Project Dates: Work need to be completed one week before school start date August 16 2017. Prevailing Wage: This is a pr
3537 Johnson Ave El Monte, CA 91731
MOUNTAIN VIEW HIGH SCHOOL BUILDING F (BAND ROOM) PAINT PROJECT 2900 Parkway Dr. El Monte, CA91732
Job Walk: Thursday, June 29, 2017 @ 1:00 PM RFI’S due: Wednesday July 5, 2017 Bids Due: Monday July 10, 2017 @ 5:00 PM E-mail to: Jorge Estrada, Maintenance & Operations Coordinator E-mail
[email protected] Project Dates: Work need to be completed one week before school start date August 16 2017 Prevailing Wage: This is a prevailing wage project. Submittals: Provide company profile, experience, and references. Proof of Insurance: general liability, automobile and worker’s compensation. Provide final closeout documentation within 10 days of project completion. SCOPE OF WORK
The general scope of work consist of patching, repair cracks, filling nail holes and prepare interior walls and offices of Building F at Mount View High School to apply a fresh coat of paint. The scheduled wall surfaces and offices will be specified on the attached building plans. Walls’ surface must be smooth, dry and cleaned before painting. Contractor must provide all labor and materials to complete this project Brick walls should NOT be included as part of the project, but must be covered to protect them from overspray. Repair damage sections of ceiling and paint entire ceiling white on each scheduled room. Remove electrical plates, grilles, access panels, light fixture trims and fittings prior to surface preparation. Remove picture frames, boards and paper decorations prior to surface preparation. Surfaces must be perfectly dry, clean and smooth before applying primer coat. Fill any crack holes, and scratches with filler compound and make smooth before applying primer and paint. Use masking tape and plastic to cover all edges, and other surfaces that do not require painting. Exit metal doors must be prepared and painted with specific methods for metal painting *** Paint exposed conduit and electrical equipment existing in finished areas to match surface to be painted. Paint wood window and door jams Interior wood doors are NOT included Provide drop cloths and mask off all floor areas where painting is being done. YOU ARE RESPONSIBLE for any damages or stains to newly installed carpet and flooring. Clean dust and dispose of all trash generated by work assignment. Disposed leftover paint, and paint products used on the job assignment.
Scheduled to paint rooms and offices are listed on the following table. Square footage is approximate, and some offices contain cabinets that do not need to be painted. They must be covered and protected from overspray and damages.
Room
MVHS BUILDING F PAINT PROJECT Scope Wall color
Ft^2
Room #
301 Choir
1620
F16
Paint 3 walls, Ceiling, Paint doors & trim
Primer = Zinsser Cover Stain Ceiling = White Top Coat= Dangerous Robot
Primer= Zinsser Cover Stain Indoor door color=Swiss Coffee
302 Band
2900
F4
Paint 3 walls, Ceiling, Paint doors & trim
Primer = Zinsser Cover stain Ceiling = White Top Coat= Dangerous Robot
Primer= Zinsser Cover Stain Indoor door color= Swiss Coffee
303 Sound
400
F5
Paint 3 walls, Ceiling, Paint doors & trim
Primer = Zinsser Cover stain Ceiling = White Top Coat= Dangerous Robot
Primer= Zinsser Cover Stain Indoor door color= Swiss Coffee
Office 1
168
F2
Paint walls, Ceiling, Paint doors & trim
Primer= Zinsser Cover Stain Indoor door color= Swiss Coffee
Office 2
100
F15
Paint walls, Ceiling, Paint doors & trim
Office 3
80
Practice F13
Paint walls, Ceiling, Paint doors & trim
Office 4
80
Practice F12
Paint walls, Ceiling, Paint doors & trim
Office 5
80
Practice F11
Paint walls, Ceiling, Paint doors & trim
Primer = Zinsser Cover stain Ceiling = White Top Coat= Dangerous Robot Primer = Zinsser Cover stain Ceiling = White Top Coat= Dangerous Robot Primer = Zinsser Cover stain Ceiling = White Top Coat= Dangerous Robot Primer = Zinsser Cover stain Ceiling = White Top Coat= Dangerous Robot Primer = Zinsser Cover stain Ceiling = White Top Coat= Dangerous Robot
PAINT MATERIALS Interior walls = Dunn Edwards Grey Dangerous Robot # DE6387 Inside of exit doors and jams = Dunn Edwards Swiss Coffee # DEW341 Inside wood door jams = Dunn Edwards Swiss Coffee # DEW341 Primer = Dunn Edwards Zinsser Cover Stain
Door & Trim color
Primer= Zinsser Cover Stain Indoor door color= Swiss Coffee Primer= Zinsser Cover Stain Indoor door color= Swiss Coffee Primer= Zinsser Cover Stain Indoor door color= Swiss Coffee Primer= Zinsser Cover Stain Indoor door color= Swiss Coffee
3537 Johnson Ave El Monte, CA 91731 El
BID FORM The District reserves the right to accept or reject any bid All projects over $25,000.00 require Bond Payment.
$ ________________________
Total lump sum bid including cost of all materials and labor and expenses to complete the attached scope of work.
CONTRACTOR INFORMATION Name:
________________________________
Address:
________________________________
Phone Number: ________________________________
ALL THE DOCUMENTATION MUST BE SUBMITTED TO OUR PURCHASING DEPARTMENT IF YOU WIN THE BID. A CHECK OFF LIST OF DOCUMENTS WILL BE ATTACHED FOR YOUR INFORMATION.