 Other Consultation Activity There are three broad groupings of the public who are generally the most concerned with municipal D.C. policy: 1. The residential development community, consisting of land developers and builders, who are typically responsible for generating the majority of the D.C. revenues. Others, such as realtors, are directly impacted by D.C. policy. They are, therefore, potentially interested in all aspects of the charge, particularly the quantum by unit type, projects to be funded by the D.C. and the timing thereof,
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 9-2 and municipal policy with respect to development agreements, D.C. credits and front-ending requirements. 2. The second public grouping embraces the public at large and includes taxpayer coalition groups and others interested in public policy (e.g. in encouraging a higher non-automobile modal split). 3. The third grouping is the industrial/commercial/institutional development sector, consisting of land developers and major owners or organizations with significant construction plans, such as hotels, entertainment complexes, shopping centres, offices, industrial buildings and institutions. Also involved are organizations such as Industry Associations, the Chamber of Commerce, the Board of Trade and the Economic Development Agencies, who are all potentially interested in municipal D.C. policy. Their primary concern is frequently with the quantum of the charge, gross floor area exclusions such as basement, mechanical or indoor parking areas, or exemptions and phase-in or capping provisions in order to moderate the impact.
9.2
Anticipated Impact of the Charge on Development
The establishment of sound D.C. policy often requires the achievement of an acceptable balance between two competing realities. The first is that high nonresidential D.C.s can, to some degree, represent a barrier to increased economic activity and sustained industrial/commercial growth, particularly for capital intensive uses. Also, in many cases, increased residential D.C.s can ultimately be expected to be recovered via higher housing prices and can impact project feasibility in some cases (e.g. rental apartments). On the other hand, D.C.s or other municipal capital funding sources need to be obtained in order to help ensure that the necessary infrastructure and amenities are installed. The timely installation of such works is a key initiative in providing adequate service levels and in facilitating strong economic growth, investment and wealth generation.
9.3
Implementation Requirements
Once the County has calculated the charge, prepared the complete Background Study, carried out the public process and passed a new by-law, the emphasis shifts to implementation matters.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 9-3 These include notices, potential appeals and complaints, credits, front-ending agreements, subdivision agreement conditions and finally the collection of revenues and funding of projects. The following provides an overview of the requirements in each case.
9.3.1 Notice of Passage In accordance with s.13 of the D.C.A., when a D.C. by-law is passed, the municipal clerk shall give written notice of the passing and of the last day for appealing the by-law (the day that is 40 days after the day it was passed). Such notice must be given not later than 20 days after the day the by-law is passed (i.e. as of the day of newspaper publication or the mailing of the notice). Section 10 of O.Reg. 82/98 further defines the notice requirements which are summarized as follows: 1. Notice may be given by publication in a newspaper which is (in the Clerk’s opinion) of sufficient circulation to give the public reasonable notice, or by personal service, fax or mail to every owner of land in the area to which the bylaw relates; 2. s.s.10 (4) lists the persons/organizations who must be given notice; and 3. s.s.10 (5) lists the eight items which the notice must cover.
9.3.2 By-law Pamphlet In addition to the “notice” information, the County must prepare a “pamphlet” explaining each D.C. by-law in force, setting out: 4. a description of the general purpose of the D.C.s; 5. the “rules” for determining if a charge is payable in a particular case and for determining the amount of the charge; 6. the services to which the D.C.s relate; and 7. a general description of the general purpose of the Treasurer’s statement and where it may be received by the public. Where a by-law is not appealed to the O.M.B., the pamphlet must be readied within 60 days after the by-law comes into force. Later dates apply to appealed by-laws. The County must give one copy of the most recent pamphlet without charge, to any person who requests one. Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 9-4
9.3.3 Appeals Sections 13 to 19 of the D.C.A., 1997 set out requirements relative to making and processing a D.C. by-law appeal and an O.M.B. Hearing in response to an appeal. Any person or organization may appeal a D.C. by-law to the O.M.B. by filing a notice of appeal with the municipal clerk, setting out the objection to the by-law and the reasons supporting the objection. This must be done by the last day for appealing the by-law, which is 40 days after the by-law is passed.
9.3.4 Complaints A person required to pay a D.C., or his agent, may complain to Municipal Council imposing the charge that: 8. the amount of the charge was incorrectly determined; 9. the credit to be used against the D.C. was incorrectly determined; or 10. there was an error in the application of the D.C. Sections 20 to 25 of the D.C.A., 1997 set out the requirements that exist, including the fact that a complaint may not be made later than 90 days after a D.C. (or any part of it) is payable. A complainant may appeal the decision of Municipal Council to the O.M.B.
9.3.5 Credits Sections 38 to 41 of the D.C.A., 1997 set out a number of credit requirements, which apply where a County agrees to allow a person to perform work in the future that relates to a service in the D.C. by-law. These credits would be used to reduce the amount of D.C.s to be paid. The value of the credit is limited to the reasonable cost of the work which does not exceed the average level of service. The credit applies only to the service to which the work relates, unless the County agrees to expand the credit to other services for which a D.C. is payable.
9.3.6 Front-Ending Agreements The County and one or more landowners may enter into a front-ending agreement which provides for the costs of a project which will benefit an area in the County to which the D.C. by-law applies. Such an agreement can provide for the costs to be borne by one or more parties to the agreement who are, in turn, reimbursed in future by persons who develop land defined in the agreement. Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page 9-5 Part III of the D.C.A., 1997 (Sections 44 to 58) addresses front-ending agreements and removes some of the obstacles to their use which were contained in the D.C.A., 1989. Accordingly, the County assesses whether this mechanism is appropriate for its use, as part of funding projects prior to municipal funds being available.
9.3.7 Severance and Subdivision Agreement Conditions Section 59 of the D.C.A., 1997 prevents a County from imposing directly or indirectly, a charge related to development or a requirement to construct a service related to development, by way of a condition or agreement under s.51 or s.53 of the Planning Act, except for: •
“local services, related to a plan of subdivision or within the area to which the plan relates, to be installed or paid for by the owner as a condition of approval under Section 51 of the Planning Act;”
•
“local services to be installed or paid for by the owner as a condition of approval under Section 53 of the Planning Act.”
It is also noted that s.s.59(4) of the D.C.A., 1997 requires that the municipal approval authority for a draft plan of subdivision under s.s.51(31) of the Planning Act, use its power to impose conditions to ensure that the first purchaser of newly subdivided land is informed of all the D.C.s related to the development, at the time the land is transferred. In this regard, if the County in question is a commenting agency, in order to comply with subsection 59(4) of the D.C.A., 1997 it would need to provide to the approval authority, information regarding the applicable municipal D.C.s related to the site. If the County is an approval authority for the purposes of Section 51 of the Planning Act, it would be responsible to ensure that it collects information from all entities which can impose a D.C. The most effective way to ensure that purchasers are aware of this condition would be to require it as a provision in a registered subdivision agreement, so that any purchaser of the property would be aware of the charges at the time the title was searched prior to closing a transaction conveying the lands.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page A-1
Appendix A – Background Information on Residential and Non-residential Growth Forecast
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Schedule 1 Prince Edward County Residential Growth Forecast Summary Housing Units
Forecast
Historical
Year
Incremental
Institutional Population
1
Population
Population Excluding Institutional Population¹
Seasonal Population
Total Permanent and Seasonal Singles & SemiPopulation¹ Detached
Multiple Dwellings2
Apartments3
Total Households
Other
Seasonal Households
Total Households + Seasonal Households
Person Per Unit (PPU)
Personal Per Unit (PPU) with Seasonal
Mid 2001
24,901
611
24,290
4,795
29,085
8,745
270
735
120
9,870
1,310
11,180
2.52
2.66
Mid 2006
25,496
741
24,755
5,636
30,391
9,115
325
735
120
10,295
1,540
11,835
2.48
2.63
Mid 2011
25,258
653
24,605
5,966
30,571
9,340
345
710
155
10,550
1,630
12,180
2.39
2.56
Mid 2016
24,735
635
24,100
7,148
31,248
9,465
340
755
165
10,725
1,953
12,678
2.31
2.51
Early 2018
24,886
654
24,231
7,475
31,706
9,575
349
755
165
10,844
2,043
12,887
2.29
2.51
Early 2028
26,214
689
25,524
10,205
35,729
10,215
494
802
165
11,676
2,788
14,464
2.25
2.52
Early 2038
27,430
721
26,709
12,125
38,834
10,820
581
909
165
12,476
3,313
15,789
2.20
2.51
Buildout
34,900
918
33,982
18,860
52,842
13,422
1,108
1,247
165
15,942
5,153
21,095
2.19
2.55
Mid 2001 - Mid 2006 595 130 Mid 2006 - Mid 2011 -238 -88 Mid 2011 - Mid 2016 -523 -18 Mid 2016 - Early 2018 151 19 Early 2018 - Early 2028 1,328 35 Early 2018 - Early 2038 2,544 67 Early 2018 - Buildout 10,014 263 Source: Watson & Associates Economists Ltd., 2017. 1. Population excludes Census Undercount of approximately 4%. 2. Includes townhomes and apartments in duplexes. 3. Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
465 -150 -505 131 1,293 2,477 9,751
841 330 1,182 327 2,730 4,650 11,385
1,306 180 677 458 4,023 7,127 21,136
370 225 125 110 640 1,245 3,847
55 20 -5 9 145 232 759
0 -25 45 0 47 154 492
0 35 10 0 0 0 0
425 255 175 119 832 1,632 5,098
230 90 323 90 745 1,270 3,110
655 345 498 209 1,577 2,902 8,208
-0.05 -0.08 -0.09 0 0 0 0
-0.03 -0.07 -0.05 0 0 0 0
28,017
Figure A-1 Annual Housing Forecast¹ 300
246
Housing Units
250
200 145 150
100
188
176 140
174 135
83
174
174
174
164
164
131
164
164
164 149
149
149
149
149
86 78
50
0
Years Historical
Low Density
Medium Density
High Density
Seasonal
Historical Average
Source: Historical housing activity (2007-2016) based on Prince Edward County building permit data 2018 housing growth derived by Watson & Associates Economists Ltd.
Watson & Associates Economists Ltd.
2017-11-27
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 2 Prince Edward County Detailed Housing and Population Forecast by Growth Area, 2018-Buildout
A Development Location
Picton (Fully Serviced) Wellington (Fully Serviced) Urban Subtotal (Fully Serviced) Bloomfield (Water Only) Rossmore (Water Only) Concsecon/ Carrying Place (Water Only) Ameliasburg (Water Only) Urban Subtotal (Water Only)
Rural
Municipal Total
Growth Period
B
Singles & Semi-Detached
Townhomes
C
D= (A+B+C)
E
F (D+E)
G
Apartments
Total Permanent Households
Seasonal Households
Total Permanent + Seasonal Households
Gross Permanent Population in New Units
H
I
Gross Permanent Gross Permanent Population in New Population in New Units + 50% Units + 100% Seasonal Seasonal Population Population Equivalent Equivalent
J
K = (G+J)
L = (H+J)
Decline in Existing Permanent Units
Permanent Net Population Increase
M = (I+J)
Net Population Net Population + 50% + 100% Seasonal Seasonal Population Population Increase Increase
Early 2018 - Early 2028
82
57
28
167
7
174
331
344
357
(110)
221
234
247
Early 2018 - Early 2038
143
109
94
346
19
365
653
688
723
(224)
429
464
499 2,548
Early 2018 - Buildout
714
264
284
1,261
78
1,339
2,596
2,739
2,881
(333)
2,263
2,406
Early 2018 - Early 2028
211
88
19
318
33
351
695
755
816
(46)
649
709
770
Early 2018 - Early 2038
376
123
60
560
78
638
1,225
1,368
1,510
(93)
1,132
1,275
1,417 6,697
2,011
505
216
2,733
179
2,912
6,180
6,508
6,835
(138)
6,042
6,370
Early 2018 - Early 2028
Early 2018 - Buildout
293
145
47
485
40
525
1,026
1,099
1,173
(156)
870
943
1,017
Early 2018 - Early 2038
519
232
154
906
97
1,003
1,878
2,056
2,233
(317)
1,561
1,739
1,916 9,245
Early 2018 - Buildout
2,784
769
499
3,994
257
4,251
8,776
9,247
9,716
(471)
8,305
8,776
Early 2018 - Early 2028
18
-
-
18
2
20
46
50
53
(15)
31
35
38
Early 2018 - Early 2038
37
-
-
37
4
41
95
102
110
(30)
65
72
80
Early 2018 - Buildout
270
110
-
-
110
9
119
281
297
314
(44)
237
253
Early 2018 - Early 2028
9
-
-
9
-
9
23
23
23
(26)
(3)
(3)
(3)
Early 2018 - Early 2038
16
-
-
16
1
17
41
43
45
(52)
(11)
(9)
(7) 23
Early 2018 - Buildout
35
-
-
35
3
38
90
95
101
(78)
12
17
Early 2018 - Early 2028
9
-
-
9
1
10
23
25
27
(18)
5
7
9
Early 2018 - Early 2038
14
-
-
14
3
17
36
41
47
(37)
(1)
4
10
Early 2018 - Buildout
99
56
-
-
56
3
59
143
148
154
(55)
88
93
Early 2018 - Early 2028
4
-
-
4
1
5
10
12
14
(2)
8
10
12
Early 2018 - Early 2038
7
-
-
7
1
8
18
20
22
(5)
13
15
17
Early 2018 - Buildout Early 2018 - Early 2028
19
-
-
19
2
21
49
53
56
(7)
42
46
40
-
-
40
4
44
102
110
117
(61)
41
49
56
Early 2018 - Early 2038
74
-
-
74
9
83
190
206
224
(124)
66
82
100
Early 2018 - Buildout
220
-
-
220
17
237
563
593
625
(184)
379
409
441
Early 2018 - Early 2028
307
-
-
307
701
1,008
786
2,068
3,351
(404)
382
1,664
2,947
49
Early 2018 - Early 2038
652
-
-
652
1,164
1,816
1,668
3,798
5,927
(818)
850
2,980
5,109
Early 2018 - Buildout
877
-
-
877
2,836
3,713
2,284
7,474
12,664
(1,217)
1,067
6,257
11,447
Early 2018 - Early 2028
640
145
47
832
745
1,577
1,914
3,277
4,641
(621)
1,293
2,656
4,020
Early 2018 - Early 2038
1,245
232
154
1,632
1,270
2,902
3,736
6,060
8,384
(1,259)
2,477
4,801
7,125
Early 2018 - Buildout
3,881
769
499
5,150
3,110
8,260
11,623
17,314
23,005
(1,872)
9,751
15,442
21,133
Source: Watson & Associates Economists Ltd., 2017.
Watson Associates Economists Ltd.
2017-11-27
H:\Prince Edward County\2018 DC Study\Growth\Housing Market Model 2018_PEC_FINAL
Schedule 3 Prince Edward County Current Year Growth Forecast Mid 2016 to Early 2018 Population (Net of Institutional)
Mid 2016 Population
24,100
Occupants of New Housing Units, Mid 2016 to Early 2018
Units (2) multiplied by persons per unit (3) gross population increase
119 2.46 293
293
Decline in Housing Unit Occupancy, Mid 2016 to Early 2018
Units (4) multiplied by ppu decline rate (5) total decline in population
10,725 -0.0151 -162
-162
Population Estimate to Early 2018
24,231
Net Population Increase, Mid 2016 to Early 2018
131
(1) 2011 population based on StatsCan Census unadjusted for Census Undercount. (2) Estimated residential units constructed, Mid 2011 to the beginning of the growth period, assuming a six month lag between construction and occupancy. (3) Average number of persons per unit (ppu) is assumed to be:
Structural Type
Persons
% Distribution
Weighted Persons
Per Unit¹
of Estimated Units²
Per Unit Average
Singles & Semi Detached
2.50
92%
2.31
Multiples (6)
1.99
8%
0.15
Apartments (7)
1.77
0%
0.00
100%
2.46
Total ¹
Based on 2011 Census custom database
² Based on Building permit/completion acitivty
(4) 2011 households taken from StatsCan Census. (5) Decline occurs due to aging of the population and family life cycle changes, lower fertility rates and changing economic conditions. (6) Includes townhomes and apartments in duplexes. (7) Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
Watson & Associates Economists Ltd.
2017-11-27
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 4a Prince Edward County Ten Year Growth Forecast Early 2018 to Early 2028 Population (Net of Institutional)
Early 2018 Population
24,231
Occupants of New Housing Units, Early 2018 to Early 2028
Units (2) multiplied by persons per unit (3) gross population increase
832 2.30 1,914
1,914
Decline in Housing Unit Occupancy, Early 2018 to Early 2028
Units (4) multiplied by ppu decline rate (5) total decline in population
10,844 -0.0572 -621
-621
Population Estimate to Early 2028
25,524
Net Population Increase, Early 2018 to Early 2028
1,293
(1) Early 2018 Population based on: 2011 Population (24,100) + Mid 2011 to Early 2018 estimated housing units to beginning of forecast period (119 x 2.46 = 293) + (10,725 x -0.0151 = -162) = 24,231 (2) Based upon forecast building permits/completions assuming a lag between construction and occupancy. (3) Average number of persons per unit (ppu) is assumed to be: Persons
% Distribution
Weighted Persons
Per Unit¹
of Estimated Units²
Per Unit Average
Singles & Semi Detached
2.56
77%
1.97
Multiples (6)
1.47
17%
0.26
1.35
6%
0.08
100%
2.30
Structural Type
Apartments (7) one bedroom or less 1.17 two bedrooms or more 1.91 Total ¹
Persons per unit based on adjusted Statistics Canada Custom 2011 Census database.
² Forecast unit mix based upon historical trends and housing units in the development process.
(4) Early 2018 households based upon 10,725 (2011 Census) + 119 (Mid 2011 to Early 2018 unit estimate) = 10,844 (5) Decline occurs due to aging of the population and family life cycle changes, lower fertility rates and changing economic conditions. (6) Includes townhomes and apartments in duplexes. (7) Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
Watson & Associates Economists Ltd.
2017-11-27
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 4b Prince Edward County Twenty Year Growth Forecast Early 2018 to Early 2038 Population (Net of Institutional)
Early 2018 Population
24,231
Occupants of New Housing Units, Early 2018 to Early 2038
Units (2) multiplied by persons per unit (3) gross population increase
1,632 2.29 3,736
3,736
Decline in Housing Unit Occupancy, Early 2018 to Early 2038
Units (4) multiplied by ppu decline rate (5) total decline in population
10,844 -0.1161 -1,259
-1,259
Population Estimate to Early 2038
26,709
Net Population Increase, Early 2018 to Early 2038
2,477
(1) Early 2018 Population based on: 2011 Population (24,100) + Mid 2011 to Early 2018 estimated housing units to beginning of forecast period (119 x 2.46 = 293) + (10,725 x -0.0151 = -162) = 24,231 (2) Based upon forecast building permits/completions assuming a lag between construction and occupancy. (3) Average number of persons per unit (ppu) is assumed to be: Persons
% Distribution
Weighted Persons
Per Unit¹
of Estimated Units²
Per Unit Average
Singles & Semi Detached
2.56
76%
1.95
Multiples (6)
1.47
14%
0.21
1.35
9%
0.13
100%
2.29
Structural Type
Apartments (7) one bedroom or less 1.17 two bedrooms or more 1.91 Total ¹
Persons per unit based on adjusted Statistics Canada Custom 2011 Census database.
² Forecast unit mix based upon historical trends and housing units in the development process.
(4) Early 2018 households based upon 10,725 (2011 Census) + 119 (Mid 2011 to Early 2018 unit estimate) = 10,844 (5) Decline occurs due to aging of the population and family life cycle changes, lower fertility rates and changing economic conditions. (6) Includes townhomes and apartments in duplexes. (7) Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
Watson & Associates Economists Ltd.
2017-11-27
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 5 Prince Edward County Buildout Growth Forecast Early 2018 to Buildout Population (Net of Institutional)
Early 2018 Population
24,231
Occupants of New Housing Units, Early 2018 to Buildout
Units (2) multiplied by persons per unit (3) gross population increase
5,098 2.28 11,623
11,623
Decline in Housing Unit Occupancy, Early 2018 to Buildout
Units (4) multiplied by ppu. decline rate (5) total decline in population
10,844 -0.1727 -1,872
-1,872
Population Estimate to Buildout
33,982
Net Population Increase, Early 2018 to Buildout
9,751
(1) Early 2018 Population based on: 2011 Population (24,100) + Mid 2011 to Early 2018 estimated housing units to beginning of forecast period (119 x 2.46 = 293) + (10,725 x -0.0151 = -162) = 24,231 (2) Based upon forecast building permits/completions assuming a lag between construction and occupancy. (3) Average number of persons per unit (ppu) is assumed to be: Structural Type
Persons
% Distribution
Weighted Persons
Per Unit¹
of Estimated Units²
Per Unit Average
Singles & Semi Detached
2.56
75%
1.93
Multiples (6)
1.47
15%
0.22
Apartments (7)
1.35
10%
0.13
100%
2.28
one bedroom or less 1.17 two bedrooms or more 1.91 Total ¹
Persons per unit based on adjusted Statistics Canada Custom 2011 Census database.
² Forecast unit mix based upon historical trends and housing units in the development process.
(4) Early 2018 households based upon 10,725 (2011 Census) + 119 (Mid 2011 to Early 2018 unit estimate) = 10,844 (5) Decline occurs due to aging of the population and family life cycle changes, lower fertility rates and changing economic conditions. (6) Includes townhomes and apartments in duplexes. (7) Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
Watson & Associates Economists Ltd.
2017-11-27
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 6A Prince Edward County Summary Of Units In The Development Process Density Type Stage of Development
Singles & SemiDetached
Multiples
1
Apartments
2
Total
Registered Not Built % Breakdown
179 46%
69 18%
140 36%
388 100%
Draft Plans Approved % Breakdown
122 61%
78 39%
0 0%
200 100%
Application Under Review % Breakdown
654 79%
141 17%
34 4%
829 100%
Vacant lands designated for Residential % Breakdown
4,984 81%
549 9%
604 10%
6,137 100%
Total
5,939
837
778
7,554
% Breakdown
79%
11%
10%
100%
Source: Prince Edward County Building Department 1. Includes townhomes and apartments in duplexes. 2. Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
Watson & Associates Economists Ltd.
2017-11-23
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 6B Picton Summary Of Units In The Development Process Density Type Stage of Development
Singles & SemiDetached
Multiples
1
Apartments
2
Total
Registered Not Built % Breakdown
37 16%
48 21%
140 62%
225 100%
Draft Plans Approved % Breakdown
68 47%
78 53%
0 0%
146 100%
Application Under Review % Breakdown
271 68%
91 23%
34 9%
396 100%
Vacant lands designated for Residential % Breakdown
1,617 74%
167 12%
0 14%
2,704 100%
Total % Breakdown
1,993 74%
336 12%
375 14%
2,704 100%
Source: Prince Edward County Building Department 1. Includes townhomes and apartments in duplexes. 2. Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
Schedule 6C Wellington Summary Of Units In The Development Process Density Type Stage of Development
Singles & SemiDetached
Registered Not Built % Breakdown
Multiples
1
Apartments
2
Total
142 87%
21 13%
0 0%
163 100%
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
345 87%
50 13%
0 0%
395 100%
Vacant lands designated for Residential % Breakdown
1,941 81%
213 9%
229 10%
2,383 100%
Total % Breakdown
2,428 83%
284 10%
229 8%
2,941 100%
Draft Plans Approved % Breakdown Application Under Review % Breakdown
Source: Prince Edward County Building Department 1. Includes townhomes and apartments in duplexes. 2. Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
Watson & Associates Economists Ltd.
2017-11-23
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 6D Bloomfield Summary Of Units In The Development Process Density Type Stage of Development
Singles & SemiDetached
Multiples
1
Apartments
2
Total
Registered Not Built % Breakdown
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
Draft Plans Approved % Breakdown
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
Application Under Review % Breakdown
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
Vacant lands designated for Residential % Breakdown
119 100%
0 0%
0 0%
119 100%
Total % Breakdown
119 100%
0 0%
0 0%
119 100%
Source: Prince Edward County Building Department 1. Includes townhomes and apartments in duplexes. 2. Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
Schedule 6E Rossmore Summary Of Units In The Development Process Density Type Stage of Development
Singles & SemiDetached
Registered Not Built % Breakdown
Multiples
1
Apartments
2
Total
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
36 100%
0 0%
0 0%
36 100%
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
Vacant lands designated for Residential % Breakdown
38 100%
0 0%
0%
38 100%
Total % Breakdown
74 100%
0 0%
0 0%
74 100%
Draft Plans Approved % Breakdown Application Under Review % Breakdown
Source: Prince Edward County Building Department 1. Includes townhomes and apartments in duplexes. 2. Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
Watson & Associates Economists Ltd.
2017-11-23
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 6F Carrying Place/Consecon Summary Of Units In The Development Process Density Type Stage of Development
Singles & SemiDetached
Multiples
1
Apartments
2
Total
Registered Not Built % Breakdown
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
Draft Plans Approved % Breakdown
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
Application Under Review % Breakdown
38 100%
0 0%
0 0%
38 100%
Vacant lands designated for Residential % Breakdown
21 100%
0%
0%
21 100%
Total % Breakdown
59 100%
0 0%
0 0%
59 100%
Source: Prince Edward County Building Department 1. Includes townhomes and apartments in duplexes. 2. Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
Schedule 6G Ameliasburgh Summary Of Units In The Development Process Density Type Stage of Development
Singles & SemiDetached
Registered Not Built % Breakdown
Multiples
1
Apartments
2
Total
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
18 100%
0 0%
0 0%
18 100%
0 #DIV/0!
0 #DIV/0!
#DIV/0!
0 #DIV/0!
Vacant lands designated for Residential % Breakdown
3 100%
0 0%
0 0%
3 100%
Total % Breakdown
21 100%
0 0%
0 0%
21 100%
Draft Plans Approved % Breakdown Application Under Review % Breakdown
Source: Prince Edward County Building Department 1. Includes townhomes and apartments in duplexes. 2. Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
Watson & Associates Economists Ltd.
2017-11-23
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 6H Rural Summary Of Units In The Development Process Density Type Stage of Development
Singles & SemiDetached
Multiples
1
Apartments
2
Total
Registered Not Built % Breakdown
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
Draft Plans Approved % Breakdown
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
Application Under Review % Breakdown
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
Vacant lands designated for Residential % Breakdown
928 100%
0 0%
0 0%
928 100%
Total % Breakdown
928 100%
0 0%
0 0%
928 100%
Source: Prince Edward County Building Department 1. Includes townhomes and apartments in duplexes. 2. Includes bachelor, 1 bedroom and 2 bedroom+ apartments.
Watson & Associates Economists Ltd.
2017-11-23
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 7 Prince Edward County Historical Residential Building Permits Years 2007 - 2016
Residential Building Permits
Singles & Semi Detached
Year
Multiples
1
Apartments
2
Total
0
0
0
0
2007
135
10
0
145
2008
117
3
20
140
2009
83
0
0
83
2010
74
4
0
78
2011
81
0
5
86
Sub-total
490
17
25
809
Average (2007 - 2011)
104
4
8
116
60.6%
2.1%
3.1%
65.8%
2012
64
1
1
66
2013
82
0
0
82
2014
82
1
2
85
2015
103
1
0
104
2016
97
1
1
99
428
4
4
670
86
1
1
87
63.9%
0.6%
0.6%
65.1%
918
21
29
1,479
92
2
3
97
62.1%
1.4%
2.0%
65.4%
% Breakdown
Sub-total Average (2012 - 2016) % Breakdown 2007 - 2016 Total Average % Breakdown
Source: Prince Edward County Building Department Sources: 1. Includes townhomes and apartments in duplexes. Building 2. Includes Permits bachelor, - Statistics 1 bedroom Canada andPublication, 2 bedroom+ 64-001XIB apartments.
Watson & Associates Economists Ltd.
2017-11-23
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 8 Prince Edward County Persons Per Unit By Age And Type Of Dwelling (2011 Census) Age of Dwelling 1-5
Singles and Semi-Detached < 1 BR
1 BR
2 BR
3/4 BR
-
-
2.054
2.711
5+ BR 3.091
6-10
-
-
2.256
2.881
-
-
1.923
2.750
16-20
-
-
1.917
2.378
-
2.252
20-25
-
-
2.091
2.610
-
2.526
-
2.494
-
-
3.905
2.704 2.778
2.286
2.467
35+
0.750
1.763
1.991
2.404
3.241
2.345
Total
0.667
2.293
2.030
2.477
3.199
2.414
1-5 6-10
< 1 BR 1.118
1 BR
Multiples 2 BR 3/4 BR
5+ BR
-
-
-
-
Total
-
-
-
-
-
-
-
-
-
-
16-20
-
-
-
-
-
-
20-25
-
-
-
-
-
-
-
-
-
0.886
-
-
4.750
-
2.149
Total
0.881
-
-
5.667
-
1.986
< 1 BR
1 BR
Apartments 2 BR 3/4 BR
-
5+ BR
Total
-
-
-
-
-
-
6-10
-
-
-
-
-
11-15
-
-
-
-
-
16-20
-
-
-
-
-
20-25
-
-
-
-
-
25-35
-
-
1.35
-
-
-
1.043
1.450
2.034
-
-
1.903
Total
1.000
1.611
1.873
-
-
1.770
Age of
-
20 Year Average
1.350
35+
Dwelling
1.47
3
Age of 1-5
-
1.471
35+
Dwelling
-
20 Year Average
-
11-15
25-35
2.56
2
Age of Dwelling
20 Year Average
2.500
11-15
25-35
-
Total
1.714
All Density Types < 1 BR
1-5
-
6-10
-
11-15
-
16-20
-
20-25
-
25-35
-
1 BR -
2 BR
3/4 BR
5+ BR
2.574
2.041
2.913
1.743
2.739
1.900
2.365
-
2.138
-
1.750
2.626
-
2.432
-
2.156
2.426
-
2.333
1.067 1.462
3.182
Total
2.024
3.905
2.430 2.434 2.620
35+
1.120
1.483
1.978
2.401
3.351
2.298
Total
1.167
1.507
1.968
2.468
3.296
2.330
1. The Census PPU has been adjusted to account for the downward PPU trend which has been recently experienced in both new and older units, largely due to the aging of the population 2. Includes townhomes and apartments in duplexes. 3. Includes bachelor, 1 bedroom and 2 bedroom+ apartments. Note: Does not include Statistics Canada data classified as 'Other' PPU Not calculated for samples less than or equal to 50 dwelling units, and does not include institutional population
Watson & Associates Economists Ltd.
2017-11-23
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 9 Prince Edward County Persons Per Unit By Structural Type And Age Of Dwelling (2011 Census) 3.50
Persons Per Dwelling
3.00 2.50
2.70 2.78
2.50 2.57
2.78
2.86
2.71
2.65
2.53
2.49
2.67
2.65 2.34
2.25
2.00
1.70
1.50
1.50
1.66
1.83
1.72
1.64
1.61
1.00 0.50 0.00 1-5
6-10
11-15
16-20
20-25
25-35
35+
Age of Dwelling Singles and Semi-Detached
Multiples
Apartments
Multiple and Apartment PPUs are based on Prince Edward County PPU Data.
Watson Associates Economists Ltd.
2017-11-23H:\Prince Edward County\2018 DC Study\Growth\Housing Market Model 2018_PEC_FINAL
Schedule 10a Prince Edward County Employment Forecast, 2018 to Buildout
Period
Population Excluding Census Undercount
Activity Rate
Employment
Primary
Work at Home
Industrial
Commercial/ Population Related
Institutional
Total
Primary
Work at Home
Industrial
Commercial/ Population Related
Institutional
Total
Mid 2001 Mid 2006 Mid 2011 Mid 2016 Early 2018 Early 2028 Early 2038 Buildout
24,901
0.021
0.065
0.046
0.086
0.056
0.273
525
1,610
1,135
2,140
1,385
6,795
25,496
0.024
0.060
0.049
0.093
0.064
0.291
620
1,540
1,253
2,378
1,635
7,425
25,258
0.017
0.047
0.035
0.087
0.071
0.256
420
1,185
888
2,198
1,785
6,476
24,735
0.020
0.050
0.035
0.087
0.071
0.262
486
1,235
870
2,152
1,748
6,490
24,886
0.016
0.050
0.044
0.102
0.079
0.290
400
1,243
1,089
2,528
1,957
7,217
26,214
0.016
0.053
0.048
0.109
0.078
0.304
432
1,389
1,249
2,869
2,036
7,975
27,430
0.016
0.054
0.052
0.119
0.078
0.319
447
1,481
1,415
3,272
2,131
8,746
34,900
0.015
0.053
0.052
0.122
0.076
0.318
523
1,847
1,815
4,259
2,641
11,085
Mid 2001 - Mid 2006 Mid 2006 - Mid 2011 Early 2018 - Early 2028 Early 2018 - Early 2038 Early 2018 - Buildout
595
0.003
-0.004
0.004
0.007
0.009
0.018
95
-70
118
238
250
630
-238
-0.0077
-0.0135
-0.0140
-0.0062
0.0065
-0.0349
-200
-355
-365
-180
150
-949
1,328
0.0004
0.0031
0.0039
0.0079
-0.0010
0.0142
32
146
160
341
79
758
2,544
0.0002
0.0041
0.0078
0.0177
-0.0010
0.0288
47
238
326
744
174
1,529
10,014
-0.0011
0.0030
0.0083
0.0205
-0.0030
0.0276
123
604
726
1,731
684
3,868
Incremental Change
Annual Average
Mid 2001 - Mid 2006 Mid 2006 - Mid 2011 Early 2018 - Early 2028 Early 2018 - Early 2038 Early 2018 - Buildout
119
0.00065
-0.00085
0.00071
0.00147
0.00170
0.00368
19
-14
24
48
50
126
-48
-0.00154
-0.00270
-0.00280
-0.00125
0.00131
-0.00697
-40
-71
-73
-36
30
-190
133
0.00004
0.00031
0.00039
0.00079
-0.00010
0.00142
3
15
16
34
8
76
127
0.00001
0.00020
0.00039
0.00089
-0.00005
0.00144
2
12
16
37
9
76
154
-0.00002
0.00005
0.00013
0.00032
-0.00005
0.00043
2
9
11
27
11
60
Source: Watson & Associates Economists Ltd., 2017.
Watson & Associates Economists Ltd.
2017-11-27
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 10b Prince Edward County Detailed Employment Forecast by Growth Area, 2018 - Buildout Employment
Development Location
Picton (Fully Serviced) Wellington (Fully Serviced) Urban Subtotal (Fully Serviced) Bloomfield (Water Only) Rossmore (Water Only) Concsecon/ Carrying Place (Water Only) Ameliasburg (Water Only) Urban Subtotal (Water Only)
Rural
Municipal Total
Growth Period
Work at Home
Primary
Industrial
Gross Floor Area
Commercial
Total Employment
Institutional
Industrial
Commercial
Total Gross Floor Area
Institutional
Early 2018 - Early 2028
(2)
47
81
205
43
374
89,100
102,500
30,100
221,700
Early 2018 - Early 2038
(3)
71
171
407
83
729
188,100
203,500
58,100
449,700 1,009,600
Early 2018 - Buildout
(9)
166
342
851
297
1,647
376,200
425,500
207,900
Early 2018 - Early 2028
(2)
76
18
85
20
197
19,800
42,500
14,000
76,300
Early 2018 - Early 2038
(3)
127
60
226
49
459
66,000
113,000
34,300
213,300
Early 2018 - Buildout
(9)
361
256
670
294
1,572
281,600
335,000
205,800
822,400
Early 2018 - Early 2028
(4)
123
99
290
63
571
108,900
145,000
44,100
298,000
Early 2018 - Early 2038
(6)
198
231
633
132
1,188
254,100
316,500
92,400
663,000
Early 2018 - Buildout
(18)
527
598
1,521
591
3,219
657,800
760,500
413,700
1,832,000
Early 2018 - Early 2028
(1)
4
-
3
1
7
-
1,500
700
2,200
Early 2018 - Early 2038
(1)
6
-
7
2
14
-
3,500
1,400
4,900
Early 2018 - Buildout
(3)
13
-
17
7
34
-
8,500
4,900
13,400
Early 2018 - Early 2028
-
1
-
5
1
7
-
2,500
700
3,200
Early 2018 - Early 2038
-
1
-
11
2
14
-
5,500
1,400
6,900
Early 2018 - Buildout
-
1
-
26
7
34
-
13,000
4,900
17,900
Early 2018 - Early 2028
-
1
-
-
1
2
-
-
700
700
Early 2018 - Early 2038
-
5
-
-
6
11
-
-
4,200
4,200
Early 2018 - Buildout
-
10
-
-
12
22
-
-
8,400
8,400
Early 2018 - Early 2028
-
1
-
-
-
1
-
-
-
-
Early 2018 - Early 2038
-
1
-
-
-
1
-
-
-
-
Early 2018 - Buildout
-
2
-
-
-
2
-
-
-
-
Early 2018 - Early 2028
(1)
7
-
8
3
17
-
4,000
2,100
6,100
Early 2018 - Early 2038
(1)
13
-
18
10
40
-
9,000
7,000
16,000
Early 2018 - Buildout
(3)
26
-
43
26
92
-
21,500
18,200
39,700
Early 2018 - Early 2028
37
16
61
43
13
170
67,100
21,500
9,100
97,700 173,400
Early 2018 - Early 2038
54
27
95
93
32
301
104,500
46,500
22,400
Early 2018 - Buildout
144
51
128
167
67
557
140,800
83,500
46,900
271,200
Early 2018 - Early 2028
32
146
160
341
79
758
176,000
170,500
55,300
401,800
Early 2018 - Early 2038
47
238
326
744
174
1,529
358,600
372,000
121,800
852,400
Early 2018 - Buildout
123
604
726
1,731
684
3,868
798,600
865,500
478,800
2,142,900
Source: Watson & Associates Economists Ltd., 2017 1. Square Foot Per Employee Assumptions Industrial
1,100
Commercial/ Population Related
500
Institutional
700
Watson Associates Economists Ltd.
2017-11-27
H:\Prince Edward County\2018 DC Study\Growth\Housing Market Model 2018_PEC_FINAL
Schedule 11 Prince Edward County Non-Residential Construction Value Years 2007 - 2016 (000's 2015 $)
YEAR 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Subtotal Percent of Total Average
Industrial New Improve Additions 2,029 405 0 1,505 1,274 0 2,196 5,514 0 2,237 945 0 4,162 730 0 6,014 794 315 2,850 220 0 1,240 588 0 1,794 332 0 0 501 793 24,027 11,304 1,108 66% 31% 3% 2,085 913 597
2002 - 2014 Period Total 2002-2014 Average % Breakdown
Total 2,434 2,779 7,710 3,183 4,892 7,123 3,070 1,828 2,126 1,294 36,440 100% 3,594
New 3,074 11,495 15,705 4,053 1,176 1,002 743 804 2,802 321 41,175 61% 3,517
46,727 3,594 29.1%
Commercial Improve Additions 898 1,027 2,186 0 484 0 1,677 437 1,607 800 1,024 1,996 1,757 516 1,166 0 742 247 8,987 416 20,529 5,438 31% 8% 1,006 836
Total 4,999 13,681 16,189 6,166 3,583 4,023 3,016 1,970 3,791 9,724 67,141 100% 5,359
69,665 5,359 43.4%
New 0 0 1,662 1,452 247 126 0 1,517 4,007 0 9,012 40% 673
Institutional Improve Additions 3,353 0 3,284 0 68 720 67 710 107 1,344 817 0 330 0 275 0 2,393 0 0 0 10,694 2,774 48% 12% 764 1,956
Total 3,353 3,284 2,449 2,230 1,698 943 330 1,792 6,400 0 22,480 100% 3,393
44,109 3,393 27.5%
New Improve 5,103 4,656 13,000 6,744 19,562 6,066 7,742 2,689 5,586 2,444 7,142 2,636 3,593 2,307 3,562 2,029 8,603 3,467 321 9,489 74,214 42,527 59% 34% 6,274 2,682
Total Additions 1,027 0 720 1,148 2,143 2,311 516 0 247 1,208 9,320 7% 3,390
Total 10,786 19,745 26,348 11,578 10,173 12,090 6,416 5,591 12,317 11,018 126,062 100% 12,346
160,501 12,346 100.0%
Source: Statistics Canada Publication, 64-001-XIB Note: Inflated to year-end 2014 (January, 2015) dollars using Reed Construction Cost Index
Watson & Associates Economists Ltd.
2017-11-23
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Schedule 12 Prince Edward County Employment To Population Ratio By Major Employment Sector, 2001 To 2011 Year
NAICS
2001
Change
2006
2011
01-06
Comments
06-11
Employment by industry Primary Industry Employment 11
Agriculture, forestry, fishing and hunting
21
Mining and oil and gas extraction Sub-total
980
1,045
725
65
-320 Categories which relate to 0 local land-based resources.
10
0
0
-10
990
1,045
725
55
-320
40
55
70
15
15
Industrial and Other Employment 22
Utilities
23
Construction
310
255
265
-55
Manufacturing
570
690
365
120
Wholesale trade
240
235
110
-5
Transportation and warehousing
250
180
180
-70
31-33 41 48-49 56
Waste management and remediation services Sub-total
10 Categories which relate -325
primarily to industrial land
-125 supply and demand. 0
78
108
53
30
-55
1,488
1,525
1,043
35
-480
880
810
750
-70
-60
50
105
125
55
20 -60
Population Related Employment 44-45
Retail trade
51
Information and cultural industries
52
Finance and insurance
200
170
110
-30
53
Real estate and rental and leasing
135
215
170
80
-45 Categories which relate
54
Professional, scientific and technical services
300
350
385
50
35 primarily to population
55
Management of companies and enterprises
56
Administrative and support
71 72 81
0 growth within the municipality.
0
0
0
0
78
108
53
30
-55
Arts, entertainment and recreation
165
240
195
75
-45
Accommodation and food services
640
735
660
95
-75
Other services (except public administration)
370
310
290
-60
-20
2,818
3,045
2,738
225
-305
Sub-total Institutional 61
Educational services
345
410
365
65
-45
62
Health care and social assistance
930
1,130
1,080
200
-50
91
Public administration
225
270
525
45
255
Sub-total
1,500
1,810
1,970
310
160
Total Employment
6,796
7,425
6,476
625
-945
24,901
25,496
25,258
595
-238
Population Employment to Population Ratio Industrial and Other Employment
0.06
0.06
0.04
0.00
-0.02
Population Related Employment
0.11
0.12
0.11
0.01
-0.01
Institutional Employment
0.06
0.07
0.08
0.01
0.01
Primary Industry Employment
0.04
0.04
0.03
0.00
-0.01
Total
0.27
0.29
0.26
0.02
-0.03
Source: Statistics Canada Employment by Place of Work Note: 2001-2011 employment figures are classified by North American Industry Classification System (NAICS) Code
Watson & Associates Economists Ltd.
2017-11-23
H:\Prince Edward County\2018 DC Study\Growth\ Housing Market Model 2018_PEC_FINAL
Page B-1
Appendix B – Level of Service
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Fire Facilities ft² of building area
Description
Picton Fire Hall (shared) Milford Fire Hall Heights Fire Hall (shared) Mallory Fire Hall (shared) Wellington Fire Hall Hillier Fire Hall (shared) Consecon Fire Hall Carrying Place Fire Hall Ameliasburgh Fire Hall (shared) Rossmore Fire Hall North Marysburg (rental) Sophiasburgh Fire Hall New Picton Fire/EMS Station Consecon Fire Station
2 Ross Street 3080 County Rd 10 343 Loch Sloy Ind. Park 126 County Rd 32 44 Belleville Street 65 Station Rd 81 Consecon Main St 3819 County Rd 3 13 Coleman Street 219 County Rd 3 4415 County Rd 2771 County Rd 5 8 MacDonald Drive 14 County Rd 29
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
1,678 2,114 4,421 3,981 2,826 1,690 1,220 2,253 736 4,494 1,046 3,422 -
1,678 2,114 4,421 4,781 2,826 1,690 1,220 2,253 736 4,494 1,046 3,422 -
1,678 2,114 4,421 4,781 2,826 1,690 1,220 2,253 736 4,494 1,046 3,422 -
1,678 2,114 4,421 4,781 2,826 1,690 1,220 2,253 736 4,494 1,046 3,422 -
1,678 2,114 4,421 4,781 2,826 1,690 1,220 2,253 736 4,494 1,046 3,422 -
1,678 2,114 4,421 4,781 2,826 1,690 1,220 2,253 736 4,494 1,046 3,422 -
1,678 2,114 4,421 6,618 2,826 1,690 1,220 2,253 736 4,494 1,046 3,422 -
1,678 2,114 4,421 6,618 2,826 2,253 736 4,494 1,046 3,422 5,920
2,114 10,981 2,826 2,253 736 4,494 1,046 3,422 13,046 5,920
2,114 10,981 2,826 2,253 736 4,494 1,046 3,422 13,046 5,920
Total
29,881
30,681
30,681
30,681
30,681
30,681
32,518
35,528
46,838
46,838
Population Per Capita Standard
30,463 0.98
30,499 1.01
30,535 1.00
30,571 1.00
30,706 1.00
30,841 0.99
30,976 1.05
31,111 1.14
31,248 1.50
31,477 1.49
10 Year Average Quantity Standard Quality Standard Service Standard
2008-2017 1.12 $297 $332
DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
20 Year 7,127 $332 $2,363,527
Watson & Associates Economists Ltd.
Value/ft² 2018 Bld'g with land, Value site works, ($/ft²) etc. $251 $251 $251 $251 $251 $251 $251 $251 $251 $251 $251 $251 $251 $302
PEC 2018 DC Model v8
$294 $294 $294 $294 $294 $294 $294 $294 $294 $294 $294 $294 $294 $352
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Fire Vehicles No. of vehicles
Description
ID
Fire Chief - 2013 F150 Ford Deputy Chief - 2015 Dodge Ram Leas Fire Prev. - 2014 Jeep Cherokee Mechanic - 2008 Ford Van Aerial - 2016 Acendant 107 Aerial - 2016 Acendant 107 Rescue Van - 2003 Ford Pumper/Tanker - 2000 GMC Pumper - 1993 Ford Pumper/ Tanker Grass Unit - 2006 F450 Pumper/Tanker - 2013 Freightliner Tanker - 1990 GMC Rescue Van - 2015 E450 Tanker - 2006 Freightliner Tanker - 2013 Freightliner Tanker - 2002 International Rescue Van - 1993 Ford E350 Pumper/Tanker - 2000 GMC Tanker - 2015 Freightliner Rescue Van - 1986 Chev Pumper - 2003 Freightliner Tanker - 1997 International Rescue Van - 2009 Ford E350 Pumper/Tanker - 2000 GMC Rescue Van - 1990 GMC Rescue Pumper/Tanker - 2015 Freightliner Pumper/Tanker - 2012 Freightliner Rescue Van - 2010 Ford E 450 Res Tanker - 2007 GMC Pumper/Tanker - 1996 GMC Pumper/Tanker - 2000 GMC Tanker - 2004 International Rescue Van - 2013 Ford E450 1985 FORD 1/2 TON 4BY4
F1 F2 F4 F7 F8 1011 1013 1021 1031 1014 2011 1022 2013 2012 1012 8012 F29 3011 3012 3013 4011 4012 4013 9011 8013 8011 5011 5013 5012 F61 6011 6012 6013 F66
Watson & Associates Economists Ltd.
2008
2009
2010
2011
2012
2013
2014
2015
2016
1 1 1 1 1
1 1 1 1 1
1 1 1 1 1
1 1 1 1 1
1 1 1 1 1
1 1 1 1 1
1 1 1 1 1
1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
-
1 1 1 1 1 1 1 1 1 1 1 1
-
1 1 1
-
1 1 1 1 1 1 1 1 1 1 1 1
-
-
1 1 1 1
1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 -
1 1 1 1 1 1 1 1 1 1 1 1 -
1 1 1 -
1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1
1 1 1
2017
1 1 1 1 1 1 1 1 1 1 1 1 -
1 1 1 -
1 1 1 -
2018 Value ($/Vehicle) $51,000 $51,000 $51,000 $56,000 $899,000 $1,330,000 $82,000 $353,000 $353,000 $102,000 $353,000 $223,000 $82,000 $82,000 $353,000 $353,000 $82,000 $353,000 $353,000 $82,000 $353,000 $353,000 $82,000 $353,000 $82,000 $348,000 $348,000 $82,000 $348,000 $353,000 $353,000 $353,000 $82,000 $82,000
PEC 2018 DC Model v8
Service: Unit Measure: Description Pumper/Tanker - 2000 GMC Tanker - 2014 Freightliner Rescue Van - 2005 Ford Marine Support - 2009 Ford F150 Rescue Boat Total Population Per Capita Standard (per 1,000)
Fire Vehicles No. of vehicles ID 7011 7012 7013 F3 M1
2008
2009 1 1 1
-
1 1 1 -
2011 1 1 1
-
2012
-
2014 1 1 1 1
1 1 1
1 1 1 -
2013
-
2015 1 1 1 1
-
2016 1 1 1 1
-
2017 1 1 1 1
1 1 1 1 1
-
36
36
36
36
36
34
34
34
34
35
30,463 1.18
30,499 1.18
30,535 1.18
30,571 1.18
30,706 1.17
30,841 1.10
30,976 1.10
31,111 1.09
31,248 1.09
31,477 1.11
10 Year Average Quantity Standard (per 1,000) Quality Standard Service Standard
2008-2017 1.14 $243 $277
DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
20 Year 7,127 $277 $1,971,399
Watson & Associates Economists Ltd.
2010
2018 Value ($/Vehicle) $353,000 $353,000 $82,000 $51,000 $26,000
PEC 2018 DC Model v8
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Fire Small Equipment and Gear No. of equipment and gear
Equipped Firefighters (FT & PT) SCBA
153 75
153 75
153 75
153 75
153 75
153 75
153 75
153 75
153 75
2018 Value ($/item) 153 $3,900 75 $11,500
Total
228
228
228
228
228
228
228
228
228
228
30,463 7.48
30,499 7.48
30,535 7.47
30,571 7.46
30,706 7.43
30,841 7.39
30,976 7.36
31,111 7.33
31,248 7.30
31,477 7.24
Description
Population Per Capita Standard (per 1,000) 10 Year Average Quantity Standard (per 1,000) Quality Standard Service Standard DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
Watson & Associates Economists Ltd.
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2008-2017 7.39 $6,400 $47 20 Year 7,127 $47 $337,250
PEC 2018 DC Model v8
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure: Description Concrete HCB - Urban HCB - Rural HCB- Semi - Urban LCB- Rural Gravel
Total Population Per Capita Standard
Roads km of roadways 2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
17.5 18.3 263.8 12.5 354.8 32.2
17.5 18.3 263.8 12.5 354.8 32.2
17.5 18.3 263.8 12.5 354.8 32.2
17.5 18.3 263.8 12.5 354.8 32.2
17.5 18.3 263.8 12.5 354.8 32.2
17.5 18.3 263.8 12.5 354.8 32.2
17.5 18.3 263.8 12.5 354.8 32.2
17.5 18.3 263.8 12.5 354.8 32.2
17.5 18.7 263.8 12.5 355.2 32.8
17.5 18.7 263.8 12.5 355.2 32.8
699
699
699
699
699
699
699
699
700
700
30,463 0.02
30,499 0.02
30,535 0.02
30,571 0.02
30,706 0.02
30,841 0.02
30,976 0.02
31,111 0.02
31,248 0.02
31,477 0.02
10 Year Average Quantity Standard Quality Standard Service Standard
2008-2017 0.02 $456,176 $10,355
DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
20 Year 7,127 $10,355 $73,801,510
2018 Value ($/km) 1 $1,182,000 $2,237,000 $405,000 $1,432,000 $350,000 $266,000
1. Replacement costs include sidewalks in right of way.
Watson & Associates Economists Ltd.
PEC 2018 DC Model v8
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Bridges, Culverts & Structures Sq.m. of Bridges, Culverts & Structures Description
Burr Road Bridge (CPE-01) Consecon Bridge (CPE-02) County Road 28 North (CPE-03) County Road 28 South (CPE-04) Demorestville Bridge (CPE-07) County Road 21 Culverts (CPE-08) County Road 4 Bridge (CPE-09) Gilead Road Culvert (CPE-11) Cooper Culvert (CPE-15) Vestervelt Bridge (CPE-16) County Road 17 Culvert (CPE-17) Consecon Bridge (CPE-19) Bridge Street Culvert (CPE-20) York Street Culvert (CPE-21) Black River Bridge (CPE-22) Outlet Bridge (CPE-23) Christian Road Bridge (CPE-24) Gore Road Bridge (CPE-25) Lake Side Road West Bridge (CPE-28) Lake Side Drive East Bridge (CPE-29) Loyalist Parkway Bridge (CPE-30) Consecon River Bridge (CPE-31) Loyalist Parkway Culvert (CPE-32) Melville Bridge (CPE-33) Black Road Bridge (CPE-34) Allisonville Bridge (CPE-35) County Road 5 Bridge (CPE-36) County Road 5 CSP Culvert (CPE-37) Fry Road West Culvert (CPE-38) Loyalist Parkway Bridge (CPE-39) Robinson Road Bridge (CPE-40) Thompson Culvert (CPE-41) Snider Bridge (CPE-42)
Watson & Associates Economists Ltd.
2008 25 179 40 104 21 86 54 281 83 102 322 257 144 30 59 42 132 195 70 137 61 125 92 44 45 80 22 40 24
2009 25 179 40 104 21 86 54 281 83 102 322 257 144 30 59 42 132 195 70 137 61 125 92 44 45 80 22 40 24
2010 25 179 40 180 104 21 86 54 281 83 102 322 257 144 30 59 42 132 195 70 137 61 125 92 44 45 80 22 40 24
2011 25 179 40 180 104 21 86 54 281 83 102 322 257 144 30 59 42 132 195 70 137 61 125 92 44 45 80 22 40 24
2012 25 179 40 180 104 21 86 54 281 83 102 322 257 144 30 59 42 132 195 70 137 61 125 92 44 45 80 22 40 24
2013 25 179 40 77 180 104 21 86 54 281 83 102 322 257 144 30 59 42 132 195 70 137 61 125 92 44 45 80 22 40 24
2014 25 179 40 77 94 180 104 21 86 54 35 281 83 102 322 257 144 30 59 42 132 195 70 137 61 125 92 44 45 80 22 40 24
2015 25 179 40 77 94 180 104 21 86 54 35 281 83 102 322 257 144 30 59 42 132 195 70 137 61 125 92 44 45 80 22 40 24
2016 25 179 40 77 94 180 104 21 86 54 35 281 83 102 322 257 144 30 59 42 132 195 70 137 61 125 92 44 45 80 22 40 24
2017 25 179 40 77 94 180 104 21 86 54 35 281 83 102 322 257 144 30 59 42 132 195 70 137 61 125 92 44 45 80 22 40 24
2018 Value 2 ($/m ) $8,200 $5,100 $8,200 $7,200 $6,100 $5,100 $6,100 $8,200 $6,100 $7,200 $8,200 $5,100 $6,100 $6,100 $5,100 $5,100 $6,100 $8,200 $7,200 $8,200 $6,100 $5,100 $7,200 $6,100 $7,200 $6,100 $6,100 $8,200 $8,200 $7,200 $8,200 $8,200 $8,200
PEC 2018 DC Model v8
Service: Unit Measure:
Bridges, Culverts & Structures Sq.m. of Bridges, Culverts & Structures Description
Wesley Acres Bridge (CPE-43) Fry Road Culvert (CPE-44) Scott's Falls Bridge (CPE-45) Milford Bridge (CPE-46) Wellington Main Street Bridge (CPE-47) Total Population Per Capita Standard
2008
2010
2011
2012
2013
2014
2015
2016
2017
100 28 89 418 72 3,603
100 28 89 418 72 3,603
100 28 89 418 72 3,783
100 28 89 418 72 3,783
100 28 89 418 72 3,783
100 28 89 418 72 3,860
100 28 89 418 72 3,989
100 28 89 418 72 3,989
100 28 89 418 72 3,989
100 28 89 418 72 3,989
30,463 0.12
30,499 0.12
30,535 0.12
30,571 0.12
30,706 0.12
30,841 0.13
30,976 0.13
31,111 0.13
31,248 0.13
31,477 0.13
10 Year Average Quantity Standard Quality Standard Service Standard
2008-2017 0.12 $5,961 $742
DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
20 Year 7,127 $742 $5,285,383
Watson & Associates Economists Ltd.
2009
2018 Value 2 ($/m ) $6,100 $8,200 $6,100 $5,100 $7,200
PEC 2018 DC Model v8
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Traffic Signals & Streetlights No. of Traffic Signals
Streetlights Traffic Signals Pedestrian Crossings
1,513 40 3
1,513 40 3
1,513 40 3
1,513 40 3
1,513 40 3
1,513 40 3
1,513 40 3
1,513 40 3
1,513 40 3
2018 Value ($/item) 1,517 $3,700 40 $143,900 3 $143,900
Total
1,556
1,556
1,556
1,556
1,556
1,556
1,556
1,556
1,556
1,560
30,463 0.05
30,499 0.05
30,535 0.05
30,571 0.05
30,706 0.05
30,841 0.05
30,976 0.05
31,111 0.05
31,248 0.05
31,477 0.05
Description
Population Per Capita Standard
2008
10 Year Average Quantity Standard Quality Standard Service Standard
2008-2017 0.05 $7,568 $382
DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
20 Year 7,127 $382 $2,723,939
Watson & Associates Economists Ltd.
2009
2010
2011
2012
2013
2014
2015
2016
2017
PEC 2018 DC Model v8
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Public Works Facilities ft² of building area
Description
2009
2010
2011
2012
2013
2014
2015
2016
2017
290 12,300 775 10,600 12,200 10,600 6,300 8,050 2,604 3,800 108 1,050 1,518 392 2,100 5,100 1,426 1,300 200 77 720 217 6,200 4,800 -
290 12,300 775 10,600 12,200 10,600 6,300 8,050 2,604 3,800 108 1,050 1,518 392 2,100 5,100 1,426 1,300 200 77 720 217 6,200 4,800 -
290 12,300 775 10,600 12,200 10,600 6,300 8,050 2,604 1,050 392 2,100 5,100 1,426 1,300 200 77 720 217 6,200 -
12,300 775 10,600 12,200 10,600 6,300 8,050 2,604 1,050 392 2,100 5,100 1,426 1,300 200 720 217 6,200 420
12,300 775 10,600 12,200 10,600 6,300 8,050 2,604 1,050 392 2,100 5,100 1,426 1,300 200 720 6,200 420
12,300 775 10,600 12,200 10,600 6,300 8,050 2,604 3,800 1,050 392 2,100 5,100 1,426 200
12,300 775 10,600 12,200 10,600 6,300 8,050 2,604 3,800 1,050 392 2,100 5,100 1,426 200
12,300 775 10,600 12,200 10,600 6,300 8,050 2,604 3,800 1,050 392 2,100 5,100 1,426 200
12,300 775 10,600 12,200 10,600 6,300 8,050 2,604 3,800 1,050 392 2,100 5,100 1,426 200
12,300 775 10,600 12,200 10,600 6,300 8,050 2,604 3,800 1,050 392 2,100 5,100 1,426 200
720 6,200 420
720 420
720 420
720 420
720 420
Total
92,728
92,728
82,502
82,554
82,337
84,837
78,637
78,637
78,637
78,637
Population Per Capita Standard
30,463 3.04
30,499 3.04
30,535 2.70
30,571 2.70
30,706 2.68
30,841 2.75
30,976 2.54
31,111 2.53
31,248 2.52
31,477 2.50
Fuel Centre - Underground Equipment Depot Storage Sheds (2) Crowe Pitt Sand/Salt Dome #1 Sand/Salt Dome #2 Sand/Salt Dome Sand/Salt Dome Equipment Depot Fire Hall Storage & Sign Shop Equipment Depot - Athol Flamable Storage Shed Storage/Washrooms Salt/Sand Shed Loader Storage Shed Storage (Quonset) Equipment Depot Equipment Depot Equipment Depot Fuel Centre Fuel Centre - Above Ground Fuel Centre Fuel Centre Firehall Equipment Depot / Fire Hall Fuel Centre
115 Cty Rd., #10, Picton 115 Cty Rd., #10, Picton 75 Cty. Rd. #1, Picton 75 Cty. Rd. #1, Picton 75 Cty. Rd. #1, Picton 18 Cty Rd., #19, Ameliasburgh 35 Cty Rd. #14, Demorestville 13 Coleman St., Ameliasburgh 13 Coleman St., Ameliasburgh 30-B Cherney Cres., Cherry Valley 30-B Cherney Cres., Cherry Valley 289 Main St., Rear, Bloomfield 65 Station Rd., Hillier 18 Cty Rd., #19, Ameliasburgh 35 Cty Rd. #14, Demorestville 35 Cty Rd. #14, Demorestville 3080 Cty Rd., #10 Milford 246 Main St., Wellington 13 Coleman St., Ameliasburgh 115 Cty Rd. #10, Picton 35 Cty Rd. #14, Demorestville 65 Station Rd., Hillier 126 Cty Rd., #32 Bloomfield 65 Station Rd. Hillier 75 Cty. Rd. #1, Picton
10 Year Average Quantity Standard Quality Standard Service Standard DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
Watson & Associates Economists Ltd.
2008
Value/ft² 2018 Bld'g with land, Value site works, ($/ft²) etc. $142 $101 $142 $142 $142 $142 $142 $191 $142 $142 $142 $142 $142 $142 $142 $142 $142 $142 $142 $142 $142 $201 $188 $188 $188
2008-2017 2.70 $162 $436 20 Year 7,127 $436 $3,110,650
PEC 2018 DC Model v8
$160 $115 $160 $160 $160 $160 $160 $214 $160 $160 $160 $160 $160 $160 $160 $160 $160 $160 $160 $160 $160 $225 $210 $210 $210
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Public Works Vehicles No. of vehicles and equipment
Vehicles
92
94
96
95
76
76
76
79
79
2018 Value ($/Vehicle) 82 $113,000
Total
92
94
96
95
76
76
76
79
79
82
30,463 3.02
30,499 3.08
30,535 3.14
30,571 3.11
30,706 2.48
30,841 2.46
30,976 2.45
31,111 2.54
31,248 2.53
31,477 2.61
Description
Population Per Capita Standard (per 1,000)
2008
2009
10 Year Average Quantity Standard (per 1,000) Quality Standard Service Standard
2008-2017 2.74 $112,998 $310
DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
20 Year 7,127 $310 $2,208,158
Watson & Associates Economists Ltd.
2010
2011
2012
2013
2014
2015
2016
2017
PEC 2018 DC Model v8
Prince Edward County Service Standard Calculation Sheet Service: Contact : Unit Measure:
Parking Spaces No. of spaces
Municipal Parking Spaces (Off-Street)
192
192
192
192
192
192
192
192
192
2018 Value ($/space) 192 $6,200
Total
192
192
192
192
192
192
192
192
192
192
30,463 6.30
30,499 6.30
30,535 6.29
30,571 6.28
30,706 6.25
30,841 6.23
30,976 6.20
31,111 6.17
31,248 6.14
31,477 6.10
Description
Population Per Capita Standard (per 1,000) 10 Year Average Quantity Standard Quality Standard Service Standard DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
Watson & Associates Economists Ltd.
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2008-2017 6.23 $6,200 $39 10 Year 4,023 $39 $155,288
PEC 2018 DC Model v8
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Marinas and Boat Launches No. of Marinas and Boat Launches Description
Picton Marina (incld. Docks & Washroom/Office/Storeroom) Wellington Marina (incld. Docks) Wellington Beach Launch Roblin Lake Launch Rossmore Launch Mabel Kleinsteuber Launch Weller's Bay Launch Prinyer's Cove Launch Waupoos Launch (incld. Docks) Waupoos Isle (incld. Docks) Northport Launch Athol Ward Launch Big Island Launch Picton Harbour - Yacht Club Docks Novotany Court Boat Launch South Bay Boat Launch PE Condo Corp #4 Boardwalk Total Population Per Capita Standard (per 1,000) 10 Year Average Quantity Standard (per 1,000) Quality Standard Service Standard DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
Watson & Associates Economists Ltd.
2008
2009 1 1 1 1 1 1 1 1 1 1 1 1 1
2010
1 1 1 16
1 1 1 16
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
30,463 0.53
30,499 0.52
30,535 0.56
-
1 1 1 1 1 1 1 1 1 1 1 1 1 -
2011
2012
2013
2014
2015
2016
2017
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
30,571 0.56
30,706 0.55
30,841 0.55
30,976 0.55
31,111 0.55
31,248 0.54
31,477 0.54
2018 Value ($/item) $492,900 $224,800 $22,500 $11,200 $22,500 $22,500 $22,500 $22,500 $280,900 $168,600 $22,500 $22,500 $22,500 $618,100 $22,300 $22,300 $51,200
2008-2017 0.54 $115,917 $63 10 Year 4,023 $63 $254,012
PEC 2018 DC Model v8
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure: Description
Parkland Development Acres of Parkland 2008
Argyle Park (Parkette) Ashgill Park Athol Park/Town Hall Baxter Green Park, Bloomfield Beckers Park Benson Park, Picton Carla Court Park Centennial (Northport) Park Cenotaph Park Chapel Park Chimney Point Park Consecon Green Belt Consecon Park - 15 Potter Street Delhi Park, Picton Downes Ave Park, Picton Exhibition Grounds Fawcetteville Park Hill Street Park, Picton Jack Taylor Park Johnson Street Fields Mapel St. Parkland Massassauga Road Parkland Macauley Village Municipal Park Milennium Lookout Milford Fairgrounds Prinyer's Cover Park Rednersville Parkland Robin Lake Park Rossmore Park Rotary Park, Picton Shire Hall Park Vintage Shores Park
Watson & Associates Economists Ltd.
0.16 1.51 0.55 2.57 1.38 1.48 0.23 2.93 0.11 0.10 1.58 0.78 0.68 27.00 0.36 21.80 0.82 1.29 4.38 6.36 0.25 0.47 4.47 4.00 1.84 1.84 13.60 13.20 5.58 0.80 1.12
2009 0.16 1.51 0.55 2.57 1.38 1.48 0.23 2.93 0.11 0.10 1.58 0.78 0.68 27.00 0.36 21.80 0.82 1.29 4.38 6.36 0.25 0.47 4.47 4.00 1.84 1.84 13.60 13.20 5.58 0.80 0.33 1.12
2010 0.16 1.51 0.55 2.57 1.38 1.48 0.23 2.93 0.11 0.10 1.58 0.78 0.68 27.00 0.36 21.80 0.82 1.29 4.38 6.36 0.25 0.47 4.47 4.00 1.84 1.84 13.60 13.20 5.58 0.80 0.33 1.12
2011 0.16 1.51 0.55 2.57 1.38 1.48 0.23 2.93 0.11 0.10 1.58 0.78 0.68 27.00 0.36 21.80 0.82 1.29 4.38 6.36 0.25 0.47 4.47 4.00 1.84 1.84 13.60 13.20 5.58 0.80 0.33 1.12
2012 0.16 1.51 0.55 2.57 1.38 1.48 0.23 2.93 0.11 0.10 1.58 0.78 0.68 27.00 0.36 21.80 0.82 1.29 4.38 6.36 0.25 0.47 4.47 4.00 1.84 1.84 13.60 13.20 5.58 0.80 0.33 1.12
2013 0.16 1.51 0.55 2.57 1.38 1.48 0.23 2.93 0.11 0.10 1.58 0.78 0.68 27.00 0.36 21.80 0.82 1.29 4.38 6.36 0.25 0.47 4.47 4.00 1.84 1.84 13.60 13.20 5.58 0.80 0.33 1.12
2014 0.16 1.51 0.55 2.57 1.38 1.48 0.23 2.93 0.11 0.10 1.58 0.78 0.68 27.00 0.36 21.80 0.82 1.29 4.38 6.36 0.25 0.47 4.47 4.00 1.84 1.84 13.60 13.20 5.58 0.80 0.33 1.12
2015 0.16 1.51 0.55 2.57 1.38 1.48 0.23 2.93 0.11 0.10 1.58 0.78 0.68 27.00 0.36 21.80 0.82 1.29 4.38 6.36 0.25 0.47 4.47 4.00 1.84 1.84 13.60 13.20 5.58 0.80 0.33 1.12
2016 0.16 1.51 0.55 2.57 1.38 1.48 0.23 2.93 0.11 0.10 1.58 0.78 0.68 27.00 0.36 21.80 0.82 1.29 4.38 6.36 0.25 0.47 4.47 4.00 1.84 1.84 13.60 13.20 5.58 0.80 0.33 1.12
2017 0.16 1.51 0.55 2.57 1.38 1.48 0.23 2.93 0.11 0.10 1.58 0.78 0.68 27.00 0.36 21.80 0.82 1.29 4.38 6.36 0.25 0.47 4.47 4.00 1.84 1.84 13.60 13.20 5.58 0.80 0.33 1.12
2018 Value ($/Acre) $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500 $22,500
PEC 2018 DC Model v8
Service: Unit Measure: Description
Parkland Development Acres of Parkland 2008
DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
2011
2012
2013
2014
2015
2016
2017
10.21 1.72 9.59 5.73
10.21 1.72 9.59 5.73
10.21 1.72 9.59 5.73
10.21 1.72 9.59 5.73
10.21 1.72 9.59 5.73
10.21 1.72 9.59 5.73
10.21 1.72 9.59 5.73
10.21 1.72 9.59 5.73
10.21 1.72 9.59 5.73
150
151
151
151
151
151
151
151
151
151
30,463 4.94
30,499 4.94
30,535 4.94
30,571 4.93
30,706 4.91
30,841 4.89
30,976 4.87
31,111 4.85
31,248 4.83
31,477 4.79
Total
10 Year Average Quantity Standard (per 1,000) Quality Standard Service Standard
2010
10.21 1.72 9.59 5.73
Wellington Ball Diamond Park Wellington Main St. Park Westfall Memorial Park Wilkinson Memorial Park
Population Per Capita Standard (per 1,000)
2009
2018 Value ($/Acre) $22,500 $22,500 $22,500 $22,500
2008-2017 4.89 $22,500 $110 10 Year 4,023 $110 $442,570
Watson & Associates Economists Ltd.
PEC 2018 DC Model v8
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Parkland Amenities and Trails No. of parkland amenities and trails Description
Millenium Trail - Gravel Base Trail (49 km) Ball Diamonds Bandshell Cattle Barn Change Rooms Pole Barn Basketball Court Canteen/Storage Canteen Cenotaph Display Building-Quonset Gazebo Gazebo/Stage Fountain Horseshoe Pits Parks Shop Picnic Shelter Play Equipment - Small Play Equipment - Medium Play Equipment - Large Swings Shed/Fair Building Skatepark - Small Skatepark - Large Soccer Fields Stage Storage Building Storage Building/Stage Tennis Courts Washrooms Washrooms/Storage/Service Building Major Washroom / Service Facilities Millennium Trail Bridges
Watson & Associates Economists Ltd.
2008
2009 1 9 1 1 1 1 2 3 1 1 1 5 1 1 1 1 8 10 12 1 19 1 2
-
2010
1 9 1 1 1 1 2 3 1 1 1 5 1 1 1 1 8 10 12 1 19 1 2
1 9 1 1 1 -
-
5 1 3 1 5 7 3 -
10
10
2012 1 9 1 1 1
2 3 1 1 1 5 1 1 1 1 8 10 12 2 19 1 1 1 5 1 3 1 5 7 3
5 1 3 1 5 7 3
2011
10
2013 1 9 1 1 1
2 3 1 1 1 5 1 1 1 1 8 10 12 2 19 1 1 1 5 1 3 1 5 6 3 1 10
2014 1 9 1 1 1
2 3 1 1 1 6 1 1 1 1 8 10 12 2 19 1 1 1 5 1 3 1 5 6 3 1 10
2015 1 9 1 1 1
2 3 1 1 1 6 1 1 1 1 8 10 12 2 19 1 1 1 5 1 3 1 5 6 3 1 10
2016 1 9 1 1 1
2 3 1 1 1 6 1 1 1 1 8 10 12 2 19 1 1 1 5 1 3 1 5 6 3 1 10
2017 1 9 1 1 1
2 3 1 1 1 6 1 1 1 1 8 10 12 2 19 1 1 1 5 1 3 1 5 6 3 1 10
1 9 1 1 1 -
2 3 1 1 1 6 1 1 1 1 8 10 12 2 19 1 1 1 5 1 3 1 5 6 3 1 10
2 3 1 1 1 6 1 1 1 1 8 10 11 2 19 1 1 1 5 1 3 1 5 6 2 1 10
2018 Value ($/item) $964,500 $196,700 $63,600 $173,300 $19,000 $37,900 $46,200 $60,000 $5,400 $56,200 $135,400 $85,500 $27,100 $51,500 $6,900 $173,300 $23,600 $16,900 $56,200 $224,800 $4,500 $89,300 $113,200 $842,800 $60,000 $13,500 $12,600 $28,400 $46,400 $34,300 $85,000 $134,900 $248,700
PEC 2018 DC Model v8
Service: Unit Measure:
Parkland Amenities and Trails No. of parkland amenities and trails Description
2008
2009
2015 4 2 3 2 1
4 2 3 2 1
2017
1
1
1
1
1
1
1
Total
130
130
132
132
133
133
133
133
133
133
30,463 4.27
30,499 4.26
30,535 4.32
30,571 4.32
30,706 4.33
30,841 4.31
30,976 4.29
31,111 4.28
31,248 4.26
31,477 4.23
10 Year 4,023 $370 $1,489,315
Watson & Associates Economists Ltd.
-
4 2 3 2 1
2016
-
-
4 2 3 2 1
2014
-
DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
4 2 3 2 1
2013
-
2008-2017 4.29 $86,364 $370
4 2 3 2 1
2012
4 2 3 2 1 1 2
10 Year Average Quantity Standard (per 1,000) Quality Standard Service Standard
4 2 3 2
2011
Delhi Park Trail Bridges Retaining Walls Seawall Memorial Gates Youth Park Building Splash Pad Electronic Road Side Sign
Population Per Capita Standard (per 1,000)
4 2 3 2
2010
-
-
-
4 2 3 2 1 -
2018 Value ($/item) $106,400 $22,500 $112,400 $16,900 $280,900 $255,800 $57,300
PEC 2018 DC Model v8
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Indoor Recreation Facilities ft² of building area
Description
PEC Community Centre and Arena Wellington Arena Properties Shop (shared) Picton Community Hall Bloomfield Community Hall & Office Wellington Community Hall Ameliasburgh Community Hall Athol Community Hall Hillier Community Hall North Marysburgh Community Hall South Marysburgh Community Hall Sophiasburgh Community Hall Crystal Palace Benson Hall Curling Rink Grandstand Building Fruit Growers/Bluebird Building Wellington District Community Centre and Arena Total Population Per Capita Standard
2008
2010
2011
2012
2013
2014
2015
2016
2017
39,140 29,940 1,500 2,400 1,548 1,769 1,809 2,088 2,615 3,450 1,894 3,400 7,904 2,482 14,500 5,500 1,600 123,539
39,140 29,940 1,500 2,400 1,548 1,769 1,809 2,088 2,615 3,450 1,894 3,400 7,904 2,482 14,500 5,500 1,600 123,539
39,140 29,940 1,500 2,400 1,548 1,769 1,809 2,088 2,615 3,450 1,894 3,400 7,904 2,482 14,500 5,500 1,600 123,539
39,140 1,500 2,400 1,548 1,769 1,809 2,088 2,615 3,450 1,894 3,400 7,904 2,482 14,500 5,500 1,600 86,000 179,599
39,140 1,500 2,400 1,548 1,769 1,809 2,088 2,615 3,450 1,894 3,400 7,904 2,482 14,500 5,500 1,600 86,000 179,599
39,140 1,500 2,400 1,548 1,769 1,809 2,088 2,615 3,450 1,894 3,400 7,904 2,482 14,500 5,500 1,600 86,000 179,599
39,140 1,500 2,400 1,548 1,769 1,809 2,088 2,615 3,450 1,894 3,400 7,904 2,482 14,500 5,500 1,600 86,000 179,599
39,140 1,500 2,400 1,548 1,769 1,809 2,088 2,615 3,450 1,894 3,400 7,904 2,482 14,500 5,500 1,600 86,000 179,599
39,140 5,921 2,400 1,548 1,769 1,809 2,088 2,615 3,450 1,894 3,400 7,904 2,482 14,500 5,500 1,600 86,000 184,020
39,140 5,921 2,400 1,548 1,769 1,809 2,088 2,615 3,450 1,894 3,400 7,904 2,482 14,500 5,500 1,600 86,000 184,020
30,463 4.06
30,499 4.05
30,535 4.05
30,571 5.87
30,706 5.85
30,841 5.82
30,976 5.80
31,111 5.77
31,248 5.89
31,477 5.85
10 Year Average Quantity Standard Quality Standard Service Standard
2008-2017 5.30 $161 $852
DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
10 Year 4,023 $852 $3,429,487
Watson & Associates Economists Ltd.
2009
Value/ft² 2018 Bld'g with land, Value site works, ($/ft²) etc. $198 $158 $110 $306 $190 $332 $434 $278 $166 $208 $216 $218 $195 $403 $403 $56 $56 $158
PEC 2018 DC Model v8
$222 $178 $124 $341 $213 $370 $482 $310 $187 $232 $242 $244 $219 $447 $447 $66 $66 $178
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure: Description
Recreation Vehicles and Equipment No. of vehicles and equipment 2008
Ice Resurfacer - PEC Arena Ice Resurfacer - Wellington Arena Floor Machines (manual) Floor Machines (ride-on) Ice Edger Snow Blower Toro - Side by Side Utility Vehcile Ford Ranger Ford F-150 Ford F-250 Chevrolet Express ambulance Ford F-350 Ranger/Mini Van UTV with Dump Box and Groomer
1 1 1
10 Year Average Quantity Standard (per 1,000) Quality Standard Service Standard DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
2010 1 1 2 1 2
2012
1 1 2 1 2 2
2015 1 1 2 1 2 2
2016
2017
-
-
-
-
-
1 1 1 1 0.5 0.5 1
1 1 1 1 0.5 0.5 1
1 1 1 1 0.5 0.5 1
1 1 1 1 0.5 0.5 1
1 1 1 1 0.5 0.5 1
1 1 1 1 0.5 0.5 1
1 1 1 1 0.5 0.5 1
11
11
13
13
15
15
15
16
16
16
30,463 0.36
30,499 0.36
30,535 0.43
30,571 0.43
30,706 0.49
30,841 0.49
30,976 0.48
31,111 0.51
31,248 0.51
31,477 0.51
2
1 1 2 1 2 2
2014
-
2
1 1 2 1 2
2013
-
-
1 1 1
2011
1 1 2 1 2 2 1 1 1 1 1 0.5 0.5 1
Total Population Per Capita Standard (per 1,000)
2009
1 1 2 1 2 2 1 1 1 1 1 0.5 0.5 1
1 1 2 1 2 2 1 1 1 1 1 0.5 0.5 1
2018 Value ($/Vehicle) $107,400 $107,400 $3,800 $15,100 $3,100 $3,100 $16,400 $25,600 $30,700 $35,800 $20,500 $71,600 $25,600 $35,800
2008-2017 0.46 $31,625 $14 10 Year 4,023 $14 $58,092
Watson & Associates Economists Ltd.
PEC 2018 DC Model v8
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Library Facilities ft² of building area
Description
2008
Ameliasburgh Branch Milford Branch Bloomfield Branch Consecon Branch Wellington Branch Picton Branch
2009
2010
2011
2012
2013
2014
2015
2016
2017
1,012 1,800 1,750 1,507 5,720 5,870
1,012 1,800 1,750 1,507 8,440 5,870
1,012 1,800 1,750 1,507 8,440 5,870
1,012 1,800 1,750 1,507 8,440 5,870
1,012 1,800 1,750 1,507 8,440 5,870
1,012 1,800 1,750 1,507 8,440 5,870
1,012 1,800 1,750 1,507 8,440 5,870
1,012 1,800 1,750 1,507 8,440 5,870
1,012 1,800 1,750 1,507 8,440 5,870
1,012 1,800 1,750 1,507 8,440 5,870
Total
17,659
20,379
20,379
20,379
20,379
20,379
20,379
20,379
20,379
20,379
Population Per Capita Standard
30,463 0.58
30,499 0.67
30,535 0.67
30,571 0.67
30,706 0.66
30,841 0.66
30,976 0.66
31,111 0.66
31,248 0.65
31,477 0.65
10 Year Average Quantity Standard Quality Standard Service Standard
Value/ft² 2018 Bld'g with land, Value site works, ($/ft²) etc. $280 $158 $140 $313 $83 $183
2008-2017 0.65 $185 $121
DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
Watson & Associates Economists Ltd.
10 Year 4,023 $121 $486,220
PEC 2018 DC Model v8
$341 $194 $173 $381 $103 $224
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Library Collection Materials No. of library collection items Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Books Periodicals CD / DVD / VHS eResource Database (# of Databases) ebook
84,625 159 4,653 5 -
76,151 129 4,653 15 -
65,214 131 4,653 27 -
61,401 110 4,653 15 -
61,401 110 4,653 15 -
54,372 121 5,212 18 135
41,519 137 5,458 18 138
38,177 30 6,618 18 180
44,120 46 7,536 4 150
48,532 50 9,127 4 160
Total
89,442
80,948
70,025
66,179
66,179
59,858
47,270
45,023
51,856
57,873
Population Per Capita Standard
30,463 2.94
30,499 2.65
30,535 2.29
30,571 2.16
30,706 2.16
30,841 1.94
30,976 1.53
31,111 1.45
31,248 1.66
31,477 1.84
10 Year Average Quantity Standard Quality Standard Service Standard
2018 Value ($/item) $36 $26 $56 $460 $77
2008-2017 2.06 $38 $78
DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
Watson & Associates Economists Ltd.
10 Year 4,023 $78 $313,231
PEC 2018 DC Model v8
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Homes for Aged Facilities ft² of building area
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
H. J. McFarland Memorial Home
31,105
31,105
31,105
31,105
31,105
31,105
31,105
31,105
31,105
31,105
Total
31,105
31,105
31,105
31,105
31,105
31,105
31,105
31,105
31,105
31,105
Population Per Capita Standard
30,463 1.02
30,499 1.02
30,535 1.02
30,571 1.02
30,706 1.01
30,841 1.01
30,976 1.00
31,111 1.00
31,248 1.00
31,477 0.99
10 Year Average Quantity Standard Quality Standard Service Standard
2008-2017 1.01 $500 $504
DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
10 Year 4,023 $504 $2,028,839
Watson & Associates Economists Ltd.
Value/ft² 2018 Bld'g with land, Value site works, ($/ft²) etc. $450
PEC 2018 DC Model v8
$500
Prince Edward County Service Standard Calculation Sheet Service: Unit Measure:
Waste Diversion - Facilities - Stations/Depots ft² of building area
Description
Transfer Station Shelters (3)
2008
Various Locations
Total Percentage attributable to Eligible Portion Total Eligible Portion of Facilities Population Per Capita Standard (per1,000) 10 Year Average Quantity Standard (per 1,000) Quality Standard Service Standard DC Amount (before deductions) Forecast Population $ per Capita Eligible Amount
Watson & Associates Economists Ltd.
2009
2010
2011
2012
2013
2014
2015
2016
2017
246
246
246
246
246
246
246
246
246
246
246 100% 246
246 100% 246
246 100% 246
246 100% 246
246 100% 246
246 100% 246
246 100% 246
246 100% 246
246 100% 246
246 100% 246
30,463 8.08
30,499 8.07
30,535 8.06
30,571 8.05
30,706 8.01
30,841 7.98
30,976 7.94
31,111 7.91
31,248 7.87
Value/ft² 2018 Bld'g with land, Value site works, ($/ft²) etc. $142
31,477 7.82
2008-2017 7.98 $160 $1 10 Year 4,023 $1 $5,149
PEC 2018 DC Model v8
$160
Page C-1
Appendix C – Long-term Capital and Operating Cost Examination
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page C-2
Appendix C – Long-term Capital and Operating Cost Examination As a requirement of the D.C.A., 1997 under subsection 10(2)(c), an analysis must be undertaken to assess the long-term capital and operating cost impacts for the capital infrastructure projects identified within the D.C. As part of this analysis, it was deemed necessary to isolate the incremental operating expenditures directly associated with these capital projects, factor in cost savings attributable to economies of scale or cost sharing where applicable, and prorate the cost on a per unit basis (i.e. square foot of building space, per vehicle, etc.). This was undertaken through a review of the County’s 2016 Financial Information Return. In addition to the operational impacts, over time the initial capital projects will require replacement. This replacement of capital is often referred to as lifecycle cost. By definition, lifecycle costs are all the costs which are incurred during the life of a physical asset, from the time its acquisition is first considered, to the time it is taken out of service for disposal or redeployment. The method selected for lifecycle costing is the sinking fund method which provides that money will be contributed annually and invested, so that those funds will grow over time to equal the amount required for future replacement. The following factors samples of what were utilized to calculate the annual replacement cost of the capital projects (annual contribution = factor x capital asset cost) and are based on an annual growth rate of -1% (net of inflation) over the average useful life of the asset: Lifecycle Cost: Average Useful Life (Years)
Lifecycle Cost: Factor
Facilities, Buildings
40
0.02759
Roads and Related
20
0.05531
Rolling Stock and Equipment
10
0.10547
Fire Vehicles
15
0.07201
Infrastructure
40
0.03034
Parks Related
30
0.03864
Asset
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page C-3 Table C-1 depicts the annual operating impact resulting from the proposed gross capital projects at the time they are all in place. It is important to note that, while municipal program expenditures will increase with growth in population, the costs associated with the new infrastructure (i.e. facilities) would be delayed until the time these works are in place. Table D-1 Operating and Capital Expenditure Impacts for Future Capital Expenditures
SERVICE
ANNUAL LIFECYCLE EXPENDITURES
ANNUAL OPERATING EXPENDITURES
TOTAL ANNUAL EXPENDITURES
1.
Transportation
1,252,138
2,894,608
4,146,746
2.
Fire Protection
72,690
598,977
671,667
3
Marinas and Boat Launches
4.
Parks and Recreation
5.
Library
-
90,445
90,445
162,031
418,675
580,706
79,774
298,118
377,892
1,630,995
1,779,657
19,185
120,115
6.
Administration (Studies)
7.
Homes for the Aged
148,662
8. 9.
Waste Diversion Municipal Parking
100,930
Total
Watson & Associates Economists Ltd.
-
1,816,225
-
5,951,003
7,767,228
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
Page D-1
Appendix D – Proposed D.C. By-law
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-2
Appendix D – Proposed D.C. By-Law THE CORPORATION OF THE COUNTY OF PRINCE EDWARD BY-LAW NUMBER 2018-___ A BY-LAW FOR THE IMPOSITION OF DEVELOPMENT CHARGE
WHEREAS the County of Prince Edward will experience growth through development and re-development; AND WHEREAS development and re-development requires the provision of physical and social services by the County of Prince Edward; AND WHEREAS Council desires to ensure that the capital cost of meeting growth-related demands for or burden on municipal services does not place an excessive financial burden on the County of Prince Edward or its existing taxpayers while at the same time ensuring new taxpayers contribute no more than the net capital cost attributable to providing the current level of municipal services; AND WHEREAS the Development Charges Act, 1997 (the “Act”) provides that the council of a municipality may by by-law impose development charges against land to pay for increased capital costs required because of increased needs for services; AND WHEREAS a development charge background study has been completed in accordance with the Act; AND WHEREAS the Council of The Corporation of the County of Prince Edward has given notice of and held a public meeting on the ____ day of _____, 2018 in accordance with the Act and the regulations thereto; NOW THEREFORE THE COUNCIL OF THE CORPORATION OF THE COUNTY OF PRINCE EDWARD ENACTS AS FOLLOWS: 1.
INTERPRETATION
1.1
In this By-law the following items shall have the corresponding meanings: “Act” means the Development Charges Act, as amended, or any successor thereof;
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-3 “agricultural use” means a bona fide farming operation, including sod farm, the breeding and boarding of horses, and greenhouses; “apartment unit” means a building containing 4 or more dwelling units which have a common entrance from the street level, and the occupants of which have the right to use common elements, including units defined as Assisted Care Dwelling Units; “assisted care dwelling unit” means a unit in a residential building not otherwise defined in this bylaw containing self-contained dwelling units which may include culinary facilities that are designed to accommodate persons with specific needs and where meals are provided within a common eating area; “bedroom” means a room which can be used as a sleeping quarters but does not include a kitchen, bathroom, living room or dining room, but does include a den or study; “board of education” has the same meaning as set out in the Education Act, R.S.O. 19990, Chap. E.2, as amended, or any successor thereof; “Building Code Act” means the Building Code Act, S.O. 1992, as amended, or any successor thereof; “capital cost” means costs incurred or proposed to be incurred by the municipality or a local board thereof directly or by others on behalf of and as authorized by the municipality or local board, (a)
to acquire land or an interest in land, including a leasehold interest,
(b)
to improve land,
(c)
to acquire, lease, construct or improve buildings and structures,
(d)
to acquire, construct or improve facilities including, (i)
furniture and equipment other than computer equipment, and
(ii)
material acquired for circulation, reference or information purposes by a library board as defined in the Public Libraries Act, R.S.O. 19990, Chap. P.44, as amended, or any successor thereof; and
(iii)
rolling stock with an estimated useful life of seven years or more, and
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-4 (e)
to undertake studies in connection with any matter under the Act and any of the matters in clauses (a) to (d) above, including the development charge background study required for the provision of services designated in this By-law within or outside the municipality, including interest on borrowing for those expenditures under clauses (a) to (e) above that are growth-related; “commercial” means any use of land, structures or buildings for the purposes of buying or selling commodities and services, but does not include industrial or agricultural uses, but does include hotels, motels, motor inns and boarding, lodging and rooming houses; “Council” means the Council of the County of Prince Edward; “County” means the area within the geographic limits of the County of Prince Edward; “development” means the construction, erection or placing of one or more buildings or structures on land or the making of an addition or alteration to a building or structure that the effect of increasing the size of usability thereof, and includes redevelopment; “development charge” means a charge imposed with respect to this By-law; “dwelling unit” means one or more rooms used, designed or intended to be used as a residence and which has access to culinary and or sanitary facilities; “existing” means the number, use and size that existed as of the date this by-law was passed; “farm building” means a farm building as defined in the Building Code Act and excludes retail sales activities; including but not limited to restaurants, banquet facilities, hospitality and accommodation facilities, gift shops; services related to grooming, boarding or breeding of household pets; and marijuana and alcohol processing or production facilities; “fully or partially serviced areas” means, with respect to the D.C. reduction policy in s. 3.14.2, the lands as defined in Schedule “B”. “gross floor area” means: (a)
in the case of a residential building or structure, the total area of all floors above grade of a dwelling unit measured between the outside surfaces of
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-5 exterior walls or between the outside surfaces of exterior walls and the centre line of party walls dividing the dwelling unit from any other dwelling unit or other portion of a building; and (b)
in the case of a non-residential building or structure, or in the case of a mixed-use building or structure in respect of the non-residential portion thereof, the total area of all building floors above or below grade measured between the outside surfaces of the exterior walls, or between the outside surfaces of exterior walls and the centre line of party walls dividing a nonresidential use and a residential use, and where the building has only one wall or does not have any walls, the gross floor area shall be the total of the areas directly beneath any roof-like structure of the building, except for: (i)
a room or enclosed area within the building or structure above or below that is used exclusively for the accommodation of heating, cooling, ventilating, electrical, mechanical or telecommunications equipment that service the building;
(ii)
loading facilities above or below grade; and
(iii)
a part of the building or structure below grade that is used for the parking of motor vehicles or for storage or other accessory use;
“industrial” means lands, buildings or structures used or designed or intended for use for manufacturing, processing, fabricating or assembly of raw goods, warehousing or bulk storage of goods, and includes office uses and the sale of commodities to the general public where such uses are accessory to an industrial use, but does not include the sale of commodities to the general public through a warehouse club. Industrial wind turbines and industrial solar farms are included as industrial developments; “industrial wind turbines” means any wind energy system, comprising one or more turbines, with a combined nameplate generating capacity greater than 500 kilowatts and a height greater than 50 metres, that converts energy into electricity, and consists of a wind turbine, a tower, and associated control or conversion electronics. A wind turbine and energy system may be connected to the electricity grid in circuits at a substation to provide electricity off-site for sale to an electrical utility or other intermediary;
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-6 “institutional” means land, buildings, structures or any part thereof used by any organization, group or association for promotion of charitable, or educational objectives and not for profit or gain; “Local Board” means a school board, public utility, commission, transportation commission, public library board, board of park management, local board of health, board of commissioners of police, planning board, or any other board, commission, committee, body or local authority established or exercising any power or authority under any general or special Act with respect to any of the affairs or purposes, including school purposes, of the municipality or any part or parts thereof; “local services” means those services, facilities or things which are under the jurisdiction of the County of Prince Edward and are related to a plan of subdivision or within the area to which the plan relates in respect of the lands under Sections 41, 51 or 53 of the Planning Act, R.S.O. 19990, Chap. P.13, as amended, or any successor thereof; “multiple dwellings” means all dwellings other than single-detached, semidetached and apartment unit dwellings; “municipality” means the Corporation of the County of Prince Edward; “non-residential use” means a building or structure of any kind whatsoever used, designed or intended to be used for other than a residential use; “Official Plan” means the Official Plan adopted for the County, as amended and approved; “Owner” means the owner of land or a person who has made application for an approval for the development of land upon which a development charge is imposed’ “place of worship” means that part of a building or structure that is exempt from taxation as a place of worship under the Assessment Act, R.S.O. 1990, Chap. A.31, as amended, or any successor thereof; “Rate” means the interest rate established weekly by the Bank of Canada based on Treasury Bills having a term of 91 days; “regulation” means any regulation made pursuant to the Act; Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-7 “Residential Dwelling” means a permanent or non-permanent building, occupied or capable of being occupied as a home, residence or sleeping place by one or more persons, containing one or more Dwelling Units but not including motels, hotels, tents, truck campers, mobile camper trailers or boarding, lodging or rooming houses; “residential use” means the use of a building or structure or portion thereof for one or more Dwelling Units. This also includes a Dwelling Unit on land that is used for an Agricultural Use; “row dwelling” means a building containing three or more attached dwelling units in a single row, each of which dwelling units has an independent entrance from the outside and is vertically separated from any abutting dwelling unit; “semi-detached dwelling” means a dwelling unit in a residential building consisting of two dwelling units having one vertical wall or one horizontal wall, but not other parts, attached or another dwelling unit where the residential unit are not connected by an interior corridor; “service” means a service designed in Schedule “A” to this By-law, and “services” shall have a corresponding meaning; “servicing agreement” means an agreement between a landowner and the municipality relative to the provision of municipal services to specified land within the municipality; “single detached dwelling unit” means a residential building consisting of one dwelling unit and not attached to another structure; “industrial solar farm” means any solar energy system comprised of one or more solar panels and associated control or conversion electronics that converts sunlight into electricity, with a nameplate generating capacity greater than 500 kilowatts. A solar farm may be connected to the electricity grid in circuits at a substation to provide electricity off-site for sale to an electrical utility or other intermediary; “temporary building or structure” means a building or structure constructed or erected or placed on land for a continuous period not exceeding eight months, or an addition or alteration to a building or structure that has the effect of increasing the total floor area thereof for a continuous period not exceeding eight months; and Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-8 “Zoning By-Law” means the Zoning By-Law of the County of Prince Edward or any successor thereof passed pursuant to Section 34 of the Planning Act, S.O. 1998. 2.
DESIGNATION OF SERVICES
2.1
The categories of services for which development charges are imposed under this By-law are as follows: a) Administrative Services; b) Transportation Services; c) Fire Protection Services; d) Parks and Recreation Services; e) Library Services; f) Homes for the Aged; g) Marinas and Boat Launches; h) Waste Diversion Services; and i) Municipal Parking Services
3.
APPLICATION OF BY-LAW RULES
3.1
Development charges shall be payable in the amounts set out in this By-law where: (a)
the lands are located in the area described in section 3.2; and
(b)
the development of the lands requires any of the approvals set out in subsection 3.4(a).
Area to Which By-law Applies 3.2
Subject to section 3.3, this By-law applies to all lands in the County of Prince Edward whether or not the land or use thereof is exempt from taxation under s.13 or the Assessment Act.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-9 3.3.
Notwithstanding clause 3.2 above, this by-law shall not apply to lands that are owned by and used for the purposes of: (a)
the municipality or a local board thereof; or
(b)
a board of education.
Approvals for Development 3.4
(a) Development charges shall be imposed on all lands, buildings or structures that are developed for residential or non-residential uses if the development requires: the passing of a zoning by-law or of an amendment to a zoning bylaw under section 34 of the Planning Act; (ii) the approval of a minor variance under section 45 of the Planning Act; (iii) a conveyance of land to which a by-law passed under subsection 50(7) of the Planning Act applies; (iv) the approval of a plan of subdivision under section 51 of the Planning Act; (v) a consent under section 53 of the Planning Act; (vi) the approval of a description under section 50 of the Condominium Act, R.S.O. 1990, Chap. C.26, as amended, or any successor thereof; or (vii) the issuing of a permit under the Building Code Act in relation to a building or structure. No more than one development charge for each service designated in subsection 2.1 shall be imposed upon any lands, buildings or structures to which this By-law applies even though two or more of the actions described in subsection 3.4(a) are required before the lands, buildings or structures can be developed. (i)
(b)
(c)
Despite subsection 3.4(b), if two or more of the actions described in subsection 3.4(a) occur at different times, additional development charges shall be imposed if the subsequent action has the effect or increasing the need for services.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-10 Exemptions 3.5
Notwithstanding the provisions of this By-law, development charges shall not be imposed with respect to: (a)
an enlargement to an existing dwelling unit;
(b)
one or two additional dwelling units in an existing single detached dwelling; or
(c)
one additional dwelling unit in any other existing residential building;
3.6
Notwithstanding section 3.5(b), development charges shall be imposed if the total gross floor area of the additional one or two units exceeds the gross floor area of the existing dwelling unit.
3.7
Notwithstanding section 3.5, development charges shall be imposed if the additional unit has a gross floor area greater than (a)
in the case of a semi-detached or row dwelling, the gross floor area of the existing dwelling unit; and
(b)
in the case of any other residential building, the gross floor area of the smallest dwelling unit contained in the residential building.
Exemption for Industrial Development: 3.8
Notwithstanding any other provision of this by-law, no development charge is payable with respect to an enlargement of the gross floor area of an existing industrial building where the gross floor area is enlarged by 50 percent or less.
3.9
If the gross floor area of an existing industrial building is enlarged by greater than 50 percent, the amount of the development charge payable in respect of the enlargement is the amount of the development charge that would otherwise be payable multiplied by the fraction determined as follows: 1) determine the amount by which the enlargement exceeds 50 percent of the gross floor area before the enlargement; 2) divide the amount determined under subsection 1) by the amount of the enlargement
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-11 3.10
For the purpose of section 3.8 herein, “existing industrial building” is used as defined in the Regulation made pursuant to the Act.
Other Exemptions: 3.11
Notwithstanding the provision of this by-law, development charges shall not be imposed with respect to: a)
Non-residential farm building
b)
Places of worship
c)
Industrial development (excluding industrial wind turbines and solar farms)
(c.1) The County will refund such amount of the development charges paid for temporary buildings or structures when in the opinion of the Chief Building Official that the building or structure has been removed within eight months of building permit issuance. Amount of Charges Residential 3.12
The development charges set out in Schedule A shall be imposed on residential uses of lands, buildings or structures, including a dwelling unit accessory to a non-residential use and, in the case of a mixed use building or structure, on the residential uses in the mixed use building or structure, according to the type of residential unit, and calculated with respect to each of the services according to the type of residential use.
Non-Residential 3.13
The development charges described in Schedule A to this by-law shall be imposed on non-residential uses of lands, buildings or structures, and, in the case of a mixed use building or structure, on the non-residential uses in the mixed use building or structure, and calculated with respect to each of the services according to the total floor area of the non-residential use.
3.13.1 Notwithstanding s.3.12 and s.3.13, the development charges described in Schedule a to this by-law shall be imposed on industrial wind turbines, and calculated at the single-detached and semi-detached dwelling (greater than 2
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-12 bedroom) rate with respect to transportation, fire protection, and administration services.” 3.13.2 Notwithstanding s.3.12 and s.3.13, the development charges described in Schedule A to this by-law shall be imposed on industrial solar farms, and calculated at the single-detached and semi-detached dwelling (greater than 2 bedroom) rate, with respect to transportation, fire protection, and administration services, for each 500 kW of industrial solar farm development.” Reduction of Development Charges for Redevelopment 3.14
Despite any other provisions of this By-law, where, as a result of the redevelopment of land, a building or structure existing on the same land within 60 months prior to the date of payment of development charges in regard to such redevelopment was, or is to be demolished, in whole or in part, or converted from one principal use to another principal use on the same land, in order to facilitate the redevelopment, the development charges otherwise payable with respect to such redevelopment shall be reduced by the following amounts: (a)
in the case of a residential building or structure, or in the case of a mixeduse building or structure, the residential uses in the mixed-use building or structure, an amount calculated by multiplying the applicable development charge under subsection 3.11 by the number, according to type, of dwelling units that have been or will be demolished or converted to another principal use; and
(b)
in the case of a non-residential building or structure or, in the case of mixed-use building or structure, the non-residential uses in the mixed-use building or structure, an amount calculated by multiplying the applicable development charges under subsection 3.12, by the gross floor area that has been or will be demolished or converted to another principal use;
provided that such amounts shall not exceed, in total, the amount of the development charges otherwise payable with respect to the redevelopment. 3.14.1 (1)
In this Section “Affordable Housing Unit” means any single detached dwelling with more than two bedrooms for which the purchase price is at least 25% less than the average purchase price for a single detached dwelling in the County of Prince Edward.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-13 (2)
In determining the average purchase price for a single detached dwelling in the County of Prince Edward for the purposes of subparagraph 1 above, the average purchase price for a single detached dwelling will be calculated for the calendar year next preceding the calendar year in which the completed application for the building permit for the dwelling unit in question is received and shall be determined by the Chief Building Official on the basis of information compiled by the Quinte Real Estate Board or its successor.
(3)
The development charge payable for a single detached dwelling unit with more than two bedrooms that qualifies as an Affordable Housing Unit in accordance with the definition as set out in subparagraph 1 above shall be equal to the development charge otherwise payable pursuant to this Bylaw for a single detached dwelling unit that contains two bedrooms or less.
(4)
Despite the provisions of subparagraph 3 above, the development charge required by this By-law for a single detached dwelling unit with more than two bedrooms shall be paid prior to the issuance of the building permit in accordance with the provisions of this By-law.
(5)
The person to whom the building permit was issued may upon completion of the initial sale of a single detached dwelling unit with more than two bedrooms apply to the Chief Building Official for a reduction of the Development Charge payable to the rate set out in Section 3.14.1 (3) above and shall provide such documentary evidence as is satisfactory to the Chief Building Official that the building qualifies as an Affordable Housing Unit as defined in subparagraph 1 above.
(6)
Satisfactory documentary evidence that the building qualifies as an Affordable Housing Unit shall include, but not be limited to:
(7)
(a)
a copy of a Land Transfer Tax Affidavit duly executed in accordance with Section 5 (1.2) of the Land Transfer Tax Act; or
(b)
a statement forming part of the electronic document as required by Section 5 (1.1) of the Land Transfer Tax Act.
Upon receiving an application for reduction of the Development Charge in accordance with subparagraph 5 of this By-law, and upon being satisfied that the building qualifies as an Affordable Housing Unit as defined in subparagraph 1 above, the Chief Building Official may refund to the
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-14 person to whom the building permit was originally issued a sum equal to the difference between the Development Charge that originally paid upon the issuance of the building permit and the Development Charge that would be payable for a single detached dwelling unit that contains two bedrooms or less as provided for in this By-law. To Encourage Growth in Specific Areas 3.14.2 Despite any other provision of this By-law, in order to encourage growth; (1)
For residential development occurring within the fully or partially serviced areas, the development charge in Schedule B shall be reduced by 50% until December 31, 2018.
(2)
For all non-residential development occurring within the fully or partially serviced areas the development charge in Schedule B shall be reduced by 50% until December 31, 2018.”
Time of Payment of Development Charges 3.15
Development charges imposed under this By-law are calculated, payable, and collected upon issuance of a building permit for the development.
3.16
Despite section 3.15, Council from time to time, and at any time, may enter into agreements providing for all or any part of a development charge to be paid before or after it would otherwise be payable, in accordance with section 27 of the Act.
4.
PAYMENT BY SERVICES
4.1
Despite the payment required under subsections 3.11 and 3.12, Council may, by agreement, give a credit towards a development charge in exchange for work that relates to a service to which a development charge relates under this By-law.
5.
INDEXING
5.1
Development charges therefore shall be adjusted annually by the percentage change during the preceding year as recorded in the Statistics Canada Quarterly, Construction Price Statistics, Non-residential building construction price indexes for the Toronto area.
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-15 6.
SCHEDULES
6.1
The following schedules shall form part of this By-law: Schedule A – Residential and Non-Residential Development Charges Schedule B – Map of Fully or Partially Serviced Areas within the County
7.
CONFLICTS
7.1
Where the County and an owner or former owner have entered into an agreement with respect to land within the area to which this By-law applies, and a conflict exists between the provisions of this By-law and such agreement, the provisions of the agreement shall prevail to the extent that there is a conflict.
7.2
Notwithstanding section 7.1, where a development which is the subject of an agreement to which section 7.1 applies, is subsequently the subject of one or more of the actions described in subsection 3.4(a), an additional development charge in respect of the development permitted by the action shall be calculated, payable and collected in accordance with the provisions of this By-law if the development has the effect of increasing the need for services, unless such agreement provides otherwise.
8.
SEVERABILITY
8.1
If, for any reason, any provision of this By-law is held to be invalid, it is hereby declared to be the intention of Council that all the remainder of this By-law shall continue in full force and effect until repealed, re-enacted, amended or modified.
9.
DATE BY-LAW IN FORCE
9.1
This By-law shall come into effect at 12:01 AM on ___________, 2018.
10.
DATE BY-LAW EXPIRES
10.1
This By-law will expire at 12:01 AM on ___________, 2023 unless it is repealed by Council at an earlier date.
PASSED THIS __________ day of __________, 2018
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-16
Mayor
County Clerk
Watson & Associates Economists Ltd.
H:\Prince Edward County\2018 DC Study\Report\PEC 2017 DCBS-Final.docx
D-17 SCHEDULE “A” TO BY-LAW NO. ____-2018 SCHEDULE OF DEVELOPMENT CHARGES RESIDENTIAL Service
Single and Single and Semi-Detached Semi-Detached Dwelling (>2 Dwelling (=2 Bedrooms) (=2 Bedrooms) residential D.C. for Services Related to Highways, Fire Protection Services, and Administration Services and is imposed per 500 kilowatts of nameplate generating capacity.
4.3
2017 D.C. Background Study D.C. Recommendations
It is recommended that non-residential development charges continue to be imposed for wind and solar energy facilities on the basis of nameplate generating capacity and for all other types of non-residential development per sq.ft. of GFA.
Watson & Associates Economists Ltd. Policy-Dec1.docx
H:\Prince Edward County\2018 DC Study\Report\App F - PEC Implementation
Page 5-2
5. Non-Statutory Development Charge Exemptions 5.1
Development Charges Act Requirements
The D.C.A. provides for a number of statutory D.C. exemptions, as noted below. 1. Where the only effect of the municipal approval action is to permit the enlargement of an existing dwelling unit (s.s.2(3)(a)); 2. Where the only effect of the municipal approval action is to permit the creation of up to two additional dwelling units, as prescribed (s.s.2(3)(b) and s.2 of O.Reg. 82/98); 3. Where the only effect of the municipal approval action is to permit the creation of a second dwelling unit, subject to the prescribed restrictions, in prescribed classes of proposed new residential buildings. (s.s.2(3)(c) and s.2 of O.Reg. 82/98); 4. Land owned by and used for purposes of a municipality or a school board under the Education Act, by reason only that it is exempt from taxation under the Assessment Act s.3); 5. The amount of the D.C. otherwise payable where the gross floor area of an existing industrial building is enlarged by 50% or less (s.4)3.2\ Based on legal precedents, D.C.s are generally not collectable under the D.C.A. in the case of federal, provincial, crown corporation and, in some cases, college and university development. Rules must be developed to determine if a D.C. is payable in any particular case and these rules may provide for full or partial exemptions for types of development (s.s.5(1)9 & 10). A D.C. by-law must set out an express statement indicating how, if at all, the rules provide for exemptions (s.6, para. 1). A municipality may also provide a form of partial D.C. exemption by phasing in an increased charge or by discounting the amount of the charge on particular types of development (s.s.5(1)10). The D.C.A. states that, “If the development charge by-law will exempt a type of development, phase in a development charge or otherwise provide for a type of development to have a lower development charge than is allowed, the rules for Watson & Associates Economists Ltd. Policy-Dec1.docx
H:\Prince Edward County\2018 DC Study\Report\App F - PEC Implementation
Page 5-3 determining development charges may not provide for any resulting shortfall to be made up through higher development charges for other development” (s.s.5(6)3). In this regard, it is important to note that some development may pay a lower D.C. than similar development located elsewhere. This does not reflect a discount or partial exemption. It is the result of making an area-specific or service-specific calculation.
5.2
County of Prince Edward Current Practices
The County’s 2013 D.C. By-Law (as amended) includes the following non-statutory exemptions •
A non-residential farm building as defined in the Building Code Act;
• •
A place of worship; New Industrial development (excluding wind and solar energy facilities);
•
Park Model Trailer conforming to National Standard of Canada CAN CSAZ241.0-92 or similar standard that is up to a maximum size of 50 square metres;
• •
A temporary building or structure; A reduction of 30% in D.C.s is allowed for the affordable housing, as defined in the by-law, for any residential dwelling unit for which the purchase price is at least 25% less than the average purchase price for the same type of residential dwelling unit in the County of Prince Edward and for any residential dwelling unit where the monthly rent is at or below the maximum affordable monthly rent amount established by the Province of Ontario; and Reduction of D.C.s to Encourage Growth in Specific Areas o 50% reduction for residential development occurring in fully or partially serviced areas o 50% reduction for all non-residential development
•
5.3
2017 D.C. Background Study Recommendations
Non-statutory exemptions for farm buildings, places of worship and temporary buildings or structures, within the County’s current D.C. By-law are generally recognized in municipal D.C. by-laws across Ontario. It is proposed that all following exemptions be reviewed by Council to ensure that they are consistent with the County’s current policies. Furthermore, Council should also understand that any exemptions granted over the term of the D.C. by-law are required to be funded from non-D.C. sources. As such, there is a financial impact to the County of doing so. Watson & Associates Economists Ltd. Policy-Dec1.docx
H:\Prince Edward County\2018 DC Study\Report\App F - PEC Implementation
Page 5-4
5.3.1 Agricultural Exemptions Agricultural exemptions are widely granted. However, the specific definition of agricultural development to be exempt can vary. With regard to the definition of farm buildings within the County’s current D.C. By-law, Building Code O.Reg. 332/12 defines Farm Buildings as: Farm Building means all or part of a building, a) That does not contain any area used for residential occupancy; b) That is associated with and located on land devoted to the practice of farming; and c) that is used essentially for the housing of equipment or livestock or the production, storage or processing of agricultural and horticultural produce or feeds. For clarity in the application of this exemption, and regard for the increase in agritourism within the County, the County may wish to expand the definition of “non-residential farm buildings” to exclude certain types of uses that are generally considered commercial in nature. For example, the above definition for non-residential farm buildings could be expanded to exclude: •
retail sales activities; including but not limited to restaurants, banquet facilities, hospitality and accommodation facilities, gift shops; services related to grooming, boarding or breeding of household pets; and marijuana and alcohol processing or production facilities.
5.3.2 Places of Worship Exemptions The places of worship exemptions reflect the largely off-peak hour usage of the facilities, in order not to discourage such activities.
5.3.3 Park Model Trailer Exemptions In recent years the County has experienced strong growth in seasonal development in the form of residential trailer developments. The D.C. growth forecast, which includes seasonal residential growth, forecasts an increase of approximately 826 seasonal trailer units by 2038 (i.e. 41 units per year). Based on the calculated D.C.s per single and semi detached dwelling unit (=2 Bedrooms) Single and Semi-Detached Dwelling (=2 Bedrooms) $670,000 Single and Semi-Detached Dwelling (=