International Journal of Advanced Engineering Technology
Research Article
MEASUREMENTS AND SIMULATION FOR POWER QUALITY OF A WIND FARM 1
1
S.P. Shukla, 2Sushil Kumar Address for correspondence
Department of Electrical Engineering, Bhilai Institute of Technology, Durg, Chattisgarh (India)
[email protected] 2 Department of Electrical & Electronics Engineering, Bhilai Institute of Technology, Durg, Chattisgarh
[email protected] ABSTRACT This work investigates the impact of windfarm on the distribution network power quality. The quality of wind power is decided by IEEE Standard 519-1992 and IEEE Standard 1547. The experiments were carried out at the Vankuswade wind power project, Satara, (M.S.), India. The results are then compared by MATLAB simulation software (Version R2008a). The system is also simulated for system stability considering various faults on the simulated model. The field measurement results give important indications about the real effects of the integration of large interruptible renewable energy sources within the power system. The simulation results show an agreement with the measured response. KEY WORDS Wind power, Power Quality, Voltage Sag, Voltage Swell, Stability.
INTRODUCTION Wind power generation has experienced a
vicinity of a wind turbine at low voltage
very fast development worldwide mainly due
levels, and (ii) the interaction of wind farm
to environmental reasons. As the wind power
with the power system at the point of common
penetration into the grid is increasing quickly,
coupling with the grid at medium voltage
the influence of wind turbines on the power
level (Fig.1)
1,2, 11
quality is becoming an important issue
8
. Slow voltage variations,
.
flicker, voltage sags, transients and harmonics
The generation of wind power occurs with the
are measured by means of a modern digital
operation of multiple wind turbines in
measurement system. Important measuremed
windfarms. The integration of these wind
results are discussed.
parks into the power system may cause power
consisting
quality concerns. The important issue is how
Generators connected to the distribution
much the power quality will be affected by
network is simulated for various normal and
power production and connection of WTs to
abnormal conditions.
the grid. The purpose of this work is (i) to
The two results are then analyzed.
analyze the power quality in the electrical
IJAET/Vol. I/ Issue I/April-June, 2010/27-36
of
Then a wind farm
Doubly
Fed
Induction
International Journal of Advanced Engineering Technology
Fig. 1. Wind turbine with DFIG.
Wind Farm Site Description
reactive
Measurements are carried out at Asia’s largest
Capacitors are not provided on H.V. side [2].
wind
at
The site has good power availability with an
Satara
average wind speed above 5m/s. Each
district and Gudhepanchgani in Sangli district
machine is active yaw and pitch regulated
of Maharashtra State (India). The wind
with
electric-
is
Experiments are performed at a wind farm
BHEL/NORDEX make, 3-Phase, 415 Volt,
sites to study the interaction of wind turbine
82/250 kW, 82/424 Amp, 8/6 Pole, 30/40
(induction type) generator with the utility grid.
Turbine RPM, 757/1008 Generator RPM, ∆-
A DFIG has a wound rotor that is connected
connected asynchronous machine. The wind
to
turbine is horizontal axis and installed at 30m
modulated IGBT frequency converter which
hub height. There are 8 nos. of machines
controls the excitation system in order to
installed at the 2 MW demonstration wind
decouple the mechanical and electrical rotor
power
frequency and to match the network and rotor
farm
installed
Vankusavade/Chalkewadi
generator
project
Development
of
sites
under
in
study
Maharashtra
Agency
Energy
(MEDA)
at
power
drawn
power/torque
the
network
from
control
through
a
the
grid.
capability.
pulse-width
frequency (Fig. 1). The wind turbine rotor is
Chalkewadi.
coupled to the generator through a gearbox
The generator is connected directly to the grid
which adapts the two different speeds of rotor
through 0.415/11 and 11/33 kV step-up
and generator. The control system usually
transformers as shown in Fig. 2. Three
keeps the power factor to unity, but the
switching capacitor banks (two of 37.5 kVAR
windfarm can also exchange reactive power
and one of 25 kVAR) are connected across the
with the rest of the network.
generator (i.e. on L.V. side) to compensate the IJAET/Vol. I/ Issue I/April-June, 2010/27-36
International Journal of Advanced Engineering Technology
Fig. 2. Single line diagram of the test wind farm at Chalkewadi.
measure from 1 to 600V.
Power Quality Measurement Set-Up and Methodology When
•
power
probes
LEM
FLEX
RR3035, current ranges of 30/300/3000A,
performed on a system with wind production,
bandwidth: 10 Hz to 50 kHz, Accuracy:
due to the presence of electronic devices and
1%.
and
The measurement system was placed at the
currents are usually nonsinusoidal quantities.
wind turbine terminal, between the generator
In this application the measurement system
and the LV side of the step-up transformer
has to be carefully chosen and, in particular, it
according to a 3-Φ, 3 wire star connection.
has to be composed by transducers with high
Three channels have been connected to voltage
bandwidth,
blocks,
and current probes. The neutral has been
analog to digital converters a digital signal
connected to common and has been the
processing and, a storage unit.
reference for the three channels in order to
Low Voltage measurement system
measure
The following hardware components have
simplified diagram with only one phase is
been used:
provided in Fig. 3. The measurement system
•
•
converters,
measurements
current
are
frequency
quality
Three
analog
the
voltages
conditioning
the
phase-to-neutral
voltages.
A
Power monitoring instrument Dranetz
permits measuring the currents and voltages
PX5, 8 channels, 4 voltage and 4 current,
instantaneously. Parameters configured for the
256 samples/cycle, RMS Accuracy: ±0.1%
measurement
of Reading, ±0.05% Full Scale, over
minimum, RMS voltage and current values each
7KHz
flicker
minute; mean, minimum and maximum active
according to IEC 61000-4-15, complies
and reactive power and power factor each
with IEEE 1159, IEC 61000-4-30 Class A
minute; total harmonic distortion and individual
and EN50160 [1,5].
harmonics calculated each minute; flicker
bandwidth,
Instrument
voltage
measures
probes
that
IJAET/Vol. I/ Issue I/April-June, 2010/27-36
can
are:
mean,
maximum
and
measurements, calculated as per IEC 61000-4-
International Journal of Advanced Engineering Technology
15, with Pst (short term) interval equal to 10 min., Plt (long term) interval equal to 2 hours.
Fig. 3. LV measurement set-up. 3, 9
Medium Voltage measurement system
is equal to 2.77%
The following hardware components have been
are quite high, as the measurements have been
used:
done between the generator and the l.v. side of
. The harmonic emissions
•
Power monitoring instrument Dranetz PX5.
the transformer.
•
One PEARSON ELECTRONICS VD-305A
On the high voltage side of the transformer a
capacitive voltage divider, nominal division
reduced harmonic distortion level it is expected
ratio 2000:1, Maximum Pulse Voltage: 300
due to the damping features of the transformer.
kV, bandwidth: 30 Hz to 4 MHz.
Distortion levels are usually high in DFIG
Current probes LEM FLEX.
turbines due to the frequency converter,
•
In order to analyze the collective behavior of the
depending on the commutation frequency. The
wind power plant the measurement system has
distortion caused by the converter can be clearly
been placed at the point of common coupling
observed in Fig. 5.
(PCC) with the grid according to a single phase
Although harmonic distortion is an important
connection. A simplified connection diagram is
issue but due to the high switching frequencies,
provided in Fig. 4.
the advanced control algorithms and the filtering
Measurement Results and Discussion
techniques used in the wind farm allows
Voltage waveforms analysis
reducing the distortion well down the maximum
The
voltage
waveform
measured
at
the
generator terminals is shown in Fig. 5. The THD IJAET/Vol. I/ Issue I/April-June, 2010/27-36
value tolerated by standards11.
International Journal of Advanced Engineering Technology
390.7V whereas at no load has been about 401V.
Long-term Voltage Variation Analysis The measured RMS voltage, under normal operating
conditions,
excluding
situations
Fig.5. Phase-to-neutral volt. at gen.
arising from faults or voltage interruptions,
Terminals.
during all observation intervals has been within the range of ± 5% of the nominal voltage. Voltage sags and swells PQ analyzer was set to register transients when thresholds values exceeded. Voltages below 95% and above 105% of the RMS nominal
Fig.6 Phase-to-neutral volt. at PCC.
value have been recorded. Fig. 8 shows voltage
Fig. 6 presents the voltage measured at the PCC between one phase and neutral, the THD is equal to 0.93%. The low distortion is due to the combined
smoothing
effect
due
to
the
aggregation of the generators. Compared with maximum harmonic levels for the power system
sag caused by the WT disconnection from the grid due to excessive
power
production
(overload condition). During the measurement, 18 voltage sags were registered at the generator terminal but no voltage sags were recorded at the PCC.
specified by EN 50160, even though this standard is not applicable to this context, these values of THD are largely within the limits. Voltage Variations with Power Produced It has been observed a voltage variation at the terminals of the generator depending on the power generated. Fig. 7 shows the trend of the
Fig.7 Voltage variation compared with power
active power and voltage RMS for a time period
generated.
with high power production At full load the phase-to-neutral voltage RMS has been about
IJAET/Vol. I/ Issue I/April-June, 2010/27-36
International Journal of Advanced Engineering Technology
The measurements at the LV terminals of the wind turbine showed that the flicker level (Pst) is correlated with the active power produced by the generator. In particular the flicker level Fig. 8 Voltage sag at the generator terminal. Flicker
increases with the production and remain about constant even though the power changes as
The torque from a horizontal axis wind turbine
depicted in Figs. 9-10.
has a periodic component at the frequency at which the blades pass the tower (1-2 Hz) caused by a variation of the wind speed seen by the blade.
Such
variation
depends
on
the
combination of the tower shadow, wind shear and turbulence. The torque fluctuations are directly translated into output power flicker as there
is
only
a
partial
buffer
Fig.10. Flicker measured at the generator terminal.
between
mechanical input and electrical output. Fixed speed wind turbine can cause high flicker whereas variable speed one can limit the flicker within reasonable values7. In the proposed measurement campaign the Flicker has been
Fig.11. RMS voltage at the PCC.
analyzed at the LV connection of a single WT and at the PCC of the wind farm.
Fig.12. Power generated one phase at the PCC. The flicker at the PCC depends on the power fluctuations caused by all the turbines of the Fig.9. Power generated by a single turbine.
wind farm are illustrated in Figs. 11-12. Measures
IJAET/Vol. I/ Issue I/April-June, 2010/27-36
have
revealed
that
the
flicker
International Journal of Advanced Engineering Technology
increases as the power produced decrease. In
CASE 1-
Fig. 11, part of this flicker effect could be
TURBINE RESPONSE TO A CHANGE IN
imputable to the regulation action of the on-load
WIND SPEED
tap changer (OLTC) installed in the substation
Effect of wind speed variation is shown in fig
transformer as well as caused by switching
14a & b. It increases from 8m/s -20m/s in steps.
operations of start and stop of wind turbines.
The generated power also increases, at t = 32
The results are in good agreement with other
sec. when V = 15.5m/s PGenerated becomes 9MW
contributions related to measurements in similar
i.e. rated capacity of the wind farm. A further
conditions3,4.
increment in wind velocity causes voltage swell
Simulation of a Wind Farm Using DFIG
of 2.5% at the generator terminals a swell of
Wind Turbines
0.25% at the converter terminals (Grid). Voltage
Model Description
swells are eliminated by the pitching of the
A 9-MW wind farm consisting of six 1.5 MW
blades. The pitch angle increases from 0 degree
wind turbines connected to a 25-kV distribution
as soon as the wind speed crosses 15m/s i.e. the
system exports power to a 120-kV grid through
speed for 1p.u. generation.
a 30-km, 25-kV feeder. A 2300V, 2-MVA plant consisting of a motor load (1.68 MW induction motor at 0.93 PF) and of a 200-kW resistive load is connected on the same feeder at bus B25. Both the wind turbine and the motor load have a protection system monitoring voltage, current
(a)
and machine speed. The DC link voltage of the DFIG is also monitored. 4, 6, 11 MATLAB Simulation and discussion of the results Following conditions were applied on the MATLAB model: 1. Turbine response to a change in wind speed. 2. Simulation for stability due to LG fault on the distribution system (25kV). 3. Simulation of a voltage sag on the system IJAET/Vol. I/ Issue I/April-June, 2010/27-36
(b) Fig. 14. (a) V, I , P& Q at Gen. Terminals, (b) VDC , Turbine and Wind speed & Pitch angle.
International Journal of Advanced Engineering Technology
Fig. 4. MV measurement set-up.
Fig. 13 MATLAB model of DFIG connected to grid. CASE 2-
depicts
SIMULATION FOR STABILITY DUE TO
corresponding current. But the system regains
VARIOUS
steady state without losing stability when the
FAULTS
ON
THE
25-KV
a
large
drop
in
voltage
and
SYSTEM
fault is over. When the same fault was applied
The LG fault is applied on phase A at t=5sec.
for 9 cycles, it was observed that the windfarm
for a duration of 5 cycles. Its effect on load
gets
voltage and current is shown in Fig. 15, which
contribution (P, V & I) becomes zero as shown
IJAET/Vol. I/ Issue I/April-June, 2010/27-36
tripped
from
the
network
and
its
International Journal of Advanced Engineering Technology
in Fig. 16 a. This happens due to drop in
CONCLUSIONS
generator terminal voltage below 0.9 p.u. Thus
In this paper, the power quality of a large
the stability of the system is lost. When LLG
windfarm at the low voltage level and at the
fault is applied at t = 37sec. for 5 cycles, the
PCC with the HV grid is investigated. Flicker,
generated power suddenly drops to 37% from
harmonics, and voltage sags have been analyzed
the rated value but comes back to steady state
and correlated with wind characteristics of the
when the fault is over as shown in Fig. 17a and
site. Then same were observed on a simulation
b. When LLLG fault is applied at t = 37sec. for
model. The simulated and the measured results
5 cycles , the windfarm trips immediately from
exhibit a good agreement. The investigation also
the network and does not regain the stability.
shows that the windfarm works without a
Case-3 Simulation of a voltage sag on the
negative impact on the transmission network
system
when DFIG turbines are installed.
Fig. 16 b depicts that effect of LG fault on voltage sag is much severe at the generator terminals (approx.30%), then less severe on the medium voltage distribution network (approx. 10%) and least on the high voltage grid i.e. at PCC (approx. 1%). During LLG and LLLG fault similar behavior was obtained but with
(a)
deeper sag.
(b) Fig. 16. ( a) V, I & P at Gen. Terminals (b) Voltage at Generator, Distribution, Grid Fig 15 .Load (500KW) Voltage and Current after a 5 cycle LG fault. IJAET/Vol. I/ Issue I/April-June, 2010/27-36
terminals.
International Journal of Advanced Engineering Technology
4. P. Sorensen, A.D. Hansen and P.A.C. Rosas, “Wind models for simulation of power fluctuations from wind farms”, Journal of wind
Engineering
Aerodynamics,
and
Vol.
Industrial
90,pp.
1381-
1402,December 2002. 5. IEEE
Standard
1547:
Interconnecting
Distributed Resources with Electric Power
(a)
System, IEEE Standard 1547-2003, p.p. 1-5, June 2003. 6. Yuriy Kazachkov and Steve Stapleton, “Modelling Wind Farms for power system stability
studies”
Power
Technology,
Newsletter Issue 95, April 2004. 7. S.P.Shukla, B.S.Narang “Harmonics in wind power systems” Applied science periodical, Vol.IX, No. 2, pp129-133, May, 2007. 8. Trinh Trong Chuong, Dragan “Voltage stability of grid investigation of grid
(b)
connected wind farm” PWASET, Vol. 32,
Fig. 17. (a) V, I & P at Gen. Terminals, (b)
August, 2008.
Voltage at Generator, Distribution, Grid
9. S.P.Shukla
terminals.
Recommended
al
“Transient
Control
Techniques in Synchronous Wind Turbine
REFERENCES 1. IEEE
et
Generators” CSVTU Practices
and
Requirements for Harmonic Control in
Research
Journal,
Vol.2, No. 1, pp 46-50 ,Jan.2009. 10. S.P.Shukla,
B.S.Narang
“Quality
and
Electrical Power Systems, IEEE Standard
Stability Assessment in a wind power
519-1992, pp.1-8, April 1993.
system” International Journal of Engg.
2. P. Kundur, Power system stability and control, McGraw-Hill, 1994.
Research & Indu. Appls. (IJERIA), Vol.2, No. VI, October 2009,pp 299-310.
3. Ake Larsson, “ Flicker emission of wind
11. S.P.Shukla, B.S.Narang “Power Quality and
turbines during continuous operation ” IEEE
Stability Aspects in a Wind Power System”
Trans. Energy Conversion ,Vol. 17,No. 1,pp.
Applied Science Periodical, Vol.XII, No. 4,
114-118,2002.
November, 2010.
IJAET/Vol. I/ Issue I/April-June, 2010/27-36