herbert hoover dike rehabilitation project herbert ... - City of South Bay
Recommend Documents
Sep 29, 2011 - as secretary of commerce under Presidents ... mined to use the Commerce Department to ... public works as a solution once they started.4.
4.2 Proposed Host Architecture for Each Bolvedere Subsystem . ...... a feel as to what a NetFlow record contains) by including logging of subnet masks and AS.
Riehl's earliest independent work on the jet stream ... the jet stream via observations aboard Navy aircraft ... most elementary form [as found in explanations for.
May 19, 2007 ... remains an essential text in sociology and management training. Herbert A.
Simon, Administrative. Behavior (NY: Macmillan, 1947), James G.
Try one of the apps below to open or edit this item. pdf-1823\herbert-hoover-forgotten-progressive-the-library-of-americ
... a problem loading more pages. Retrying... pdf-1296\herbert-hoover-president-of-the-united-states-by-edgar-eugene-rob
Herbert Hoover: forgotten progressive, delcredere understands the regime, ... Robert C., Jr.: Chapel Hill: The Universit
April: Herbert von Karajan wird als zweiter Sohn des Primararztes Dr. Ernst von
Karajan und dessen Frau Martha, geborene Kosmac, in. Salzburg geboren.
Feb 1, 2014 - Keywords: Adrenal, lipoadenoma, lipomatous metaplasia, adipose change, fatty change ... A case of myxoid adrenocortical carcinoma with.
Apr 27, 2012 - Momordica charantia var. charantia, and CBM12, M. charantia var. muricata. This map consists of 108 AFLP markers and five qualitative.
... sensitivity to source credibility cues. The potential of children as eyewitnesses. Law and Human. Behavior , 3, 295-
herbert hoover dike rehabilitation project herbert ... - City of South Bay
Internal erosion (seepage and piping). Through embankment. Through foundation. Culvert structures. Soil erosion into con
HERBERT HOOVER DIKE REHABILITATION PROJECT Project Update for the City Commission of South Bay Ingrid Bon, P.E. U.S. Army Corps of Engineers Jacksonville District September 2015
BUILDING STRONG®
Presentation Outline Overview Problems System-Wide Reduction Approach Dam Safety Modification Study Reach 1 Rehabilitation Culvert Replacement Program Rehabilitation Progress
2
BUILDING STRONG®
Herbert Hoover Dike Overview Lake Okeechobee is approximately 720 square miles Basin is over 5,600 square miles Average water depth is 9 feet One foot of rainfall runoff from the basin can result in a three to four foot rise of the lake During large flood events, water can flow into the lake much faster than it can be released Lake Okeechobee
3
BUILDING STRONG®
Congress Authorizes Herbert Hoover Dike in 1930
Over 3,000 lives were lost by the 1926 and 1928 hurricanes Significant economic impacts HHD first authorized in 1930 Multiple authorizations
North Shore - 16 miles South Shore - 68 miles
4
BUILDING STRONG®
Herbert Hoover Dike Today 143 miles of embankment around Lake Okeechobee
Risk Assessment – Analysis performed on 32 segments within the 7 common inundation zones to identify and prioritize remediation
Modification Report – Tentatively Selected Plan is scheduled to be finalized in Fall 2015 with final report approval by Summer 2016
BUCKHEAD RIDGE
BRIGHTON SEMINOLE INDIAN RESERVATION
Fisheating Creek
LAKEPORT
LAKE OKEECHOBEE
PORT MAYACA
PAHOKEE
MOORE HAVEN Calooshatchee River
CLEWISTON
Impact – Recommend and
LAKE HARBOR SOUTH BAY
approve the final risk reduction measures needed for the entire system with implementation starting in 2019.
8
BELLE GLADE
BUILDING STRONG®
HHD Reach 1 Rehabilitation Approval from 2000 HHD Major Rehabilitation Report Completed – 21.4 miles of cutoff wall installed between 2007 and 2013 Planned – Cutoff wall tie-ins to 3 existing structures and 1 bridge with contract award in FY16 Complete the continuous seepage barrier through Reach 1 providing the risk reduction benefits to the adjacent communities
Reach 1 Cutoff Wall Status Cutoff Wall Installation Complete Cutoff Wall Gap Closures Planned
9
BUILDING STRONG®
Reach 1 Cutoff Wall Extension Approval from 2015 HHD Major Rehabilitation Report Supplement Planned – 6.6 miles of cutoff wall installed with contract award in FY17 and completion in 2020 Impact – Final embankment remediation project to complete repairs reducing risks to inundation Zone A
Cutoff Wall Extension
Complete the continuous seepage barrier through Inundation Zone A providing the risk reduction benefits to the adjacent communities and allow a recommendation for accreditation to FEMA for this area of HHD
10
BUILDING STRONG®
HHD Culvert Replacement Program Approval from 2011 HHD Culvert Letter Report Completed – 1 removal and 2 replacements Ongoing – 8 contracts with 16 replacements completed by 2020 Planned – 7 contracts with 10 replacements completed by 2022 Complete repairs at the highest points of failure through the HHD system Note: 3 abandonments may be combined with fixes from the DSMS and are not currently scheduled Water Control Structure (Culvert ) Status Construction Contract Complete Construction Contract Ongoing Construction Contract Planned
11
BUILDING STRONG®
KI-2
Water Control Structure (Culvert) Replacements - Construction Contract Awards