Developments in Geotechnical Engineering
V.V.S. Rao G.L. Sivakumar Babu Editors
Forensic Geotechnical Engineering
Chapter 12
Failure Mechanism of Anchored Retaining Wall Due to the Breakage of Anchor Head Kazuya Itoh, Naotaka Kikkawa, Yasuo Toyosawa, Naoaki Suemasa and Toshiyuki Katada
Abstract In this research, a case history of temporary earth support collapse is first illustrated briefly and the mechanisms of accident occurrences are introduced, with the results showing that the shallow penetration of piles mainly caused the sequences of collapse. In order to understand these failure characteristics and mechanisms, centrifuge model tests using an in-flight excavator were carried out. The failure mechanism of the retaining wall in this labour accident was first demonstrated using centrifuge model tests by Toyosawa et al. Failure mechanism ofanchored retaining wall, 667–672 (1996). In this paper, we added some viewpoints regarding the mechanism of the retaining wall and it was thus clarified that the active and passive earth pressures in the retaining wall increased during excavation and then the anchor head exceeded the capacity with respect to tensile stress. As a result, the retaining wall and ground behind the wall collapsed suddenly.
Keywords Anchored retaining wall Failure mechanism Centrifuge modelling Labour accident
12.1 Introduction Accidents due to collapse frequently occur during ground excavation. The need to decrease these accidents is currently a major concern not only in Japan, but also in several other countries as well. K. Itoh (&) Department of Urban and Civil Engineering, Tokyo City University (formerly at NationalInstitute of Occupational Safety and Health), Tokyo, Japan e-mail:
[email protected] N. Kikkawa Y. Toyosawa Construction Safety Research Group, National Institute of Occupational Safety and Health Japan (JNIOSH), Tokyo, Japan N. Suemasa T. Katada Department of Urban and Civil Engineering, Tokyo City University, Tokyo, Japan © Springer India 2016 V.V.S. Rao and G.L. Sivakumar Babu (eds.), Forensic Geotechnical Engineering, Developments in Geotechnical Engineering, DOI 10.1007/978-81-322-2377-1_12
[email protected]
175
176
K. Itoh et al.
First, a case history has been described in which a temporary earth support collapsed and the ground behind the support failed. A total soil volume of 200 m3 with a maximum thickness of 4 m slid into an excavation area and as a result five workers were killed and two others were injured. Second, in the laboratory, the model ground in front of the anchored retaining wall was excavated using an in-flight excavator in a centrifugal field. Based on the results of two centrifuge model tests, the deformation characteristics, the earth pressure and failure mechanisms are discussed in this paper.
12.2 Case History of the Temporary Earth Support Collapse 12.2.1 Outline of the Construction Work This accident occurred at the building construction site which had an excavation area width of 17.6 m and length of 30.3 m as shown in Fig. 12.1. Figure 12.2 shows the results of a boring log geological survey. The main piles were used as a temporary earth support system with the lateral wooden sheeting method. The length and the interval of the main piles were 15 and 1 m, respectively. The diameter of the ground anchors was 117 mm, the length was 20.5 m (effective length 5.0 m), the angle was 45° and the horizontal interval of the anchors was 2.5 m.
12.2.2 Situation Relating to the Accident Occurrence In the morning that the accident occurred, at around 10:00 a.m., workers noticed that some H-steel piles on the east side had not penetrated below the excavation Fig. 12.1 The ground plan and location for the boring investigation
30.3 N
17.6
Collapsed area
(Building) 26.0 10.5
Location of boring investigation
22.1 Prefectural road
[email protected]
12
Failure Mechanism of Anchored Retaining …
177
11.40
3.90
Mail pile
Soil profile
G. L. (m)
N-Value (by SPT) 10 20 30
40
7.50
1.50 Clayey loam
1.71
Gravel Clay
4.0 8.0
5
Sandy silt
7.0
3.60
7.0 9.0 Fine sand
8.0 13.0
Gravel 68.2
10
75.0 Sandy mudstone
65.2 71.4 65.2 60.0
15
Fig. 12.2 Boring log of the construction site
bottom. The engineer in charge felt there was a danger of a collapse, and he tried to reinforce the main piles with additional remedial piles and blind concrete. At around 1:15 p.m., with a loud noise, the central 15 m temporary earth support structure on the east side collapsed suddenly with the ground behind the support (Fig. 12.3). The ground slid into the excavation area with a soil volume of approximately 200 m3 and a maximum thickness of approximately 4 m. Due to this collapse, eleven H-steel piles toppled. Four workers at the bottom of the excavation site were buried alive and three workers were struck by H-steel piles. As a result, five workers were killed and two others were injured.
12.2.3 Estimation of the Mechanism of the Collapse The sequence of collapse is shown schematically in Fig. 12.4. The mechanism of collapse is summarised as follows; (1) Remedial work was being performed on the excavation bottom despite insufficient penetration of the main piles. It is assumed that, due to insufficient penetration, the earth pressure caused the displacement of the main piles.
[email protected]
178
K. Itoh et al.
Fig. 12.3 The scene of the collapse accident. a The scene of the collapse accident (from south side). b The scene of the collapse accident (from north side). c Damaged H-steel for anchor head
Fig. 12.4 Estimated mechanism of the collapse
H steel (H-300*300*10*15)
Anchor
Anchor head
Excavation level of design Actual excavation level before failure
(2) The main piles were supported by the ground anchors installed at an angle of 45° from the horizontal plane. Downward force provided from the anchor’s tensile force made the connection between the wale which supported the anchor heads and the anchor heads ineffective. Finally, the unstable earth support structure led to a huge-volume soil collapse. (3) The cause of insufficient penetration of the main piles was shortage of excavation at the upper site; due to an engineering error which disregarded the plane of design as shown in Fig. 12.5.
12.2.4 Monitoring Instrumentation is usually required to monitor the performance of a sheet pile structure during construction. Measurements of movements and pressures furnish valuable information for use in verifying design assumptions. Most importantly, the data may forewarn of a potentially dangerous situation that could affect the stability of the structure. In this construction site, however, only visual inspection was used, such as checking for unusual surface signs.
[email protected]
12
Failure Mechanism of Anchored Retaining …
179
Fig. 12.5 The cause of a shortage of embedded depth of sheet pile walls (unit: m)
Actual ground level
3.6
Subgrade
0.3
6.3
6.3
5.0
8.3
Excavation shortage (3.3) Ground level for design
12.3 Centrifuge Model Tests 12.3.1 JNIOSH NIIS Mark II Centrifuge Centrifuge model tests were conducted to examine the failure mechanism of this accident, such as the retaining wall supported to ground anchors. All the tests described here were conducted using the JNIOSH NIIS Mark II Centrifuge (Horii et al. 2006).
12.3.2 In-flight Excavator The in-flight excavator developed by Toyosawa et al. (1998) was used in this study. In this test, for the excavation, this excavator can rake the soil horizontally using a cutting blade. The movement of the in-flight excavator was controlled manually from the centrifuge operation room which is in the upstairs of the centrifuge. The model ground was excavated in steps up to the occurrence of collapse, where the excavated height of each step was about 5 or 6 mm.
12.3.3 Model Preparation From the boring log of the construction site shown in Fig. 12.2, the excavation site consists mainly of Kanto loam (a kind of volcanic cohesive soil in Japan), sand and silt layers. In this paper, (1) a unit layer of sand and (2) a strata of Kanto loam and sand layer were tested.
[email protected]
180
K. Itoh et al.
12.3.3.1 Sand Layer Toyoura sand was poured uniformly into an aluminium model box in which wall and anchors had been set. The relative density of sand was about 90 %.
12.3.3.2 Kanto Loam and Sand Layer Toyoura sand was poured into the aluminium model box to a designated level. Then Kanto loam was placed and compressed on the sand layer. The profile of the model is illustrated in Fig. 12.6. An aluminium model box with internal dimensions of 100 mm (w), 450 mm (l) and 272 mm (h) was used. A Perspex window was installed in one side of the box in order to observe the model during the centrifuge test. The model sheet pile was inserted to the predetermined penetration depth. The model anchors, which were 1.0 mm diameter wire ropes through Teflon tubes, were installed at 45° and the ends of wires were connected to the load cells. Figure 12.7 shows the model of sheet pile (2 mm thick aluminium) with eight earth pressure sensors and six strain gages.
Fig. 12.6 Cross section of profile of two layers
100
150
Kanto loam Load cell
anchor
Toyoura sand
Fig. 12.7 Model of sheet pile wall
: Pressure sensor : Strain gauge 40 10 15 99 34
20
30
30
30 200
[email protected]
30
30
12
Failure Mechanism of Anchored Retaining …
181
(a) (b) B
Tensile force
Tensile force Anchor
Fig. 12.8 Physical modelling of broken anchor head. a Initial condition. b Anchor head itself broken
12.3.4 Modelling of Broken Anchor Head Figure 12.8 gives the experimental system for the broken anchor head used in this study. The mechanism of the broken anchor head is as follows. It is a problem of a simply supported beam of length B, and cross section, ϕ, carrying a tensile force. A series of pullout tests is carried out to clarify the brittleness of the anchor head model as shown in Fig. 12.9a. Figure 12.9b shows typical examples of how the beam of length B, would change the load-displacement curves for the case of wood (ramin) and cross section, ϕ, of 3 mm. Comparing the data obtained from the beam of length B, it can be clearly seen that there is a decreasing maximum load as B increases. In this study, the model anchor head used was wood (ramin), B of 20 mm, ϕ of 3 mm from tensile force 90 N at failure by Toyosawa (1998).
12.3.5 Test Procedure Figure 12.10 shows the model setup in the aluminium model box. The sensor’s pressure value and bending moment on the model sheet pile were initialized prior to the model setup. Preloading for each anchor was adjusted to 9.8 N before testing. The centrifugal acceleration was then increased to 50 g for each test. Once every sensor’s value was stable, the excavation started. To simulate the real accident, the ground in front of the model sheet pile was excavated by the in-flight excavator to a depth of 9.5 m near the end of the sheet pile.
[email protected]
182
K. Itoh et al.
Wood (Ramin)
(a)
B
φ
Load cell
wire Motor jack
(b) 100 B = 23.4 mm
B = 20 mm
B = 30 mm
Load (N)
80 60 40 20 0 0
1
2
3
0
1
2
3
0
1
2
Displacement (mm) Fig. 12.9 Pullout test. a Pullout test apparatus. b Load—displacement curves in pullout test
Fig. 12.10 Model setup
[email protected]
3
12
Failure Mechanism of Anchored Retaining …
183
12.4 Test Results and Discussions 12.4.1 Sequence of Failure Figure 12.11 shows the profile of each model after failure. Figure 12.11a shows the model with sand layer after failure. During the excavation process, the penetration depth of the wall decreased step by step as the excavation proceeded. Failure occurred when the penetration depth of the wall reached about 35 mm and continuous failure with a small displacement emerged with each excavation step. Figure 12.12 shows the ground displacement field behind the model sheet pile
Fig. 12.11 Profile of models after failure. a Sand layer. b Kanto loam and sand layer
Fig. 12.12 PIV analysis in the case of the sand layer
[email protected]
184
K. Itoh et al.
at the final excavation step using PIV (Particle Image Velocimetry, Kikkawa et al. 2006). The failure line angle was about 65°. The model consisting of Kanto loam and sand layers is shown after collapse in Fig. 12.11b. The failure happened suddenly when the penetration depth reached about 60 mm. The failure line’s angle in the sand was about 65°.
12.4.2 Earth Pressure and Bending Moment on Sheet Pile Walls The measured earth pressure (total lateral stress) on the model sheet pile together with depth during increasing centrifugal acceleration and excavation processes is shown in Fig. 12.13. The active and passive earth pressures increased during excavation rather than with increasing centrifugal acceleration. For the sand layer model (Fig. 12.13a), both pressures rapidly increased at an excavation depth of 35 mm. For the Kanto loam and sand layer (Fig. 12.13b), the active pressure exceeded 60 kN/m2 and the passive pressure exceeded 120 kN/m2 at an excavation depth of 60 mm. The variations of the bending moment with the depth of wall are shown in Fig. 12.14. The bending moment increased almost uniformly as the centrifugal acceleration increased. On the other hand, during excavation, the moment at the middle of the pile rapidly increased while the moment of the pile at the excavation surface decreased as the excavation depth increased. Therefore, the pile was bent significantly as the upper part of the pile stuck out while the pile at the excavation surface did not move much. This suggested that the anchor head suffered severe tensile force due to the bent pile.
(b)
10
Acceleration field 10G 20G 30G 40G 50G Excavation depth 0.25 m 0.5 m 0.75 m 1.0 m 1.25 m 1.5 m 1.75 m
Sheet pile wall
8 6 4
Initial level before excavation
2 [Active side] 0 -80 -60 -40 -20
[Passive side]
0
20
40
60
80 100 120 140
Length from sheet pile's end (m)
Length from sheet pile's end (m)
(a)
10
Acceleration field 10G 20G 30G 40G 50G Excavation depth 0.3 m 0.6 m 0.9 m 1.2 m 1.5 m 1.8 m 2.1 m 2.4 m 2.7 m 3.0 m
Sheet pile wall
8 6 4
Initial level before excavation
2 [Active side] 0 -80 -60 -40 -20
0
20
40
60
[Passive side] 80 100 120 140
Lateral Pressure (kN/m 2 )
Lateral Pressure (kN/m 2 )
Fig. 12.13 Lateral pressure on wall. a Lateral pressure on wall (sand layer). b Lateral pressure on wall (Kanto loam and sand layer)
[email protected]
Failure Mechanism of Anchored Retaining …
Length from sheet pile's end (m)
185
(b)
(a)
Sheet pile wall
10 8 6 4
Acceleration field 10G 20G 30G 40G 50G Excavation depth 0.25 m 0.5 m 0.75 m 1.0 m 1.25 m 1.5 m 1.75 m
Initial level before excavation
2 0
Active side
0
1000
2000
Passive side 3000
Length from sheet pile's end (m)
12
Sheet pile wall
10 8 6 4
Acceleration field 10G 20G 30G 40G 50G Excavation depth 0.3 m 0.6 m 0.9 m 1.2 m 1.5 m 1.8 m 2.1 m 2.4 m 2.7 m 3.0 m
Initial level before excavation
2 0
Active side
0
Bending Moment (kNm)
1000
Passive side 3000
2000
Bending Moment (kNm)
Fig. 12.14 Bending moment at wall. a Bending moment at wall (sand layer). b Bending moment at wall (Kanto loam and sand layer)
12.4.3 Tensile Force Acting on Anchor
Fig. 12.15 Tensile force with increasing centrifugal acceleration field and excavation steps
Tensile force acting on anchor (N)
Figure 12.15 shows the measured tensile force acting on the anchor with increasing centrifugal acceleration and excavation steps. The values in this figure were the average of the two anchors which were set in one model. The tensile force increased with increasing acceleration in each test. During the excavation process, tensile force increased gradually prior to the failure in both cases. It should be noted that those tensile forces were almost the same as the capacity of the anchor head as shown in Fig. 12.9, or had already exceeded the capacity. Therefore, it is believed that the active and passive earth pressures increased during excavation and then caused the anchor head to break. As a result the retaining wall and the ground behind the wall collapsed suddenly. [Excavation]
[Increasing acceleration] 120 100 80 60 40
Sand layer Kanto loam & Sand layers
20 0
0
10
20
30
40
Acceleration filed (g)
[email protected]
50
0
1
2
3
4
5
Excavation depth (mm)
6
186
K. Itoh et al.
12.5 Conclusions In this study, the case history of the labour accident involving the collapse of the anchored retaining wall was introduced. In order to understand the mechanism of the accident; we performed the centrifuge model tests in which model ground in front of the anchored retaining wall was excavated using an in-flight excavator. Based on the results of centrifuge model tests, it was revealed that the active and passive earth pressures in the retaining wall increased during excavation and the anchor head exceeded the capacity with respect to the tensile stress. As a result, the retaining wall and ground behind the wall collapsed suddenly.
References Horii N, Itoh K, Toyosawa Y, Tamate S (2006) Development of the NIIS Mark-II geotechnical centrifuge. In: Ng, Zhang and Wang (eds) The 6th international conference on physical modelling in geotechnics. Taylor & Francis, London. pp 141–146 Kikkawa N, Nakata Y, Hyodo M, Murata H, Nishio S (2006) Three-dimensional measurement of local strain using digital stereo photogrammetry in the triaxial test. In Hyodo, Murata and Nakata (eds.). Taylor & Francis, London. pp 61–67 Toyosawa Y, Horii N, Tamate S, Suemasa N (1996) Failure characteristics of sheet pile wall in centrifuge tests. In: Proceedings of geotechnical aspects of underground construction in soft ground, Balkema, pp 225–230 Toyosawa Y, Horii N, Tamate S, Suemasa N, Katada T (1998) Failure mechanism of anchored retaining wall. In: Proceedings of the International Conference on centrifuge 98 Tokyo, Rotterdam, Balkema, pp 667–672
[email protected]