Manuscript
Click here to access/download;Manuscript;Manuscript.docx
1 2
Identifying Early Indicators of Manageable Rework Causes and Selecting Their Mitigating Construction Best Practices
3
Elnaz Safapour, S.M.ASCE1 and Sharareh Kermanshachi, Ph.D., P.E., M.ASCE2
4 5
1
Ph.D. Student, Department of Civil Engineering, University of Texas at Arlington, 425 Nedderman Hall, 416 Yates Street, Arlington, TX 76019. E-mail:
[email protected]
6 7 8
2
(Corresponding author) Assistant Professor, Department of Civil Engineering, University of Texas at Arlington, 425 Nedderman Hall, 416 Yates Street, Box 19308, Arlington, TX 76019. E-mail:
[email protected]
9
ABSTRACT
10
Many large-scale construction projects suffer from the issuance of rework that ultimately leads to
11
substantial cost overruns and major scheduling delays. Scholars and practitioners worldwide have
12
assessed the impact of these changes and the critical causes behind them, and found it difficult to
13
mitigate after the rework has occurred. Thus, it is important to identify the early indicators of
14
manageable rework causes and implement the appropriate mitigating strategies prior to their
15
occurrence. Therefore, the aim of this study is to identify indicators of manageable rework causes
16
(IMRCs) and select the appropriate construction Best Practices (BPs) in order to reduce the value
17
of manageable and controllable rework. To fulfill the objectives of this study, 51 manageable
18
causes of rework were identified through a comprehensive literature review. According to the
19
nature of BPs, the identified IMRCs were classified into three main categories: organization,
20
project, and people. Then, 44 case study projects were collected and analyzed. As information
21
regarding other aspects of the projects was required for this study, a questionnaire survey was
22
developed and conducted to collect data from the construction projects. For this purpose, a
23
representative from each stated project was selected and asked to fill out the survey. Finally, 32
24
significant IMRCs, belonging to 13 attributes, were determined. The project management team
25
(PMT) is commonly responsible for preparing the plan, building an effective team, and monitoring
26
the process; therefore, the experience of the PMT in the design and/or construction phase, and
1
27
number of PMTs who work in a construction project are the most important indicators and record
28
the highest weights in deriving rework. Next, all of the identified BPs by Construction Industry
29
Institute (CII) were investigated and among them, 10 BPs were found significantly beneficial to
30
decrease the value of rework associated with IMRCs. The implementation of Front-End Planning
31
determines the feasibility of a project and evaluation of the conceptual scope during the
32
preplanning phase; thus, the design errors that are due to challenges regarding finance and scope
33
attributes can be decreased. The outcomes of this study will help stakeholders and project
34
managers (PMs) identify the indicators of rework early in construction projects and select the
35
appropriate BPs, thereby reducing the extra cost of rework and improving the project time and cost
36
performance.
37
INTRODUCTION
38
Change orders due to design errors and modifications are common and almost inevitable in all
39
types of construction projects (Li and Taylor 2014). They affect the cost of a project, create
40
scheduling delays, and decrease productivity (Love 2002; Arashpour et al. 2014; Li and Taylor
41
2014). Therefore, rework plays an important role in a project’s success or failure. Because of the
42
uniqueness of the budget and schedule estimation of each construction project, as well as the
43
availability of resources for planning, such as time, money and work force, change orders and
44
rework vary significantly from project to project. Taylor and Ford (2006) defined rework as “work
45
discovered to require change (either through errors, omissions, or regulation changes).”According
46
to the Love’s and Facade’s studies, the total values of rework in civil infrastructure projects were
47
found to be 10.29% (Love et al. 2010), and 16.5% (Forcada et al. 2017a) of the contract value.
48
Hence, it is critical to identify the root causes of rework and manage them to reduce their
2
49
unfavorable impact on the execution of construction projects (Love and Smith 2003; Zhang et al.
50
2012; Palaneeswaran et al. 2014; Dehghan and Ruwnapura 2014).
51
Best practice strategies can improve the performance of construction projects and can assist in
52
effectively managing large-scale projects (CII 2012). The Construction Industry Institute (CII)
53
explained BP as “a process or method that leads to enhanced project performance, when executed
54
effectively.” CII (2012) defined and introduced the following fourteen BPs: Front-End Planning,
55
Alignment, Constructability, Materials Management, Planning for Start-up, Team Building,
56
Partnering, Quality Management, Lessons Learned, Benchmarking and Metrics, Change
57
Management, Dispute Prevention and Resolution, Project Risk Assessment, and Zero Accidents
58
and Techniques. As the Planning for Start-Up strategy is commonly implemented when a project
59
is almost completed (CII 2012), it does not significantly contribute to the management and
60
reduction of the rework workload and was not included in this study. In addition, as the purpose
61
of implementing the Benchmarking and Metrics strategy is to measure the utilization of CII best
62
practices according to the measured project performance (CII 2012), it does not help with the
63
management and reduction of the rework workload according to the presented IMRCs in a project,
64
and was therefore excluded from this study. Change Management was likewise excluded because
65
its implementation directly affects all aspects of change orders and rework. In summary, all of the
66
BPs, which could potentially reduce the value of rework, were investigated to determine their
67
impact on the reduction of the value of manageable design changes in construction projects.
68
In this study, through a comprehensive literature review, 51 manageable causes of rework were
69
identified according to the studies of Hsieh et al. (2004); Kean et al. (2010); Love et al. (2012),
70
Forcada et al. (2014); Karthick et al. (2015); Ye et al. (2015). Based on the CII comprehensive
71
research (CII 2012), among the identified manageable causes of rework, 35 were found
3
72
manageable by implementing BPs during the execution of a construction project. The remaining
73
causes of rework were mostly out of control (e.g. weather condition), and need more resources and
74
allocations to be managed (e.g. owner’s change of schedule due to financial problems).
75
According to the research conducted by the Construction Industry Institute (CII 2012), the
76
implementation of BPs assists in the management of characteristics associated with organizations,
77
projects, and team members. Inspired by works of Love et al. (2012) and Forcada et al. (2014), the
78
prepared list of manageable causes of rework was classified into three main categories:
79
organization, project, and people.
80
As the overall goal of this study is to determine IMRCs, and investigate how implementation of
81
appropriate best practices reduces value of rework associated with challenges of IMRCs in
82
construction projects; therefore, this study seeks to answer the following questions:
83
Q1. What are the early indicators of manageable rework causes?
84
Q2. What are the appropriate best practices to reduce the value of rework associated with
85
indicators of manageable rework causes?
86
The following objectives were formulated to answer the research questions:(1) identify potential
87
IMRCs through existing literature;(2) classify the identified IMRCs based on the previous
88
studies;(3) determine significant IMRCs using statistical methods;(4) investigate the benefits of
89
implementing each best practice in addressing the issues of IMRCs; and (5) calculate how much
90
each BP contribute to the reduction in the value of rework.
91
In summary, the ability to predict design changes early in construction projects offers significant
92
benefits to industry practitioners, specifically stakeholders (i.e., owners, engineers, and
93
contractors) and project managers. Furthermore, implementing the appropriate best practices at the
94
right time assists in the management of undesired consequences and enables the reduction of the
4
95
dollar value of the rework. For instance, the scope of a large-scale project is commonly complex,
96
and precise clarification of the project’s scope occurs in the construction phase. Therefore, owner
97
entities can allocate sufficient funds in the preplanning phase to implement the appropriate
98
strategy. Implementing a suitable strategy results in early clarification of a project’s scope and
99
helps reduce the rework of a project. As another example, when designers lack sufficient skills in
100
new technology, implementing an appropriate strategy might be beneficial for the prevention of
101
design errors.
102
The paper is organized as follows. First, a literature review is presented. The research approach
103
for this study is then described, with a detailed description of case studies and data collection from
104
44 construction projects. Then, the process and result of the descriptive data analysis is described.
105
The procedure of how significant IMRCs were determined is discussed and presented. Next,
106
research findings are discussed to depict how implementation of best practices manages the value
107
of rework associated with IMRCs. Lastly, verification of the outcomes of this study is described.
108
LITERATURE REVIEW
109
There are several definitions and interpretations of rework in existing literature in the area of
110
construction management (Love 2002). CII (2001) characterized rework in the construction phase
111
as activities that have to be done more than once, or activities that remove previous work installed
112
as part of a project. Similarly, Josephson at al. (2002) defined rework as useless output that
113
commonly occurs due to mistake through execution of a construction project.
114
Investigation of root causes of rework assists in managing them effectively (Hwang et al. 2009).
115
Many studies have been conducted worldwide to investigate the root causes of rework and their
116
unfavorable consequences on construction projects (Hwang et al. 2009; Love et al. 2010, 2016a;
117
Ye et al. 2015, Forcada et al. 2017b). According to the previous studies, the causes of rework were
5
118
mainly classified as constructability (Feng 2009); material supply (Hwang and Ho 2012; London
119
and Singh 2013); project management team (Arashpour et al. 2012); skill (Arashpour and
120
Arashpour 2011); and project scope (Tuholski 2008). Love et al. (2012) and Forcada et al. (2014)
121
concluded that there are potential latent problems inherent in project systems, such as
122
organizational issues (e.g. lack of quality management), project issues (e.g. definition of scope),
123
and individual issues (e.g. work experience of staff). The mentioned authors also found that these
124
issues could set the stage for designers to make mistakes. Love et al. (2012) labeled the established
125
orthodoxy as people, organization, and project systems. These nomenclatures highlighted the
126
process that enables the mapping of dependencies that affect error prevention. This mapping aids
127
prevention of design errors.
128
The procedure of rework assessment and management are usually time consuming and leading
129
cost overruns if it is not well organized at the appropriate time. As complexity in modern
130
construction projects increases, the stricter rework assessment and management are required in
131
order to minimize schedule delays and cost overruns. (Love et al. 2015; Love et al. 2016a, 2016b).
132
Zaneldin (2000) explained that through the early stage of a design phase, change orders (rework)
133
might be issued with minimum cost overruns. Lack of familiarity with ways to manage change
134
orders (rework) appropriately often leads to serious schedule delays and cost overruns (Alnuaimi
135
et al. 2010). Therefore, change orders (rework) are easier to manage during the earlier phases,
136
because, to put it simply, they make it possible to avoid modifications (Arain and Pheng 2007;
137
Love et al. 2015; Du et al. 2016). Palaneeswaran et al. (2014) stated that a systematic design audit
138
for construction projects would be most effective for reducing the number of reworks. Zhang et al.
139
(2012) generated a model to reduce rework that focused on managing a continuous improvement
140
loop in four main stages: (1) rework tracking and cause classification, (2) evaluation of rework
6
141
and its causes, (3) corrective action planning, and (4) integration of changes into the total
142
management system.
143
Furthermore, as mentioned earlier, several strategies have been introduced by CII to practitioners
144
and scholars to enhance project performance and reduce change orders. In this regard, many
145
significant studies have been conducted to investigate the impact of implementing single or
146
multiple BPs in order to improve the management of construction projects (CII 2012; Akpan et al.
147
2014; Du et al. 2016; and Safapour et al. 2017). Although implementation of all best practices is
148
beneficial for enhancing project performance, it is not feasible (Safapour et al. 2017). There is a
149
gap of information pertaining to how to select the appropriate strategies based on the indicators of
150
manageable rework causes in construction projects. Therefore, a thorough investigation and
151
analysis of how to utilize the construction best practices in construction projects is needed.
152
Thus, the focus of this study is to determine IMRCs, and to define the benefits of adoption of BPs
153
in decreasing the value of rework due to challenges associated with IMRCs. For this purpose, as
154
stated earlier, the appropriate and related best practices for mitigating IMRCs were selected. The
155
definitions of these BPs were stated in Table 1.
156
Table 1. List of Construction Best Practices with Their Definition
157
RESEARCH METHODOLOGY
158
To fulfill the objectives of this study, a seven-step research methodology was developed and
159
implemented, as shown in Fig. 1. This study was initiated with a comprehensive review of
160
literature to identify potential indicators of rework causes (IMRCs) that can be managed through
161
implementation of the construction best practices. These early indicators were then classified
162
according to the previous studies. In the third step, 44 case studies of construction projects were
163
collected. As information regarding other aspects of the projects was needed for this study, a
164
structured questionnaire was developed to collect the required information (e.g., dollar value of 7
165
rework, implementing level of best practice strategies) from the stated projects. A descriptive data
166
analysis was conducted in the next step. In step 5, quantitative analyses were performed to
167
determine the IMRCs.
168
Fig. 1. Research methodology approach
169
Depending on the type of data that was collected from the survey, different statistical tests were
170
utilized. Table 2 summarizes the basic formal statistical methods that were used for the quantitative
171
analysis in this study. In the last step, the appropriate BPs were investigated and determined. The
172
weight of each early indicator of manageable rework causes was then identified, using Cohen’s d
173
method.
174
Cohen’s d parameter (Cohen 1988) was applied to investigate the extent of each manageable
175
rework indicator. Cohen’s d yields information about the difference in the means of two sample
176
groups, divided by standard deviations. The raw data for the two sample groups was used to
177
formulate the following equation for the two-sample t-test: M2 −M1
Cohen′ s d =
178
SDpooled
(1)
179
where M1 and M2 are the mean difference of two sample groups (dollar value of rework which is
180
associated with significant manageable rework indicators by two-sample t-test), respectively, and
181
the denominator is pooled standard deviation. SDpooled = √
182
(n1 −1)SD21 +(n2 −1)SD22 n1 +n2 −2
(2)
183
According to equation (2), SD1 and SD2 correspond to standard deviation of the first and second
184
groups, respectively. In addition, n1 and n2 are related to the first and second sample sizes,
185
respectively.
186
Table 2. Statistical Analysis Methods
8
187
Step 6 of this study was divided into two sub-steps: Step 6a and Step 6b. In Step 6a, the significant
188
best practices were determined to reduce the dollar value of design changes and/or modifications.
189
In Step 6b, the total weight of each best practice associated with attributes of indicators of
190
manageable rework causes were recorded and presented. In the last step, two case study projects
191
were utilized to measure the reduction in the value of rework by implementing BPs.
192 193
STEP 2: IDENTIFY AND CLASSIFY POTENTIAL MANAGEABLE REWORK INDICATORS
194
Fifty-one (51) manageable causes of rework were identified from previous studies, as mentioned
195
earlier. According to the study of CII (2012), among these causes, 35 were found to be manageable
196
by implementing the best practices. Then, the IMRCs were classified into three main categories
197
(organization, project, and people). These nomenclatures were selected based on the nature of the
198
BPs to manage a project’s characteristics associated with organization, project, and team members
199
that were thoroughly described in CII research (2012) and inspired by studies conducted by Love
200
et al. (2012), and Forcada et al. (2014).
201
Next, inspired by previous studies (Hsieh et al. 2004; Love et al. 2008, Sun and Meng 2009; Love
202
et al. 2012; Ye et al. 2015), the three mentioned categories were classified into thirteen attributes,
203
as shown in Fig. 2. These classifications and attributes led to substantial progress in understanding
204
IMRCs. Consequently, this clarification assists in the prevention of design errors.
205
Fig. 2. Classification of indicators of manageable rework causes
206
As illustrated in Fig. 2, the IMRCs in the organization category were classified into bureaucracy,
207
participant, and communication attributes. Similarly, the IMRCs in the project category were
208
classified into management team, location, design and technology, material resources, scope,
209
partnership, and finance attributes. The indicators in the category of people were classified into
210
skill, field craft experience, and socio-culture attributes. As stated earlier, the purpose of selecting
211
an appropriate terminology for the attributes was to make the IMRCs more understandable in order 9
212
to facilitate greater reduction in the value of rework. For instance, the terminology of design and
213
technology was selected because design and technology management is an important factor
214
influencing rework in construction projects (Hwang et al. 2009). The other attribute is socio-
215
culture, corresponding to cross-cultural differences and conflicts between team members. As an
216
example, the IRMC-32, percentage of craft labor sourced locally, was associated with the socio-
217
culture attribute because the participation of a construction project’s team members who are from
218
different locations or countries may result in challenges associated with different cultures.
219
STEP 3: PERFORM DATA COLLECTION
220
After identification and classification of potential IMRCs, 44 construction case study projects were
221
collected. The research team then developed a structured questionnaire to collect data
222
comprehensively associated with the same projects, as stated earlier.
223
The survey questions were categorized into three groups: (1) general project description, (2)
224
potential indicators of manageable rework, and (3) level of implementation of best practices. Fig.
225
3 shows two examples of questions included in the survey. As shown in this figure, collected
226
responses were in two forms: continuous number and seven-point Likert scale. The first section of
227
the survey consisted of 20 questions associated with general information and project
228
characteristics. The second section consisted of 35 questions that were related to the potential
229
manageable causes of rework. In the third section, ten questions addressed the level of
230
implementation of the most applicable rework best practices.
231
Fig. 3. Two example questions of the survey
232
To avoid respondents’ confusion and collect consistent data, the definitions of best practices were
233
included at the beginning of the questionnaire. The pilot test was administered to four experienced
234
practitioners from industry to examine the clarity of each question. After the questionnaire was
235
validated, it was finalized and distributed among experienced industry professionals. The survey 10
236
process was entirely set up and managed through an online system. After sending two follow-up
237
emails, 44 completed surveys gathering more data related to the case studies were collected.
238
The demographic information of survey respondents is shown in Table 3. As illustrated in this
239
table, the current role of 69% of the survey respondents was project manager. The purpose of
240
selecting the most upper-level respondents was to collect reliable and valid data corresponding to
241
construction projects.
242
Table 3. Respondents’ Demographic Information
243
STEP 4: PERFORM DESCRIPTIVE DATA ANALYSIS
244
Information from 44 case study projects is shown in Table 4. Among the projects, 31 (71%) of
245
them were heavy industrial projects, and the remaining 13 (29%) were light industrial,
246
infrastructure, and building projects. This table shows that 33 projects (75%) were located in the
247
USA, and the rest (25%) were in Canada, China, Prue, Senegal, Indonesia, Saudi Arabia, Brazil,
248
and the Netherlands. The maximum project size of the collected case studies was $5 billion for a
249
heavy industrial project located in Saudi Arabia with a 42-month baseline schedule.
250
Table 4. Information of Case Study Projects
251
Descriptive data analyses associated with baseline and actual budgets and schedules, as well as
252
rework dollar values corresponding to 44 construction projects, are shown in Table 5.
253
Table 5. Descriptive Data Analysis of Collected Data in Construction Phase
254
To avoid any bias created by larger projects on the results, the values of the issued rework were
255
normalized based on the size of the projects. To calculate the normalized value of rework for any
256
project, the value of rework was divided by the value of baseline budget for the construction phase.
257
These values were recorded and used for the rest of the analyses conducted in this study.
258
STEP 5: DETERMINE SIGNIFICANT IMRCs
11
259
The P-Values corresponding to the significant IMRCs are shown in Table 6. As there were two
260
types of data (continuous and seven-point Likert scale) collected from the survey, the two-sample
261
t-test and Kruskal-Wallis test were performed. As stated earlier, 51 manageable causes of rework
262
were initially found through existing literature. Among these causes, 35 were found manageable
263
by implementing the BPs. Finally, 32 significant IMRCs were determined, as shown in Table 6.
264
In the first, second, and third columns of Table 6, the names of the three main categories of
265
attributes (organization, project, and people) and a list of significant IMRCs are presented,
266
respectively. The fourth column contains a list of causes of rework, based on previous studies. In
267
other words, Column 4 portrays the origination of each IMRC through existing literature.
268
Abbreviations of indicators of manageable rework causes and their associated numbers (e.g.
269
IMRC-2) were used. Column 5 shows the results of the statistical data analyses. As presented in
270
Table 6, this study initially conducted the statistical analysis at the 0.05 significance level, and
271
then raised it to 0.1 to include more indicators of manageable rework causes.
272
Considering IMRC-10, reaching an agreement, which belongs to the organization category and
273
communication attribute, can be very time consuming due to conflicts between designers.
274
Consequently, the process of decision making by designer entities takes a lot of time and the
275
possibility of design changes increases.
276
In the case of IMRC-19, which belongs to the project category and design and technology
277
attribute, if the design of a system is complex, an increased number of errors is more probable due
278
to deficiencies in the designers’ knowledge and/or experience. Ultimately, these errors will cause
279
design changes and modifications during the construction phase. Poor quality of materials (IMRC-
280
25, belonging to the project category and material resources attribute) leads to replacement of the
281
materials and results in modifications of the design. As shown in Table 6, if the designers lack
12
282
skills in working with new technologies in the design phase (i.e. IMRC-29, belonging to the people
283
category and skill attribute), the probability of design errors in a complex project increases.
284
Table 6. Significant Indicators of Manageable Rework Causes and Corresponding P-Value
285 286
STEP 6a: DETERMINE BEST PRACTICES THAT REDUCE VALUE OF REWORK ASSOCIATED WITH IMRCs
287
In this section, the selection of suitable BPs to reduce the value of rework corresponding to issues
288
related to IMRCs, was investigated, and the results of the P-Values are shown in Table 7. Because
289
the implementation level of BPs was asked in a survey as a seven-point Likert scale question, the
290
Kruskal-Wallis test was utilized to investigate whether a significant difference existed between the
291
median values of the best practices implementation level associated with IMRCs.
292
As depicted in Table 7, implementation of Front-End Planning is effective in managing the
293
challenges related to bureaucracy in an organization. Bureaucracy is a time-consuming systematic
294
structure that handles the business of an organization. Therefore, with implementation of Front-
295
End Planning that allocates appropriate functions, rework associated with bureaucracy can be
296
reduced.
297
Adoption of the Team Building strategy results in clear expectations and improved commitment
298
among team members. In addition, this strategy promotes trust and accountability among members
299
of an entity. Consequently, utilization of Team Building reduces the value of rework due to
300
communication challenges within owner stakeholders, and designer and contractor entities.
301
Utilization of the Constructability strategy assists in the development of plans and specifications.
302
For instance, through implementation of this BP, a technical software such as the Building
303
Information Modeling Technique for Coordination is used to review architectural and engineering
304
disciplines for proper coordination. Thus, it was perceived that when the PMT has insufficient
13
305
work experience and/or the design of a project is complex, the adoption of Constructability would
306
be beneficial to reduce the value of rework.
307
The implementation of Quality Management results in regular audits and analyses of historical
308
data to identify design errors. Furthermore, this strategy performs root cause analyses and takes
309
corrective actions at the right time. As a result, when there are several locations and/or countries
310
involved in the design phase, the adoption of Quality Management is beneficial to decrease the
311
number of design errors.
312
It is important to mention that all 44 case studies implemented the Safety strategy in their projects,
313
and it is impossible to determine whether implementing this strategy significantly reduces the
314
challenges associated with manageable causes of rework. Therefore, it was concluded that
315
investigation of this strategy would not assist in determining whether the adoption of Safety would
316
reduce the dollar value of rework associated with IMRCs, so it was excluded from the prepared
317
list of BPs.
318
As depicted in Table 7, implementation of Front-End Planning is effective for manage the
319
challenges related to the bureaucracy in an organization. Bureaucracy is a time-consuming,
320
systematic structure that handles the business of an organization. Therefore, with implementation
321
of Front-End Planning, which allocates appropriate functions, rework associated with bureaucracy
322
can be reduced.
323
Utilization of the Constructability strategy assists in the development of plans and specifications.
324
For instance, through implementation of this BP, a technical software, such as the Building
325
Information Modeling Technique for coordination can be used to review architectural and
326
engineering disciplines for proper coordination. Thus, when the PMT has insufficient work
14
327
experience and/or the design of a project is complex, the adoption of Constructability would be
328
beneficial to reducing the value of rework.
329
Implementation of Quality Management regular audits and analyses of historical data to identify
330
design errors. Furthermore, this strategy performs root cause analyses and takes corrective actions
331
at the right time. As a result, when there are several locations and/or countries involved in the
332
design phase, the adoption of Quality Management would be beneficial to decrease the number of
333
design errors.
334 335
Table 7. Result of Kruskal-Wallis Test of BPs to Reduce the Value of Rework Associated with IMRCs
336 337
STEP 6b: CALCULATE ATTRIBUTES
338
The value of effect sizes corresponding to IMRCs, as listed in Table 8, were calculated by using
339
Cohen’s d method. Then, the values of the effect sizes were normalized, as indicated in Table 8.
340
These normalized values were calculated based on the value of effect size associated with each
341
IMRC, divided by the summation of all values of effect sizes. The maximum normalized weight
342
(6.06%) of IMRCs corresponds to the experience of the project manager in the construction phase
343
(IMRC-15). As shown in Table 8, the normalized weight of the number of PMTs who participated
344
in the project (IMRC-12), and the experience of the PM in the design phase (IMRC-14) were
345
recorded as 5.87% and 5.68%, respectively. The PMT commonly has two important tasks: to direct
346
a project to achieve objectives quickly, and to improve relations in the organization to attain higher
347
efficiency. Therefore, the highest normalized weights that were recorded corresponded to the
348
PMT.
WEIGHT
OF
BEST
PRACTICES
FOR
REWORK
349
Table 8. Weight of Early Indicators of Manageable Rework Causes
350
The weights of the BPs for managing rework attributes were calculated and are shown in Table 9.
351
The results of this table show that for reduction in the value of rework corresponding to the 15
352
participant attribute (i.e., owner, designer, and contractor stakeholders) Front-End Planning and
353
Dispute Prevention produced the greatest support. Weights corresponding to Front-End planning
354
and Dispute Prevention were similarly recorded as 0.0416. For more clarification as to how these
355
weights were recorded, consider Front-End and Dispute Prevention in Table 7, corresponding to
356
participant attribute. As can be seen, IMRC-6 (number of owner organizations) was significant in
357
this attribute for both mentioned strategies. Table 8 illustrates that the weight of IMRC-6 was
358
calculated as 0.0416. Therefore, as shown in Table 9, weights for both Front-End Planning and
359
Dispute Prevention associated with the participant attribute were recorded as 0.0416. Team
360
Building promotes trust and accountability among project participants and creates shared goals
361
among stakeholders, thereby reducing potential time-consuming disagreements and conflicts.
362
Furthermore, adoption of Dispute Prevention is important for early recognition of the indicators of
363
conflicts among participants and for forming a strong commitment to avoid them.
364
In case of Team Building, this strategy promotes trust and accountability among project
365
participants and creates shared goals between stakeholders; therefore, reducing potential time-
366
consuming disagreements and conflicts will occur. Furthermore, adoption of Dispute Prevention
367
is important to recognize the indicators of conflicts early among participants and form of a strong
368
commitment to avoid them.
369
Table 9 illustrates that Constructability offers the greatest support for reduction in design errors
370
related to attributes of management team and design and technology. As shown in Table 8, the
371
weights of Constructability corresponding to management team and design and technology
372
attributes were calculated as 0.0568 and 0.0416, respectively. For more clarification of how the
373
weight of design and technology (0.0416) was calculated, consider Constructability in Table 7,
374
which is related to the design and technology attribute. As shown in this table, IMRC-19 (difficulty
16
375
in system design) and IMRC-20 (design completion before construction phase) were determined
376
as significant for Constructability related to the design and technology attribute. Table 8 illustrates
377
that weights of IMRC-19 and IMRC-20 were calculated as 0.0170 and 0.0246, respectively. As a
378
result, the weight of Constructability for the design and technology attribute is recorded as 0.0416
379
(the summation of 0.0170 and 0.0246). This strategy benefits design quality control and clash
380
checking and decreases design errors that are due to the design management team’s lack of
381
experience in working with new technologies during the design phase.
382
Table 9. Weight of Each Best Practice for Manageable Rework Attributes
383
As indicated in Table 9, the adoption of Front-End Planning leads to early clarification of the
384
project’s goal to ensure that the scope and technical specifications are well defined and
385
documented, and results in the reduction of late design changes of the scope attribute. This strategy
386
creates finance strategy that makes project cost and schedule targets more reliable. Therefore, this
387
strategy strongly supports the finance attribute.
388
Table 9 shows that the utilization of Risk Assessment is highly recommended when team members
389
have insufficient required skills. This strategy provides a foundation on which to build the
390
compliance program with training, monitoring, and auditing; thus, this BP reduces the number of
391
issued design modifications in a construction project. In addition, it was perceived that when
392
different locations and/or countries are involved in the design and/or construction phase, the
393
adoption of Risk Assessment can be beneficial to establishing structured and disciplined regular
394
audits.
395
As shown in Table 9, the implementation of Front-End Planning and Alignment strategies are
396
highly suggested to support partnership challenges. These strategies adopt a standard template for
397
stakeholders to communicate about project goals and scope in order to achieve the success of a
17
398
project. Moreover, these strategies lead to performing required analyses to align requirements and
399
expectations of stakeholders.
400
Since communication within and between multicultural teams has a strong impact on the project’s
401
performance, the implementation of Lesson Learned will enhance a project’s cost and schedule
402
performance when participating craft laborers in a project are from different cultures (i.e. socio
403
culture attribute). The Lesson Learned strategy benefits the utilization of knowledge regarding the
404
cultural differences to supervise effectively the execution of a project.
405
STEP 7: IMPLEMENT THE RESULTS
406
Two heavy-industrial case study projects were selected to verify the results of the present study.
407
As illustrated in Table 10, the baseline budget of the construction phase of each of the two projects
408
was around $5 million. To obtain the results quickly, the case studies with short construction phase
409
durations were purposely selected. This table shows that the baseline schedules of the construction
410
phase for the first and the second projects were 8 and 7 months, respectively.
411
As illustrated in Table 10, thirteen, and ten IMRCs were presented in the first and second projects,
412
respectively. Five BPs (Constructability, Material Management, Quality Management, Lesson
413
Learned, and Risk Assessment) were implemented in the first project, and the value of rework was
414
approximately $ 1.2 million. For the second project, only Material Management, Lesson Learned,
415
and Risk Assessment were implemented. The value of the derived rework for the second project
416
was around $1.7 million. The results demonstrated that the implementation of Constructability and
417
Quality Management led to a reduction in the value of the rework of approximately $600 thousand
418
for two industrial projects with similar construction phase baseline budgets and schedules.
419 420
Table 10. Breakdown of Information for Two Case Study Projects Used for Implementation of Results
18
421
As shown in Table 10, indicators of rework associated with the management team attribute (i.e.
422
IMRC-14, low PM experience in design phase) and design and technology attribute (i.e. IMRC-
423
19, complex system design) were presented in the first and the second projects. As shown in Table
424
9, adoption of Constructability in the first project reduced the dollar value of rework associated
425
with the management team and design and technology attributes. Furthermore, Table 10 illustrates
426
that the indicators of rework associated with the management team (i.e., IMRC-14: low PM
427
experience in design phase) and (i.e., IMRC-15: Low PM experience in construction phase) were
428
present in both projects. The indicators of the location attribute (i.e., IMRC-16, several execution
429
locations in design phase) and (i.e. IMRC-17, two countries involved in design phase) were
430
likewise presented in the first and second projects. Thus, as shown in Table 9, implementation of
431
Quality Management assisted within reducing the dollar value of rework due to challenges
432
associated with the management team and location in the first project. As a result, adoption of
433
Constructability and Quality Management led to a lower dollar value of rework in the first project.
434
CONCLUSION
435
This research has two goals: (1) to determine the early indicators of manageable rework causes;
436
(2) to select the appropriate best practice strategies in order to reduce dollar value of rework
437
associated with manageable rework attributes. In this regard, 32 significant indicators were
438
identified belonging to three main categories and thirteen attributes. Furthermore, 10 appropriate
439
best practices were selected in order to reduce the dollar value of rework associated with rework
440
attributes.
441
Since the PMT commonly is responsible for the planning, execution, and closing of any
442
construction project, the experience of the PMT in the design and construction phases (i.e., IMRC-
443
15, IMRC-14) and the number of project management staff who work on the project (i.e. IMRC-
19
444
12) were determined to be the three important indicators with the highest weights in construction
445
projects. This study also concluded that implementation of Alignment and Front-End Planning
446
assist in the effective management of challenges that are due to bureaucracy in a construction
447
project. Adoption of the mentioned strategies forms an organized framework in which to establish
448
businesslike communication within an organization system, which reduces the number of design
449
changes throughout a construction project. In addition, this study demonstrated that Quality
450
Management benefits when several countries are participating in the design and/or construction
451
phase, because regular audits and analysis of the collected data are conducted to prevent potential
452
design errors. It is believed that the outcomes of this study will assist stakeholders and
453
corresponding project managers in early identification of manageable rework causes and timely
454
implementation of appropriate best practices to attain minimum design modifications throughout
455
the execution of construction projects.
456
ACKNOWLEDGMENTS
457
The authors would like to appreciate the editor of this journal and three anonymous reviewers for
458
their constructive comments that contributed in adding to the value of the manuscript.
459
REFERENCES
460 461 462
Akpan, E. O. P., Amade, B., Okangba, S. E., and Ekweozor, C. O. (2014). “Constructability practice and project deliver processes in the Nigerian construction industry.” J. Build. Perform. 5 (1), 10-21.
463 464 465
Alnuaimi, A. S., Taha, R. A., Mohsin, M. A., and Alharthi, A. S. (2010). “Causes, effects, benefits, and remedies of change order on public construction projects in Oman.” J. Constr. Eng. Manage., 10.1061/(ASCE)CO.1943-7862.0000154, 615-622.
466 467
Arain, F. M., and Pheng, L. S. (2005). “The potential effects of variation orders on institutional building projects.” J. Facil., 23(11/12), 496-510.
468 469
Arain, F. M., and Pheng, L. S. (2007). “Modeling for management of variations in building projects.” Eng. Constr. Archit. Manage., 14(5), 420-433.
470 471 472
Arashpour, M. and Arashpour, M. (2011). “Important factors influencing personnel performance of construction companies.” Proc., Int. Conf. on Economics, Business and Management, Manila, Philippines, 32-37. 20
473 474 475
Arashpour, M., Shabanikia, M., and Arashpour, M. (2012). “Valuing the contribution of knowledge-oriented workers to projects: A merit based approach in the construction industry.” Ausralas. J. Constr. Econ. Build., 12(4), 1-12.
476 477 478
Arashpour, M., Wakefield, R., Blismas, N., and Lee, E. W. M. (2014). “Analysis of disruptions caused by construction field rework on productivity in residential projects.” J. Constr. Eng. Manage., 10.1061/(ASCE)CO.1943-7862.0000804, 04013053.
479 480
Assaf, S.A., and Al-Hejji, S. (2006). “Causes of delay in large construction projects.” Int. J. Proj. Manage., 24 (4), 349-357.
481 482 483
Barry, W., and Leite, F. (2015). “Late deliverables to construction: How understanding the impacts can benefit dispute prevention and resolution.” J. Leg. Aff. Dispute Resolut. Eng. Constr., 10.1061/(ASCE)LA.1943-4170 .0000153, 04514004.
484 485
Carrillo, P., Ruikar, K., and Fuller, P. (2013). “When will we learn? Improving lessons learned practice in construction.” Int. J. Proj. Manage., 31(4), 567-578.
486 487
Chan, D. W. M., and Kumaraswamy, M. M. (1997). “A comparative study of causes of time overruns in Hong Kong construction projects.” Int. J. of Proj. Manage., 15 (1), 55–63.
488 489
Cohen, J. (1988). Statistical Power Analysis for the Behavioral Sciences, 2nd Ed. Lawrence Erlbaum Associates, Inc., Hillsdale, NJ.
490 491
Construction Industry Institute (CII). (2001). “The field rework index: Early warning for field rework and cost growth,” Rep. NO. RS153-1, Austin, TX.
492 493
Construction Industry Institute (CII). (2012). “CII Best Practices Guide: Improving Project Performance.” Rep. NO. IR 166.3, Austin, TX.
494 495 496
Dehghan, R. and Ruwnapura, J. Y. (2014). “Model of trade-off between overlapping and rework of design activities.” J. Constr. Eng. Manage., 10.1061/(ASCE)CO.1943-7862.0000786, 04013043.
497 498 499
Donyavi, S., and Flanagan, R. (2009). “The impact of effective material management on construction site performance for small and medium sized construction enterprises.” Proc. Annual Association Of Researchers in Construction Management, Belfast, UK, 11-20.
500 501 502 503
Du, L., Tang, W., Liu, C., Wang, S., Wang, T., Shen, W., Huang, M., and Zhou, Y. (2016). “Enhancing engineer-procure-construct project performance by partnering in international markets: Perspective from Chinese construction companies.” Int. J. Proj. Manage., 34(1), 30-43.
504 505
Feng, P. P. Y. (2009). “Causes and effects of rework on the delivery of healthcare facilities in California.” Ph.D. thesis, Univ. of California, Berkeley, CA.
506 507
Fisk, E. R. (1997). Construction project administration. 5th Ed., Prentice Hall, Upper Saddle River, NJ.
508 509 510
Forcada, N., Alvarez, A. P., Love, P. E. D., and Edwards, D. J. (2017b). “Rework in urban renewal projects in Colombia.” J. Infrastruct. Syst., 10.1061/(ASCE)IS.1943-555X.0000332, 04016034.
511 512
Forcada, N., Rusinol, G., MacArulla, M., and Love, P. E. D. (2014). “Rework in highway projects.” J. Civ. Eng. Manage., 20(4), 445-465. 21
513 514 515
Forcada, N., Gangolles, M., Casals, M., and Macarulla, M. (2017a). “Factors affecting rework costs in construction.” J. Constr. Eng. Manage., 10.1061/(ASCE)CO.19437862.00013241, 04017032.
516 517
George, R., Bell, L. C., and Back, W. E. (2008). “Critical activities in the Front End Planning process.” J. Manage. Eng., 10.1061/(ASCE)0742- 597X(2008)24:2(66), 66-74.
518 519
Griffith, A. F., and Gibson, G. E. (2001). “Alignment during pre-project planning.” J. Manage. Eng., 10.1061/(ASCE)0742-597X(2001)17:2(69), 69-76.
520 521
Hsieh, T., Lu, S., and Wu, C. (2004). “Statistical analysis of causes for change orders in metropolitan public works.” Int. J. Proj. Manage., 22(8), 679-686.
522 523 524
Hwang, B. G. and Ho, J. W. (2012). “Front end planning implementation in Singapore: status, importance and impact.” J. Constr. Eng. Manage., 10.1061/(ASCE)CO.19437862.0000456, 567-573.
525 526 527
Hwang, B. G., Thomas, S. R., Haas, C. T., and Caldas, C. H. (2009). “Measuring the impact of rework on construction cost performance.” J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(2009)135:3(187), 187-198.
528 529
Jadhav, O. U., and Bhirud, A. N. (2015). “An analysis of causes and effects of change orders on construction projects in Pune.” I. J. E. R. G. S., 3(6), 795-799.
530 531 532
Josephson, P. E., Larsson, B., and Li, H. (2002). “Illustrative benchmarking rework and rework costs in Swedish construction industry.” J. Manage. Eng., 10.1061/(ASCE)0742597X(2002)18:2(76), 76-83.
533 534
Karthick, R., Malathi, B., and Umarani, C. (2015). “Study on change order impact on project lifestyle.” I. J. E. R. T., 4(5), 691-695.
535 536 537
Keane, P., Sertyesilisik, B., and Ross, A. D. (2010). “Variations and change orders on construction projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr., 10.1061/(ASCE)LA.19434170.0000016, 89-96.
538 539
Kifokeris, D., and Xenidis, Y. (2017). “Constructability: Outline of past, present, and future research.” J. Constr. Eng. Manage., 10.1061/(ASCE)CO.1943-7862.0001331, 04017035.
540 541 542
Li, Y., and Taylor T. R. B. (2014). “Modeling the impact of design rework on transportation infrastructure construction project performance.” J. Constr. Eng. Manage., 10.1061/(ASCE)CO.1943-7862.0000878, 04014044.
543 544
London, K., and Singh, V. (2013). “Integrated construction supply chain design and delivery solutions.” Eng. Constr. Archit. Manage., 9(3), 135-157.
545 546 547
Love, P. E. D. (2002). “Influence of project type and procurement method on rework costs in building construction projects.” J. Constr. Eng. Manage., 10.1061/(ASCE)07339364(2002)128:1(18), 18-29.
548 549 550
Love, P. E. D., Ackermann, F., Carey, B., Morrison, J., Ward, M., and Park, A. (2016b). “Praxis of Rework Mitigation in Construction.” J. Manage. Eng., 10.1061/(ASCE)ME.19435479.0000442, 05016010.
22
551 552 553
Love, P. E. D., Ackermann, F., Teo, P., and Morrison, J. (2015). “From individual to collective learning: A conceptual learning framework for enacting rework prevention.” J. Constr. Eng. Manage., 10.1061/(ASCE)CO .1943-7862.0001013, 05015009.
554 555
Love, P. E. D., Lopez, R., Edwards, D. J., and Goh, Y. M. (2012). “Error begat error: Design error analysis and prevention in social infrastructure projects.” Accid. Anal. Prev., 48, 100-110.
556 557 558
Love, P. E. D., Edwards, D. J., and Irani, Z. (2008). “Forensic project management: An exploratory examination of the causal behavior of design-induced rework.” IEEE Trans. Eng. Manage., 55(2), 234-247.
559 560 561
Love, P. E. D., Edwards, D. J., and Smith, J. (2016a). “Rework causation: Emergent Theoretical insights and implications for research.” J. Constr. Eng. Manage., 10.1061/(ASCE)CO.1943-7862.0001114, 04016010.
562 563 564
Love, P. E. D., and Smith, J. (2003). “Bench-marking, bench-action, and bench-learning: Rework mitigation in projects.” J. Manage. Eng., 10.1061/(ASCE)0742-597X(2003)19:4(147), 147-159.
565 566 567
Love, P. E. D., Edwards, D. J., Watson, H., and Davis, P. (2010). “Rework in civil infrastructure projects: Determination of cost predictors.” J. Constr. Eng. Manage., 10.1061/(ASCE)CO.1943-7862.0000136, 275-282.
568 569 570
Mohammadi, N., Taylor, J. E., and Javernick, A. (2016). “Team building moderators of the engineering and construction industry virtual team performance.” Proc. Construction Research Congress, ASCE, San Juan, Puerto Rico, 219-228.
571 572 573
Nascimento, D. L. M., Sotelino, E. D., Lara, T. P. S., Caiado, R. G. G., and Ivson, P. (2017). “Constructability in industrial plants construction: a BIM-Lean approach using the Digital Obeya Room framework.” J. Civ. Eng. Manage., 23(8), 1100-1108.
574 575
O’Brien, J. J. (1998). Construction change orders: Impact, avoidance, and documentation. McGraw Hill, New York, NJ.
576 577 578
Palaneeswaran, E., Love, P. E. D., and Kim, J. T. (2014). “Role of design audits in reducing errors and rework: Lessons from Hong Kong.” J. Perform. Constr. Facil., 10.1061/(ASCE)CF.1943-5509.0000450, 511-517.
579 580 581
Safapour, E., Kermanshachi, S., Shane, J., and Anderson, S. (2017). “Exploring and assessing the utilization of Best Practices for achieving excellence in construction projects.” Proc. International Construction Specialty Conference, CSCE, Vancouver, Canada.
582 583
Sanvido, V., Grobler, F., Prafitt, K., Guvenis, M., and Coyle, M. (1992). “Critical success factors for construction projects.” J. Constr. Eng. Manage., 118(1), 94-111.
584 585 586
Shokri-Ghasabeh, M., and Chileshe, N. (2014). “Knowledge management: Barriers to capturing lessons learned from Australian construction contractors’ perspective.” Constr. Innov., 14(1), 108-134.
587 588
Spatz, D. M. (2000). “Team Building in construction.” Pract. Period. Struct. Des. Constr., 5(3), 93-105.
23
589 590 591
Sullivan, K. T. (2011). “Quality management programs in the construction industry: Best value compared with other methodologies.” J. Manage. Eng., 10.1061/(ASCE)ME.19435479.0000054, 210-219.
592 593
Sun, M., and Meng, X. (2009). “Taxonomy for change causes and effects in construction projects.” Int. J. Proj. Manage., 27(6), 560-572.
594 595
Sunday, O. A. (2010). “Impact of variation orders on public construction projects.” Proc. 26th Annual ARCOM Conference, Leeds, U.K., 101-110.
596 597
Taylor, T., and Ford, D. N. (2006). “Tipping point failure and robustness in single development projects.” Sys. Dyn. Rev., 22(1), 51-71.
598 599 600
Thomas, H. R., Riley, D. R., and Messner, J. I. (2005). “Fundamental principles of site material management.” J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(2005)131:7(808), 808-815.
601 602
Tuholski, S. J. (2008). “Transformation, flow, and value constellations in AEC projects.” Ph.D. thesis, Univ. of California, Berkeley, CA.
603 604 605
Wang, T., Tang, W., Du., L., Duffield, C. F., and Wei, Y. (2016). “Relationships among risk management, partnering, and contractor capability in international EPC project delivery.” J. Manage. Eng., 10.1061/(ASCE)ME.1943-5479.0000459, 04016017.
606 607
Wu, C., Hsieh, T., and Cheng, W. (2005). “Statistical analysis of causes for design change in highway construction on Taiwan.” Int. J. Proj. Manage., 23(7), 554-563.
608 609
Ye, G., Jin, Z., Xia, B., and Skitmore, M. (2015). “Analyzing causes for reworks in construction projects in China.” J. Manage. Eng., 10.1061/(ASCE)ME.1943-5479.0000347, 04014097.
610 611
Zaneldin, E. (2000). “An information model for improving design coordination in building projects.” < https://uwspace.uwaterloo.ca/bitstream/handle/10012/532/NQ51242.pdf>.
612 613
Zavadskas, E. K., Turskis, Z., and Tamosaitiene, J. (2010). “Risk assessment of construction projects.” J. Civ. Eng. Manage.,16(1), 33-46.
614 615 616 617
Zhang, D., Haas, C. T., Goodrum, P. M., Caldas, C. H., and Granger, R. (2012). “Construction small-projects rework reduction for capital facilities.” J. Constr. Eng. Manage., 10.1061/(ASCE)CO.1943- 7862.0000552, 1377-1385.
24
Table
Click here to access/download;Table;Tables.docx
Table 1. List of Construction Best Practices with Their Definition Best Practice
BPs Explanation
Previous Studies
Partnering
Companies may collaborate in order to achieve specific business objectives by maximizing the effectiveness of each participant’s resources.
Du et al. (2016) Wang et al. (2016)
Alignment
The condition where appropriate project participants are working within acceptable tolerances to develop and meet a uniformly defined and understood set of project priorities.”
Griffith and Gibson (2001)
Front End Planning
The process through which owners develop sufficient strategic information to address risk and commit resources in order to maximize project success.
Geaorge et al. (2008), Hwang and Ho (2012)
Constructability
The optimal use of construction knowledge and experience in planning, design, procurement, and field operations to achieve overall project objectives.
Kifokeris and Xenidis (2017), Nascimento et al. (2017)
A project-focused process that builds and develops shared goals, interdependence, trust and commitment, and accountability among team members. The process used to identify, assess, and manage risk. The project team evaluates risk exposure for potential project impact to provide focus for mitigation strategies. An integrated process for planning and controlling all necessary efforts to make certain that the quality and quantity of materials and equipment are appropriately specified in a timely manner, are obtained at a reasonable cost, and are available when needed. Use of a dispute review board as an alternative to litigation. The Dispute Review Board technique provides a process for addressing disputes in their early stages before the dispute affects the progress of the work, creates adversarial positions, and leads to litigation. This strategy incorporates all activities conducted to improve the efficiency, contract compliance and cost effectiveness of design, engineering, procurement, QA/QC, construction, and startup elements of construction projects.
Spatz (2000), Mohammadi et al. (2016) Zavadskas et al. (2010)
Team Building
Risk Assessment
Material Management
Dispute Prevention
Quality Management
Lesson Learned
Knowledge gained from experience, successful or otherwise, for improving future performance.
Thomas et al. (2005), Donyavi and Flanagan (2009) Barry and Leite (2015)
Sullivan (2011)
Carrillo et al. (2013), Shokri-Ghasabeh and Chilesha (2014)
Table 2. Statistical Analysis Methods Statistical Test
Assumptions
Two-sample t-test (adjusted R2): This test was used • The two groups follow a normal distribution. where the response is a count or numerical value. • Each Project was independent from other projects. Kruskal-Wallis: This test was used for Likert scale questions (ordinal seven-point scale), where it could not necessarily be assumed that the data follows a normal distribution.
• The two groups follow an identically scaled distribution. • Each Project was independent from other projects. • The distribution of two groups are the same.
Table 3. Respondents’ Demographic Information Years of Experience 0-10 11-20 21-30 31-40 Above 40
Number 4 12 14 12 2
Percentage (%) 9 27 32 27 5
Current Role in the Company Program Director Project Manager Engineer
Number 10 30 4
Percentage (%) 22 69 9
Table 4. Information of Case Study Projects Project
Project Type
Project Location
Baseline Budget ($)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44
Heavy Industrial Heavy Industrial Infrastructure Heavy Industrial Buildings Heavy Industrial Heavy Industrial Heavy Industrial Heavy Industrial Heavy Industrial Buildings Infrastructure Light Industrial Heavy Industrial Light Industrial Heavy Industrial Heavy Industrial Heavy Industrial Heavy Industrial Heavy Industrial Heavy Industrial Buildings Heavy Industrial Buildings Infrastructure Heavy Industrial Heavy Industrial Heavy Industrial Light Industrial Heavy Industrial Buildings Heavy Industrial Heavy Industrial Buildings Buildings Heavy Industrial Heavy Industrial Heavy Industrial Heavy Industrial Heavy Industrial Heavy Industrial Heavy Industrial Heavy Industrial Heavy Industrial
USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA USA Senegal Indonesia Saudi Arabia Brazil Netherlands Canada Peru Indonesia Alaska Canada China
$21,450,000 $45,000,000 $4,882,621 $5,900,000 $19,999,000 $43,500,000 $575,000,000 $11,053,269 $17,400,000 $13,500,000 $17,003,722 $81,800,000 $77,000,000 $166,333,047 $77,000,000 $273,550,000 $217,250,000 $111,818,500 $11,000,000 $448,864,480 $376,433,800 $273,550,000 $7,000,000 $425,000 $1,600,000 $18,300,000 $9,250,000 $125,000,000 $11,000,000 $25,700,000 $639,326 $39,754,613 $560,000 $203,638,000 $273,550,000 $5,000,000,000 $450,000,000 $30,000,000 $550,000,000 $166,333,047 $1,443,000,000 $639,326 $273,550,000 $4,290,000
Actual Cost ($) $18,980,000 $42,957,344 $5,276,921.35 $6,200,000 $19,999,000 $43,500,000 $650,000,000 $9,015,969 $17,800,000 $13,888,000 $14,039,249 $79,500,000 $83,249,000 $192,884,724 $90,000,000 $295,037,296 $214,600,000 $105,041,153 $13,600,000 $666,347,825 $319,660,518 $295,037,296 $5,910,365 $418,293 $1,259,000 $15,260,000 $7,706,000 $138,000,000 $10,700,000 $42,700,000 $698,056 $29,364,523 $560,000 $190,083,306 $295,037,296 $5,600,000,000 $490,000,000 $30,500,000 $575,000,000 $192,884,724 $1,563,340,000 $698,056 $295,037,296 $4,648,000
Baseline Schedule (months) 30 30 24 8 12 16 39 24 24 15 27 47 16 24 22 22 30 24 30 26 26 22 30 24 24 19.4 16.5 24 17.5 22 10 54 10 36 22 42 42 21 22 26 33 10 22 8
Actual Schedule (months) 36 36 34 8 12 20 52 30 24 17 34 70 21 36 23 24 36 22 36 35 35 24 31 26 26 19.1 18 30 16.6 24 12 55 11 31 24 44 45 23 25 35 36 12 24 9
Table 5. Descriptive Data Analysis of Collected Data in Construction Phase
Cost
Schedule Change Orders
Construction Phase Baseline Budget Actual Cost Baseline Schedule Actual Schedule Rework
Standard Deviation
Variance
134,588,433
$1.8E+16
Minimum
Mean
Maximum
$337,721
$87,279,265
$740,100,000
$327,000
$151,578,590
$2,500,000,000
393,970,564
$1.5E+17
4 Months
16 Months
40 Months
9.6 Months
93.7 Months
3 Months
17.5 Months
46 Months
10.5 Months
110.1 Months
$21,000
$2,068,557
$9,350,000
$2,081,929
$4.3E+12
Category
Table 6. Significant Indicators of Manageable Rework Causes and Corresponding P-Values Attribute
Organization
Bureaucracy
Participants
Communication
Management Team
Project
Location
Design & Technology Material Resources Scope Partnership Finance
People
Skill Field Craft Experience Socio-Culture
Indicators of Manageable Rework Causes (IMRCs) IMRC-1- Difficulty in obtaining design approval IMRC-2- Number of financial approval authority threshold IMRC-3- Number of external entities required to approve the design IMRC-4- Number of active Internal stakeholders in decision making process IMRC-5- Alignment quality of internal stakeholders IMRC-6- Number of owner organizations IMRC-7- Number of designer organizations IMRC-8- Number of contractor organizations IMRC-9- Communication effectiveness within owners IMRC-10- Communication effectiveness within designers IMRC-11- Communication effectiveness within contractors IMRC-12-Percentage of actual project management staff IMRC-13-Number of executive oversight entities above the PM IMRC-14- PMT experience in design phase IMRC-15- PMT experience in construction phase IMRC-16-Number of execution locations on this project during detailed design phase IMRC-17-Number of countries involved in design phase IMRC-18- Number of countries involved in construction phase IMRC-19-Difficulty in system design IMRC-20- Percentage of design at the start of construction IMRC-21- RFI leads to design changes IMRC-22- Number of new systems tied into existing systems IMRC-23- Delay in delivery of permanent facility equipment IMRC-24- Permanent equipment quality issues IMRC-25-Quality of bulk materials
Causes of Rework based on Previous Studies
P-Value
Long waiting time for approval (Chan & Kumaraswamy 1997) Long-lead procurement (Fisk 1997)
0.015** 0.001**
Occurrence of conflicts and disputes (Wu et al. 2005)
0.034**
Impediment of prompt decision-making (Sanvido et al.1992)
0.043**
Poor coordination (Arain and Pheng 2005) Impediment of prompt decision-making (Sanvido et al. 1992) Poor coordination ( Arain and Pheng 2005) Poor site management (Sunday 2010) Owner fail to make decision right time (Jadhav & Bhirud 2015) Failure by consultant to supervise effectively (Jadhav & Bhirud 2015) Poor project management by contractor (Ye et al. 2015) Poor site management and supervision (Ye et al. 2015) Low speed of decision making (Chan & Kumaraswamy 1997) Lack of experience ( Arain and Pheng 2005) Lack of experience ( Arain and Pheng 2005)
0.020** 0.003** 0.055* 0.016** 0.006** 0.001** 0.001** 0.023** 0.035** 0.001** 0.001**
Inappropriate linking all design team (Chan & Kumaraswamy 1997)
0.051* 0.057* 0.081* 0.038* 0.031* 0.018* 0.035** 0.003** 0.047** 0.043**
IMRC-27-Total number of joint-venture partners in a project IMRC-28-Number of funding phases IMRC-29-Degree of familiarity with technologies in design IMRC-30- familiarity with technologies in construction phase
Socio-cultural factors (O’Brien 1998) Socio-cultural factors (O’Brien 1998) Mistake and defect in design (Hsieh et al. 2004) Incomplete design information (Jadhav & Bhirud 2015) Changes in design ( Arain and Pheng 2005) Lack of experience ( Arain and Pheng 2005) Unavailability of equipment (O’Brian 1998) Low productivity of equipment (Assaf and Al-Hejji 2006) Replacement of material (Karthick et al. 2015) The owner may make changes to achieve certain milestones within a given time frame (Wu et al. 2005) Low speed of decision making (Chan & Kumaraswamy 1997) Delay in payment (Karthick et al. 2015) Defect in design (Hsieh et al. 2004) Changes in construction method(Wu et al. 2005)
IMRC-31- Field craft labor quality issue
Skill Shortage ( Arain and Pheng 2005)
0.069*
IMRC-32- Percentage of craft labor sourced locally
Socio-cultural factors (O’Brien 1998)
0.011**
IMRC-26- Clarity of owner’s project goals and objectives
** denotes significant differences with 95% confidence; * denotes significant differences with 90% confidence
0.039** 0.042** 0.044** 0.082* 0.063*
Skill Field Craft Experience Socio-Culture
Lesson Learned
People
Scope Partnership Finance
Dispute Prevention
Material Resources
Quality Management
Design & Technology
Material Management
Project
Location
Risk Assessment
Management Team
Front End Planning
Communication
Partnering
Participants
Alignment
Organization
Bureaucracy
Team Building
Attribute
Constructability
Category
Table 7. Result of Kruskal-Wallis Test of BPs to Reduce the Value of Rework Associated with IMRCs
IMRC-1 IMRC-2 IMRC-3 IMRC-4 IMRC-5 IMRC-6 IMRC-7 IMRC-8 IMRC-9 IMRC-10 IMRC-11 IMRC-12 IMRC-13 IMRC-14 IMRC-15 IMRC-16 IMRC-17 IMRC-18 IMRC-19 IMRC-20 IMRC-21 IMRC-22 IMRC-23 IMRC-24 IMRC-25 IMRC-26 IMRC-27 IMRC-28 IMRC-29 IMRC-30
0.198 0.825 0.475 0.285 0.175 0.497 0.112 0.458 0.423 0.108 0.477 0.365 0.185 0.001** 0.252 0.395 0.425 0.202 0.047** 0.025** 0.285 0.412 0.202 0.202 0.285 0.202 0.333 0.475 0.117 0.414
0.258 0.321 0.147 0.415 0.284 0.617 0.085 0.058 0.064* 0.081* 0.052* 0.394 0.852 0.174 0.256 0.354 0.052* 0.235 0.684 0.196 0.555 0.396 0.145 0.112 0.312 0.112 0.125 0.485 0.157 0.158
0.051* 0.285 0.025** 0.698 0.035** 0.188 0.321 0.0741* 0.147 0.120 0.346 0.168 0.096* 0.146 0.344 0.687 0.145 0.362 0.456 0.387 0.456 0.550 0.265 0.352 0.256 0.625 0.170 0.685 0.145 0.325
0.111 0.174 0.285 0.012** 0.321 0.222 0.312 0.297 0.374 0.321 0.354 0.116 0.174 0.375 0.303 0.489 0.203 0.132 0.114 0135 0.394 0.465 0.665 0.363 0.110 0.285 0.015** 0.185 0.325 0.374
0.369 0.074* 0.352 0.526 0.354 0.014** 0.483 0.743 0.345 0.147 0.466 0.016** 0.196 0.159 0.055* 0.156 0.361 0.144 0.178 0.112 0.415 0.394 0.209 0.564 0.393 0.059* 0.041** 0.018** 0.486 0.315
0.875 0.241 0.178 0.369 0.147 0.444 0.397 0.645 0.456 0.145 0.117 0.746 0.285 0.525 0.354 0.131 0.220 0.085* 0.568 0.189 0.285 0.745 0.406 0.550 0.282 0.145 0.695 0.396 0.545 0.084*
0.663 0.440 0.685 0.357 0.158 0.266 0.199 0.196 0.625 0.652 0.284 0.373 0.221 0.424 0.074* 0.208 0.334 0.068* 0.248 0.684 0.341 0.195 0.063* 0.008** 0.035** 0.465 0.375 0.358 0.357 0.458
0.660 0.446 0.358 0.359 0.169 0.442 0.174 0.456 0.412 0.354 0.365 0.191 0.356 0.075* 0.064* 0.058* 0.035** 0.346 0.863 0.374 0.396 0.375 0.175 0.065* 0.044** 0.368 0.674 0.425 0.303 0.417
0.741 0.528 0.355 0.745 0.645 0.028** 0.633 0.045 0.312 0.295 0.475 0.711 0.341 0.324 0.654 0.158 0.330 0.365 0.148 0.198 0.645 0.684 0.556 0.333 0.355 0.756 0.312 0.484 0.119 0.636
0.396 0.547 0.187 0.658 0.586 0.333 0.063* 0.697 0.387 0.274 0.145 0.623 0.285 0.303 0.666 0.302 0.357 0.145 0.351 0.257 0.036** 0.045** 0.145 0.145 0.268 0.642 0.202 0.356 0.022** 0.063*
IMRC-31
0.185
0.195
0.174
0.525
0.505
0.110
0.151
0.015**
0.147
0.417
IMRC-32
0.452
0.302
0.415
0.405
0.220
0.111
0.325
0.369
0.101
0.002**
IMRC
Table 8. Weight of Early Indicators of Manageable Rework Causes Indicators of Manageable Rework Causes (IMRCs)
Weight
IMRC-15- PM experience in construction IMRC-12- Number of PM staff IMRC-14- PM experience in design
0.0606 0.0587 0.0568
IMRC-13- No. of entities above PM
0.0549
IMRC-2- No. of financial approval authority
0.0530
IMRC-3- No. of entities for design approval
0.0511
IMRC-9- Communication within owners IMRC-10- Communication within designers IMRC-23- Delay in delivery of facility IMRC-11- Communication within contractors IMRC-6- No. of owner organizations IMRC-29- Familiarity with design tech. IMRC-7- No. of designer organizations
00378
IMRC-8- No. of contractor organizations IMRC-5- Alignment of internal entities
0.0359 0.0340
IMRC-16- No. of locations in design
0.0321
Indicators of Manageable Rework Causes (IMRCs)
Weight 0.0303 0.0284 0.0265
0.0492 0.0473 0.0454
IMRC-1- Difficulty in design approval IMRC-32- percentage of local craft staff IMRC-22- No. of new systems IMRC-20- Design completion before construction phase IMRC-21- RFI leads to design changes IMRC-18- No. of countries in construction IMRC-31- Field craft labor quality issues IMRC-19- Difficulty in system design IMRC-24- Equipment quality issues
0.0435
IMRC-4- No. of active internal entities
0.0132
0.0416 0.0397
IMRC-25- Quality of bulk materials IMRC-28- No. of funding phases IMRC-30- Familiarity with construction technology IMRC-26- Clarity of owner goals IMRC-27- No. of joint-venture partners IMRC-17- No. of countries in design phase
0.0113 0.0094
0.0246 0.0227 0.0208 0.0189 0.0170 0.0151
0.0075 0.0056 0.0037 0.0018
People
Project
0.0814
Participant
0.0699
Communication Management Team Location Design & Technology Material Resources Scope Partnership Finance Skill Field Craft Experience Socio- Culture
Quality Management
Material Management
Risk Assessment
Front End Planning
Lesson Learned
Bureaucracy
Partnering
Alignment
Team Building
Constructability
Attribute
Dispute Prevention
Organization
Category
Table 9. Weight of Each Best Practice for Manageable Rework Attributes
0.0416
0.0378
0.0530 0.0132
0.0416
0.140 0.0568
0.0549
0.1193
0.0018
0.0208
0.0606
0.1174
0.0208
0.0339
0.0416
0.0492 0.0718
0.0264
0.0056 0.0037
0.0037 0.0094 0.0075
0.0472 0.0189 0.0284
Table 10. Breakdown of Information for Two Case Study Projects Used for Implementation of Results Project 1 2 Project
1
2
Baseline Budget Baseline Schedule Construction Phase Construction Phase Heavy Industrial $5,022,000 8 Months Heavy Industrial $5,000,000 7 Months Existing IMRCs in the Project IMRC-3: High no. of external entities required to approve design IMRC-4: High no. of active internal stakeholders in decision making process IMRC-12: Low percentage of PM staff IMRC-13: High no. of executive oversight entities IMRC-16: Several no. of execution locations in design phase IMRC-17: Two countries involved in design phase IMRC-19: Complex system design IMRC-21: RFIs drive serious project changes IMRC-22: Several new systems were tied into existing systems IMRC-23: Several weeks delay in the delivery of permanent facility equipment IMRC-28:Two no. of funding phases IMRC-8: Several no. of contractor organizations IMRC-14: Low PM experience in design phase IMRC-15: Low PM experience in construction phase IMRC-16: Several no. of execution locations in design phase IMRC-17: Two countries involved in design phase IMRC-18: Six no. of countries involved in construction phase IMRC-22: Several new systems were tied into existing systems IMRC-23: Several weeks delay in the delivery of permanent facility equipment IMRC-26: Low clarity of owner’s project goal IMRC-28:Three no. of funding phases IMRC-32: Between 60% and 80% of craft labors were not sourced locally Type of Project
Rework $1,239,831 $1,667,500 Implementation of BPs Constructability: Yes Team Building: No Alignment: No Partnering: No Front End Planning: No Material Management: Yes Quality Management: Yes Lesson Learned: Yes Risk Assessment: Yes Dispute Prevention: No
Constructability: No Team Building: No Alignment: No Partnering: No Front End Planning: No Material Management: Yes Quality Management: No Lesson Learned: Yes Risk Assessment: Yes Dispute Prevention: No
Figure
Click here to access/download;Figure;Fig.1.pdf
Step 1
Review Existing Literature
Step 2
Identify and Classify Potential IMRCs* Perform Data Collection
Step 3
Step 4
Case Study
Survey
Perform Descriptive Data Analysis 1st Study Outcome
Step 5
Determine Significant IMRCs 2nd Study Outcome
Step 6a
Determine Best Practices that Reduce the Value of Rework Associated with IMRCs
Step 6b
Calculate Weight of Best Practices for Rework Attributes
Step 7
Implement the Results
Fig. 1. Research methodology approach (IMRC*= Indicators of Manageable Rework Causes)
Figure
Click here to access/download;Figure;Fig.2.pdf
Organization •Bureaucracy •Participants •Communication
Project •Management Team •Location •Design & Technology •Material Resources •Scope •Partnership •Finance
People •Skill •Field Craft Experience •Socio-Culture
Fig. 2. Classification of indicators of manageable rework causes
Figure
Click here to access/download;Figure;Fig.3.pdf
Question 23. Were there joint-venture partners in this project? If yes, how many? Question 39. Please indicate the impact of external agencies on the project execution plan. No Impact on Meeting the Execution Plan 1 2
Moderate 3
4
5
Substantial Impact on Meeting the Execution Plan 6 7
Fig. 3. Two example questions of the survey