1 Jul 2012 ... 3.2 Pipe to be used for Transportation of Natural Gas . ... 3.6 Natural Gas
Distribution Line . .... 5.0 Pipeline Design Factors .
NATURAL GAS PIPELINE
PLAN OF DEVELOPMENT Donlin Gold Project
July 2012
NATURAL GAS PIPELINE
PLAN OF DEVELOPMENT Donlin Gold Project
July 2012
4720 Business Park Blvd. Suite G-25 Anchorage, Alaska 99503
Prepared By: SRK Consulting (US), Inc. 4710 Business Park Blvd. Suite F-40 Anchorage, Alaska 99503
Plan of Development Donlin Gold Project
Table of Contents
TABLE OF CONTENTS 1.0 2.0
3.0
INTRODUCTION ........................................................................................................ 1-1 PURPOSE AND NEED .............................................................................................. 2-1 2.1 Purpose ........................................................................................................... 2-1 2.2 Need ................................................................................................................ 2-1 2.3 Background and Proposed Mine Information .................................................. 2-1 2.4 Expected Public Benefits ................................................................................. 2-2 PROJECT DESCRIPTION ......................................................................................... 3-1 3.1 Commodity to be Transported and Purpose.................................................... 3-2 3.2 Pipe to be used for Transportation of Natural Gas .......................................... 3-3 3.3 Timeline of Proposed Project .......................................................................... 3-4 3.3.1 Planned Commencement Date for Construction ................................. 3-4 3.3.2 Estimated Construction Time............................................................... 3-4 3.3.3 Planned Commencement Date for Operation ...................................... 3-7 3.3.4 Duration of Pipeline Operation............................................................. 3-7 3.4 Estimated Number of Persons to be Employed ............................................... 3-7 3.5 Financing Requirements for the Proposed Project .......................................... 3-7 3.5.1 Corporate Organization Structure ........................................................ 3-7 3.6 Natural Gas Distribution Line........................................................................... 3-8 3.7 Surface and Subsurface Attributes .................................................................. 3-9 3.8 Length/Width of ROW; Area Needed for Related Activities ............................. 3-9 3.9 Ancillary to an Existing Right-of-Way ............................................................ 3-10 3.10 Alternative Routes and Locations .................................................................. 3-10 3.10.1 Pipeline .............................................................................................. 3-10 3.10.2 Theodore River Alternate Route ........................................................ 3-11 3.10.3 Little Mt. Susitna Alternate Route ...................................................... 3-11 3.10.4 Round Mountain Alternate Route ...................................................... 3-11 3.10.5 Goodman Pass Alternate Route ........................................................ 3-12 3.10.6 Egypt Mountain Alternate Route ........................................................ 3-12 3.10.7 St. John’s Hill Alternate Route ........................................................... 3-12 3.10.8 Windy Fork Alternate Route............................................................... 3-12 3.10.9 Big River Alternate Route .................................................................. 3-13 3.10.10 Tatlawiksuk River Alternate Route ................................................. 3-13 3.10.11 Kuskokwim River Alternate Route ................................................. 3-13 3.10.12 Moose Creek Alternate Route........................................................ 3-13 3.10.13 Kuskokwim Hills Alternate Route ................................................... 3-13 3.10.14 Alternative Route Assessments for the Electric Transmission Line .................................................................................................... 3-13 3.11 Safeguards for Persons, Property, and Public and the Environment ............ 3-26 3.11.1 Safety of Workers .............................................................................. 3-26 3.11.2 Public Health and Safety ................................................................... 3-27 3.11.3 Public or Private Property .................................................................. 3-29
Donlin Gold
i
July 2012
Plan of Development Donlin Gold Project
Table of Contents
3.11.4 3.11.5 3.11.6 3.11.7 3.11.8 3.11.9
4.0
5.0
6.0
7.0
Vegetation or Timber ......................................................................... 3-30 Fish or Other Wildlife or Their Habitat ............................................... 3-31 Restoring Areas of Vegetation or Timber .......................................... 3-31 Erosion and Rehabilitation of Areas Eroded ...................................... 3-32 Ensure Compliance by Contractors and Subcontractors ................... 3-32 Quality Control and Procedures for Inspecting and Testing the Pipeline .............................................................................................. 3-33 3.11.10 Special Safeguards to Protect the Interests of Individuals Living in the General Area for Subsistence Purposes .................................. 3-34 3.11.11 Special Safeguards to Protect the Interests of Commercial Lodges ............................................................................................... 3-35 Right-of-Way Location (ROW) ................................................................................. 4-1 4.1 Legal Description ............................................................................................. 4-1 4.2 Site-specific Engineering Surveys for Critical Areas ....................................... 4-1 4.3 River Crossings ............................................................................................... 4-1 4.4 Calculation of Estimated right-of-way Acreage................................................ 4-3 Pipeline Design Factors ........................................................................................... 5-1 5.1 Technical Summary ......................................................................................... 5-1 5.2 Toxicity of Pipeline Product ............................................................................. 5-2 5.3 Anticipated Operating Temperatures............................................................... 5-2 5.4 Depth of Pipeline ............................................................................................. 5-3 5.5 Permanent Width or Size................................................................................. 5-3 5.6 Temporary Areas Needed ............................................................................... 5-4 Additional Right-of-Way Components .................................................................... 6-1 6.1 Connection to Existing Right-of-Way ............................................................... 6-1 6.2 Existing Components on or off Public Land..................................................... 6-1 6.3 Possible Future Components .......................................................................... 6-1 6.4 Location and Description of Compressor Station ............................................ 6-1 6.5 Location and Description of Electric Transmission Line .................................. 6-2 6.6 6-4 6.7 Location and Description of Fiber Optic Cable and Repeater Station ............. 6-4 6.8 Location and Description of Sand and Gravel Sites ........................................ 6-4 6.9 Location and Description of Pig Launcher/Receiver Facilities......................... 6-4 6.10 Location and Description of Metering Stations ................................................ 6-5 6.11 Location and Description of Mainline Block Valves ......................................... 6-7 Government Agency Involvement........................................................................... 7-1 7.1 Entities that have Regulatory Authority or would be affected by the Proposed Project ............................................................................................. 7-1 7.2 Communications Protocol................................................................................ 7-2 7.2.1 State Agency Coordination .................................................................. 7-2 7.2.2 Federal Agency Coordination .............................................................. 7-2 7.3 List of Project Authorizations ........................................................................... 7-4 7.3.1 State ROW Lease Required Documents ............................................. 7-4
Donlin Gold
ii
July 2012
Plan of Development Donlin Gold Project
8.0
Table of Contents
Construction of Facilities......................................................................................... 8-1 8.1 Construction Planning Considerations ............................................................ 8-1 8.1.1 Remote Cabins/Residential Areas ....................................................... 8-1 8.1.2 Iditarod Trail ......................................................................................... 8-1 8.1.3 Active Faults ........................................................................................ 8-4 8.1.4 Wetlands .............................................................................................. 8-4 8.1.5 Waterbodies......................................................................................... 8-5 8.1.6 Access ................................................................................................. 8-5 8.1.7 Susitna Flats State Game Refuge ....................................................... 8-6 8.1.8 Construction Communications Details ................................................. 8-6 8.2 Construction Execution.................................................................................... 8-6 8.2.1 Overview of Construction Execution .................................................... 8-7 8.2.2 Construction Execution Sequence..................................................... 8-10 8.2.3 Beluga Tie-In to BPL.......................................................................... 8-12 8.2.4 Terminus at Mine Site ........................................................................ 8-12 8.2.5 Compressor Station ........................................................................... 8-13 8.2.6 Electric Transmission Line ................................................................. 8-18 8.2.7 Fiber Optic Communication Line ....................................................... 8-18 8.2.8 Ancillary Construction Support Facilities ........................................... 8-21 8.2.9 Transportation of Equipment and Materials ....................................... 8-51 8.2.10 Construction Labor Requirements/Mobilization ................................. 8-52 8.2.11 Personnel to Support Construction .................................................... 8-52 8.2.12 Land Requirements ........................................................................... 8-54 8.2.13 Flagging or Staking the ROW ............................................................ 8-54 8.2.14 Barrier Delineation ............................................................................. 8-55 8.2.15 Vegetation Clearing and Grading ...................................................... 8-55 8.2.16 Workpad Construction ....................................................................... 8-56 8.2.17 Ice and Snow Pads ............................................................................ 8-57 8.2.18 Frost Packing ..................................................................................... 8-59 8.2.19 Winter grading ................................................................................... 8-59 8.2.20 Summer Grading ............................................................................... 8-60 8.2.21 Granular Workpad ............................................................................. 8-60 8.2.22 Workpad versus Graded Construction ............................................... 8-60 8.2.23 Temporary Stormwater Control ......................................................... 8-61 8.3 Pipe Installation ............................................................................................. 8-62 8.3.1 Blasting .............................................................................................. 8-62 8.3.2 Stringing............................................................................................. 8-63 8.3.3 Bending and Set-up ........................................................................... 8-63 8.3.4 Lineup and Welding ........................................................................... 8-64 8.3.5 Inspection (Nondestructive Examination) .......................................... 8-65 8.3.6 Field Joint Coating ............................................................................. 8-65 8.3.7 Trenching ........................................................................................... 8-66 8.3.8 Bedding.............................................................................................. 8-67 8.3.9 Lowering In ........................................................................................ 8-67 8.3.10 Buoyancy Control .............................................................................. 8-68 8.3.11 Trench Breakers ................................................................................ 8-68 8.3.12 Padding and Backfill .......................................................................... 8-68 8.3.13 Backfill ............................................................................................... 8-68
Donlin Gold
iii
July 2012
Plan of Development Donlin Gold Project
9.0
Table of Contents
8.3.14 Tie-ins ................................................................................................ 8-69 8.3.15 Waterbody and Wetland Crossings ................................................... 8-69 8.3.16 Waterbody Crossings ........................................................................ 8-70 8.3.17 Wetland Crossings............................................................................. 8-73 8.3.18 Waterbody Approaches ..................................................................... 8-75 8.3.19 Equipment Crossing .......................................................................... 8-75 8.3.20 Residential Areas (primarily remote cabins) ...................................... 8-76 8.3.21 Iditarod ............................................................................................... 8-76 8.3.22 Fault Crossings .................................................................................. 8-76 8.3.23 Snow Avalanche Hazards.................................................................. 8-79 8.3.24 Unsuitable Soils ................................................................................. 8-79 8.3.25 Permafrost ......................................................................................... 8-79 8.3.26 Mainline Block Valves and Launchers/Receivers .............................. 8-82 8.3.27 Cathodic Protection ........................................................................... 8-82 8.3.28 Cleanup, Erosion Control and Reclamation Crews ........................... 8-82 8.3.29 Cleaning, Pressure Testing and Drying ............................................. 8-83 8.3.30 Pipeline Commissioning .................................................................... 8-85 8.3.31 Engineering Drawings and Specifications ......................................... 8-85 8.4 Safety and Training Requirements ................................................................ 8-85 8.4.1 Environmental, Safety and Project Orientation/Training .................... 8-85 8.5 Environmental and Quality Control and Procedures for Inspection ............... 8-87 8.6 Signs and Markers......................................................................................... 8-87 8.7 As-Built Survey .............................................................................................. 8-88 8.8 Contingency Planning.................................................................................... 8-88 8.9 Contacts ........................................................................................................ 8-88 8.9.1 Holder Contacts ................................................................................. 8-88 8.9.2 ROW Granting Agency Contacts ....................................................... 8-88 8.10 Waste Management ...................................................................................... 8-89 Resource Values and Environmental Concerns .................................................... 9-1 9.1 Location with Respect to Existing Corridors .................................................... 9-1 9.2 Anticipated Conflicts with Resources or Public Health and Safety .................. 9-1 9.2.1 Air ........................................................................................................ 9-1 9.2.2 Noise.................................................................................................... 9-2 9.2.3 Geologic Hazards ................................................................................ 9-4 9.2.4 Mineral and Energy Resources ........................................................... 9-5 9.2.5 Paleontological Resources .................................................................. 9-5 9.2.6 Cultural Resources .............................................................................. 9-6 9.2.7 Regional Setting .................................................................................. 9-8 9.2.8 Water Resources ................................................................................. 9-4 9.2.9 Wetlands and Vegetation..................................................................... 9-5 9.2.10 Fisheries Resources ............................................................................ 9-8 9.2.11 Wildlife Resources ............................................................................. 9-10 9.2.12 Special Status Species ...................................................................... 9-12 9.2.13 Visual Resources ............................................................................... 9-13 9.2.14 Social and Economic ......................................................................... 9-15 9.2.15 Subsistence ....................................................................................... 9-16 9.2.16 State or Federal Projects ................................................................... 9-17
Donlin Gold
iv
July 2012
Plan of Development Donlin Gold Project
Table of Contents
9.2.17 Recreation Activities .......................................................................... 9-17 9.2.18 Wilderness ......................................................................................... 9-18 10.0 Stabilization, Rehabilitation and Reclamation ..................................................... 10-1 10.1 Soil Removal and Replacement .................................................................... 10-2 10.1.1 Trench/Right-of-Way.......................................................................... 10-2 10.2 Drainage and Erosion Control, Clean-up and Reclamation ........................... 10-2 10.2.1 Stabilization of the Backfilled Trench ................................................. 10-3 10.2.2 Streambank Protection ...................................................................... 10-4 10.2.3 Reclamation of Waterbody Crossings ............................................... 10-4 10.3 Clean-up Crew Functions .............................................................................. 10-5 10.4 Reclamation Crew Functions......................................................................... 10-6 10.5 Natural Reinvasion/Seeding Specifications ................................................... 10-6 10.6 Fertilizer ......................................................................................................... 10-7 10.7 Control of Non-Native Invasive Plants ........................................................... 10-7 10.8 Limiting Access to ROW ................................................................................ 10-7 10.9 Status of Temporary Roads following Construction ...................................... 10-7 10.10 Status of Temporary PSYs and Campsites ....................................... 10-7 10.11 Status of Temporary Camp Facilities following Construction ............ 10-7 10.12 Status of Temporary Airstrips following Construction ........................ 10-8 10.13 Status of Material Sites following use for Construction ...................... 10-8 10.14 Status of Barge Landings and Port Facilities following Construction .................................................................................................. 10-8 10.15 Disposition of Salvageable Materials at Completion of Construction .................................................................................................. 10-8 10.16 Status of Temporary Land needs following Construction .................. 10-8 10.17 Pipeline Maintenance Activities ......................................................... 10-8 10.18 Inspection and Monitoring.................................................................. 10-8 10.19 Unconditional Guaranty for Duties and Obligations ........................... 10-9 11.0 Operation and Maintenance................................................................................... 11-1 11.1 Operation and Maintenance Plan/Manual ..................................................... 11-1 11.2 ROW Maintenance Schedules ...................................................................... 11-1 11.3 Safety ............................................................................................................ 11-1 11.4 Removal/Addition of Pipe & Equipment Operation or Maintenance .............. 11-1 11.5 Signs and Line Markers ................................................................................. 11-1 11.6 New and Expanded Access for Operation and Maintenance ........................ 11-2 11.7 Inspection and Testing of Pipeline................................................................. 11-2 11.8 Facilities Security........................................................................................... 11-2 11.9 ROW Configuration ....................................................................................... 11-2 11.9.1 Minimum Cover.................................................................................. 11-3 11.9.2 Inspection, Surveillance and Monitoring of Right-of-way ................... 11-3 11.9.3 Encroachments .................................................................................. 11-4 11.9.4 ROW Maintenance Clearing .............................................................. 11-4
Donlin Gold
v
July 2012
Plan of Development Donlin Gold Project
Table of Contents
11.9.5 Heavy Equipment Crossing Buried Pipeline ROW ............................ 11-4 11.10 Pigging ............................................................................................... 11-5 11.10.1 Maintenance Pigging ..................................................................... 11-5 11.10.2 Smart Pigging Inspections ............................................................. 11-5 11.10.3 Disposal of Operational and Pigging Wastes................................. 11-5 11.11 Cathodic Protection and Corrosion Control ....................................... 11-6 11.12 Valves ................................................................................................ 11-6 11.12.1 Access to Values ........................................................................... 11-7 11.13 Overpressure Safety Devices ............................................................ 11-7 11.14 Smoking or open Flames ................................................................... 11-7 11.15 Pipe Movement .................................................................................. 11-7 11.16 Normal Operating and Maintenance Procedures Review .................. 11-8 11.17 Construction Records ........................................................................ 11-8 11.18 Operations Records ........................................................................... 11-9 11.19 Drug Testing .................................................................................... 11-10 11.20 Industrial Waste and Toxic Substances near Right-of-way ............. 11-11 12.0 Termination and Final Reclamation ...................................................................... 12-1 12.1 Removal of Structures at Termination ........................................................... 12-1 12.2 Status of Pipe ................................................................................................ 12-1 12.3 Status of Transmission Line .......................................................................... 12-2 12.4 Status of Fiber Optic Cable ........................................................................... 12-2 12.5 Status of Roads ............................................................................................. 12-2 12.6 Status of Material Sites.................................................................................. 12-2 12.7 Status of Retained Barge Landings ............................................................... 12-3 12.8 Status of Retained Airstrips ........................................................................... 12-3 12.9 Disposition of Salvageable Materials............................................................. 12-3 Final Stabilization, Rehabilitation and Reclamation of Disturbed 12.10 Areas 12-3 13.0 References .............................................................................................................. 13-1
APPENDICES Appendix A: Appendix B: Appendix C: Appendix D: Appendix E: Appendix F: Appendix G:
Donlin Gold
Strip Maps Line List Geotechnical Survey Data Stream Crossings Engineering Typicals Construction Plan and Schedule Right-of-Way Typicals
vi
July 2012
Plan of Development Donlin Gold Project
Table of Contents
FIGURES Figure 1-1: Location of Proposed Donlin Gold Natural Gas Pipeline Route ...................................... 1-2 Figure 3-1: Corporate Organization Structure .................................................................................... 3-8 Figure 3-2: Theodore River Alternate Route .................................................................................... 3-14 Figure 3-3: Little Mount Susitna Alternate Route ............................................................................. 3-15 Figure 3-4: Round Mountain Alternate Route................................................................................... 3-16 Figure 3-5: Goodman Pass Alternate Route .................................................................................... 3-17 Figure 3-6: Egypt Mountain Alternate Route .................................................................................... 3-18 Figure 3-7: St Johns Hill Alternate Route ......................................................................................... 3-19 Figure 3-8: Windy Fork Alternate Route ........................................................................................... 3-20 Figure 3-9: Big River Alternate Route .............................................................................................. 3-21 Figure 3-10: Tatlawiksuk River Alternate Route ............................................................................... 3-22 Figure 3-11: Kuskokwim River Alternate Route ............................................................................... 3-23 Figure 3-12: Moose Creek Alternate Route...................................................................................... 3-24 Figure 3-13: Kuskokwim Hills Alternate Route ................................................................................. 3-25 Figure 3-14: Lodge Locations ........................................................................................................... 3-37 Figure 4-1: Beluga Camp Storage & Pipe Yard Areas ....................................................................... 4-2 Figure 6-1: Compressor Site Location Map........................................................................................ 6-3 Figure 6-2: Metering Stations ............................................................................................................. 6-6 Figure 7-1: Communication Protocol .................................................................................................. 7-3 Figure 7-2: State ROW Lease Required Documents ......................................................................... 7-5 Figure 8-1: Compressor Station Site Plan ........................................................................................ 8-15 Figure 8-2: Electric Transmission Line and Fiber Optic Cable ......................................................... 8-20 Figure 8-3: General Construction Camp Configuration .................................................................... 8-35 Figure 8-4: Camp Movement Plan Diagram ..................................................................................... 8-36 Figure 8-5: Permafrost Distribution Map .......................................................................................... 8-81 Figure 9-1: Physiographic Divisions ................................................................................................... 9-9 Figure 9-2: ADF&G Game Units and Guide Use Areas within Pipeline Corridor ............................. 9-21
Donlin Gold
vii
July 2012
Plan of Development Donlin Gold Project
Table of Contents
TABLES Table 3-1: Composition of Gas to be Transported ............................................................................. 3-2 Table 3-2: Spread Execution Squence ............................................................................................... 3-6 Table 3-3: Number of Persons Employed .......................................................................................... 3-7 Table 3-4: Cost of Proposed Natural Gas Pipeline ............................................................................ 3-7 Table 3-5: Commercial Lodges ........................................................................................................ 3-36 Table 4-1: Estimated Acres Calculation ............................................................................................. 4-3 Table 5-1: Project Specific Design Criteria ......................................................................................... 5-1 Table 5-2: Minimum Cover Requirements .......................................................................................... 5-3 Table 6-1: Mainline Valve Location Summary .................................................................................... 6-8 Table 7-1: Federal, State and Local Agencies with Regulatory Authority .......................................... 7-1 Table 7-2: Federally Recognized Tribes along the Pipeline Route by Region ................................... 7-2 Table 7-3: Permits and Authorizations ............................................................................................... 7-6 Table 8-1: Proximity of Pipeline to Iditarod Trail................................................................................. 8-3 Table 8-2: Construction Execution Sequence .................................................................................. 8-10 Table 8-3: Operating Design Factors ............................................................................................... 8-14 Table 8-4: Pipe Storage Yards ......................................................................................................... 8-23 Table 8-5: Potential Material Sites.................................................................................................... 8-27 Table 8-6: Pipeline Shoofly and Access Roads Material Needs ...................................................... 8-31 Table 8-7: Pipeline Airfields Material Needs .................................................................................... 8-31 Table 8-8: Access Road Identifications ............................................................................................ 8-38 Table 8-9: Potential Water Sources and Use ................................................................................... 8-41 Table 8-10: Pipeline Construction Fuel Estimate ............................................................................. 8-47 Table 8-11: Approximate Fuel Quantities by Spread and Section ................................................... 8-48 Table 8-12: HDD and HDD Camp Fuel Estimate ............................................................................. 8-49 Table 8-13: Fuel Handling and Storage ........................................................................................... 8-50 Table 8-14: Characteristics of Castle Mountain Fault ...................................................................... 8-77 Table 8-15: Characteristics of Denali Fault ....................................................................................... 8-78
Donlin Gold
viii
July 2012
Plan of Development Donlin Gold Project
Table of Contents
ACRONYMS ASCE CWMP JP QCP VFD ADEC ADF&G AHPA ANHP ANSCA ANSI APE API ARO ARPA AS ASME ATV AUT AWS BLM BMPs BPL BTU Calista CEA CFR CIRI CMP COE CP CWA DCJV DNR EIS ENSTAR EPA ESD
Donlin Gold
American Society of Civil Engineers Comprehensive Waste Management Plan Jungjuk Port Quality Control Plan variable frequency drive Alaska Department of Environmental Conservation Alaska Department of Fish and Game Alaska Historic Preservation Act Alaska Natural Heritage Program Alaska Native Settlement Claims Act American National Standards Institute area of potential effect American Petroleum Institute abrasion-resistant overcoat Archeological Resource Protection Act Alaska Statutes American Society of Mechanical Engineers all terrain vehicle automated ultrasonic testing American Welding Society U.S. Department of Interior, Bureau of Land Management best management practices Beluga natural gas pipeline British thermal units Calista Corporation Chugach Electric Association Code of Federal Regulations Cook Inlet Regional Corporation Comprehensive Management Plan U.S. Army Corps of Engineers cathodic protection Clean Water Act Donlin Creek Joint Venture Alaska Department of Natural Resources environmental impact statement ENSTAR Natural Gas Company. U.S. Environmental Protection Agency emergency shutdown
ix
July 2012
Plan of Development Donlin Gold Project
FBE FERC GCI GIS GMAW GMU GPS HDD HSE IBC ILI IMC INHT LGP LIDAR MAOP MEA MLV MOA MP MV NDE NEC NEPA NESC NFPA NHPA NIP NPDES (APDES) NPS NTP O&M OSHA PDC PDUS PHMSA POD PRPA PSY
Donlin Gold
Table of Contents
fusion-bonded epoxy Federal Energy Regulatory Commission General Communications, Inc. geographical information system gas metal arc welding Game Management Unit global positioning system horizontal directional drilling health, safety, and environmental International Building Code inline inspection International Mechanical Code Iditarod National Historic Trail low ground pressure light detection and ranging maximum allowable operating pressure Matanuska Electrical Association mainline block valve Memorandum of Agreement Milepost medium voltage nondestructive examination National Electrical Code National Environmental Policy Act National Electric Safety Code National Fire Protection Association National Historic Preservation Act non-native invasive plants National Pollution Discharge Elimination System (now Alaska Pollution Discharge Elimination System) Nominal pipe size notice to proceed operation and maintenance U.S. Department of Labor, Occupational Safety and Health Administration power distribution center Placer Dome U.S. Pipeline Hazardous Materials and Safety Administration Pplan of Ddevelopment Paleontological Resources Preservation Act Pipe Storage Yard
x
July 2012
Plan of Development Donlin Gold Project
RAA RCA ROD ROW RT SCADA SHPO SLE SPCC SPCO SRK SWPPP TAPS TKC TSCA UL UPS USDOT USFWS USGS VRM WT
Donlin Gold
Table of Contents
Resource Associates of Alaska Regulatory Commission of Alaska Record of Decision Right-of-way radiographic testing supervisory control and data acquisition State of Alaska Historic and Preservation Office section line easements Spill Prevention, Control, Countermeasure Plan State Pipeline Coordinator’s Office SRK Consulting (US), Inc. Storm Water Pollution Prevention Plan Trans Alaska Pipeline System tThe Kuskokwim Corporation Toxic Substances Control Act Underwriters Laboratories uninterruptible power supply U.S. Department of Transportation U.S. Fish and Wildlife Service U.S. Geological Survey visual resource management wall thickness
xi
July 2012
Plan of Development Donlin Gold Project
Table of Contents
UNITS OF MEASURE ac AF cfs cm d ft ft3 G gpm g/L Gst g/t h ha hp In km km/h kW L lb m m3 µg/L µm µS µS/cm Mt/a MW NP/AP NRMS pH sq. miles t
Donlin Gold
acre acre-foot (43,560 cubic feet) cubic feet per second centimeter day foot/feet cubic feet giga (billion) U.S. gallons per minutes grams per liter billion short tons grams per tonne hour hectares horsepower inch(es) kilometers kilometers per hour kilowatt liter pound meters cubic meters micrograms per liter micrometer (micron) microsiemens microsiemens per centimeter million tonnes per year mega watts neutralizing potential to acid generating potential ratio normalized root mean square measure of the acidity or base acidity of an aqueous solution square miles tonne
xii
July 2012
Plan of Development Donlin Gold Project
1.0
Introduction
INTRODUCTION
This Plan of Development (POD) has been prepared by Donlin Gold LLC to support the planning and development of the proposed Donlin Gold Natural Gas Pipeline project. The POD provides detailed information to support regulatory processes, permit applications, and preparation of the National Environmental Policy Act (NEPA) documents. Donlin Gold proposes to construct the proposed pipeline in conjunction with and in support of its proposed Donlin Gold mine project in Southwest Alaska. For additional information, refer to the Donlin Gold Plan of Operations, Project Description (SRK Consulting (US) Inc. [SRK] 2012). The 14-inch (356 mm) (nominal pipe size [NPS]) pipeline would transport natural gas approximately 313 miles (503 km), from an existing 20-inch (508 mm) natural gas pipeline near Beluga, Alaska, the pipeline’s point of origin, to the mine site near Crooked Creek, its point of termination. Figure 1-1 is a location map for the proposed Donlin Gold Natural Gas Pipeline Project, hereinafter referred to as proposed pipeline project or pipeline. This POD includes information about the following: •
Purpose and need
•
Background information
•
Project description
•
Right-of-way location
•
Facility design factors
•
Government agency involvement
•
Project construction
•
Fiber optic cable
•
Electric transmission line to compressor station
•
Resource values and environmental concerns
•
Stabilization, rehabilitation and reclamation
• •
Operation and maintenance (O&M) Termination and final reclamation.
This POD would be modified to incorporate any applicable measures for route adjustment, construction practices and seasonality, mitigation requirements, or other requirements that may be developed and contained in the Record of Decision (ROD) for the environmental impact statement (EIS) prepared in support of the federal review on the proposed project. It would also be modified as necessary to address measures developed by State and Federal agencies as a result of their review and authorization process for the Right-of-way (ROW) Leases and other authorizations associated with the proposed pipeline project.
Donlin Gold
1-1
July 2012
Chukchi Sea
Hamilton Nome
Chuloonawick Emmonak Alakanuk Nunam Iqua
A AD N CA
Anchorage
Bethel
Bering Sea
Takotna
ammon Bay
r
Nikolai
Juneau
Shageluk
Anvik
Talkeetna Iditarod Flat
DONLIN GOLD HolyPROJECT Cross
iv Yukon R
er
Skwentna
Georgetown Crooked Creek
Russian Mission
Upper Kalskag Lower Kalskag
Ohogamiut
R i ve
Petersville
Gulf of Alaska
Marshall
McGrath
Grayling
Donlin Gold Mountain Village Pitkas Point Saint Mary's Pilot Station
Medfra
Ophir
Stony River Red Devil
River
Fairbanks
Denali National Park & Preserve
Innoko National Wildlife Refuge
Susitna
ALASKA
Kotlik
Bill Moores Slough
Telida
im
IA
Barrow
Kuskok w
S
er
S
Stebbins Saint Michael
Riv
U
Yuk on
Susitna
Sleetmute
Willow Houston
Palme
Wasilla Big Lake
Knik
Eklutna
Chuathbaluk Aniak
River
Anchorage
Napaimute Lime Village
Yukon Delta National Wildlife Refuge
Beluga Tyonek
Hope
Tuluksak Newtok Kasigluk Atmautluak
Toksook Bay
Nunapitchuk
Bethel
Akiak Salamatof Kenai
Lake Clark National Park & Preserve
Ku sk
ghtmute
Port Alsworth
Ninilchik
K
Eek
Soldotna
Kasilof Clam Gulch
IN
Tuntutuliak Chefornak
Cooper Landing
Nikiski Kwethluk Oscarville Napaskiak
ok w
im
Napakiak
Akiachak
LE T
Mertarvik
Nondalton Pedro Bay
Kwigillingok Quinhagak
Newhalen
Koliganek
KUSKOKWIM BAY
Nikolaevsk
O
Wood-Tikchik State Park
Kongiganak
O
Kipnuk
Togiak National Wildlife Refuge
mn Illi a New Stuyahok
ke a La
Iliamna
Anchor Point
C
R
Cantwell
Kachemak
Homer Seldovia
Kokhanok
Nanwalek Port Graham
Igiugig
Portlock
Ekwok Aleknagik
Populated Places
Goodnews Bay
SCALE:
Proposed Natural Gas Pipeline Alignment Proposed Infrastructure Layout Federal Administrative Boundaries State Administrative Boundaries
Seward Meridian, UTM Zone 5, NAD83
FIGURE:
Levelock
0
12.5
25
50 mi
0
20
40
80 km
PROJECT LOCATION MAP
1-1
DONLIN GOLD PROJECT DG: PER0130.mxd, 07/11/12, R05
Moo
Plan of Development Donlin Gold Project
2.0
PURPOSE AND NEED
2.1
Purpose
Purpose and Need
The purpose of the Donlin Gold Natural Gas Pipeline Project is to provide a long-term, stable supply of natural gas to meet energy needs for the proposed Donlin Gold mine project. The proposed pipeline is designed as a privately owned facility to support the proposed mine operation. Natural gas supplied by the pipeline would be used to create electricity for the facility, operations, and heat for buildings. The use of natural gas supplied via the proposed pipeline project has been evaluated and determined to be the most practicable cost effective and environmentally acceptable means of providing a reliable longterm energy source for the proposed Donlin Gold mine project.
2.2
Need
The mine site is remote and without existing or readily developable resources that can serve as an energy supply within the timeframe needed for development of the mine. The location of the proposed mine project does not currently have adequate, naturally occurring gas resources to create sufficient energy supply for mine operations. No other energy sources or supplies of the magnitude necessary for mine operations are present or likely to be developed in proximity to the mine site or otherwise available in a timeframe needed for development of the mine. No existing transportation or utility infrastructure services the proposed mine site or surrounding area. Access to the mine site is seasonal via the Kuskokwim River or by aircraft, as weather conditions allow. Therefore, the natural gas pipeline is needed to bring in a stable and reliable source of energy sufficient for mine operations.
2.3
Background and Proposed Mine Information
The proposed Donlin Gold mine that would be served by the pipeline is a large, undeveloped, refractory gold deposit located approximately 10 miles (16 km) north of the village of Crooked Creek on the Kuskokwim River and about 277 air miles (446 km) northwest of Anchorage. The deposit is situated on Native lands owned by the Kuskokwim Corporation (TKC) the surface estate and Calista Corporation (Calista) the surface and subsurface estate. Placer gold was first discovered at Snow Gulch, a tributary of Donlin Creek in 1909. Resource Associates of Alaska (RAA) carried out a regional evaluation for Calista in 1974 to 1975, identifying mineral potential in the area. Calista conducted prospecting and limited exploration activities in 1984. The first substantial exploration program was carried out by Westgold in 1988 to 1989. Teck operated the project briefly in 1993. Placer Dome U.S. (PDUS) explored the property from 1995 to 2000, formed the Donlin Creek Joint Venture (DCJV) with NovaGold as operator in 2001, and then reassumed management of the DCJV as operator in February 2003. Barrick Gold merged with Placer Dome in 2006 and acquired the PDUS interest in the DCJV. In December 2007 Donlin Creek LLC was formed as a
Donlin Gold
2-1
July 2012
Plan of Development Donlin Gold Project
Purpose and Need
limited liability company with 50/50 ownership by Barrick Gold U.S. and NovaGold Resources Alaska, Inc. In 2011, Donlin Creek LLC changed its name to Donlin Gold LLC. Donlin Gold is proposing the development of an open pit, hardrock gold mine. The proposed project would require three to four years to construct, with the active mine life currently projected to be approximately 27.5 years. The mine is proposed to be a year-round, conventional “truck and shovel” operation using both bulk and selective mining methods. Electric power would be supplied by onsite generation. General cargo for operations would be transported from terminals in Seattle, Vancouver, BC or Dutch Harbor via marine barge to Bethel. At Bethel, it is expected that the cargo would be transferred to the dock for temporary storage or loaded directly onto river barges for transport up the Kuskokwim River to a port constructed at Jungjuk Creek. A 30 mile (48 km) all-season access road would be constructed from the proposed Jungjuk Port to the mine site. Fuel would be transported to Dutch Harbor by tanker, then to Bethel via marine barge. At Bethel fuel would either be transferred directly to double-hull river barges, or off-loaded for temporary storage. From Jungjuk Port fuel would be transferred to the mine site fuel storage facility via tank trucks. The proposed mine project would be a camp operation also accessible by a 5,000 foot (1,524 m) gravel airstrip, with a camp capable of housing 638 workers. The proposed pipeline would serve as an alternative to diesel power generation, reduce port facility storage needs and reduce the amount of diesel fuel required for operational purposes to a projected annual requirement of approximately 40,000,000 gallons (151,455,000 L).
2.4
Expected Public Benefits
The pipeline route and mine are located in areas that provide few long term employment opportunities. Good jobs, services, and health care are hard to obtain in the small, isolated, rural communities, resulting in gradual attrition of people to larger communities. With the exception of the jobs created by a few small businesses that provide services to the local communities, regular, full-time jobs are in high demand. Job opportunities currently are limited primarily to the government or social organization sector. Economic benefits from the proposed pipeline include excise tax revenues from its operation. In addition, it would create short- and long-term employment opportunities. Camp support and construction labor (skilled and unskilled) would be needed during pipeline construction. Pipeline operation and maintenance would be ongoing throughout the 30-year or greater use life of the pipeline. Mine development and operation that are supported by the pipeline represent greater employment opportunities and revenue stream for the local communities.
Donlin Gold
2-2
July 2012
Plan of Development Donlin Gold Project
Purpose and Need
The use of natural gas as a stable reliable fuel source for heating and power generation potentially reduce the project’s impacts as opposed to diesel. Additionally, providing a means for a reliable natural gas fuel source to the proposed Donlin Gold mine project may create opportunities for further development of natural gas use beyond that of the Donlin Gold project.
Donlin Gold
2-3
July 2012
Plan of Development Donlin Gold Project
3.0
Project Description
PROJECT DESCRIPTION
This POD only addresses the natural gas pipeline portion of the proposed Donlin Gold proposed mine project. For additional information, refer to the Donlin Gold Plan of Operations, Project Description (SRK 2012). The proposed pipeline route has been located and evaluated based on currently known technical, environmental, cultural, land ownership, and economic considerations. Additionally, the pipeline portion of the proposed mine project would have limited effects on air quality because it does not include nor address the emissions for producing power at the mine site. The pipeline would be designed and constructed in accordance with the following primary pipeline regulations and design codes: • • • •
49 Code of Federal Regulations (CFR) Part 192: Transportation of Natural Gas and Other Gas by Pipeline: Minimum Federal Safety Standards; October 1, 2007 American Society of Mechanical Engineers (ASME) B31.8: Gas Transmission and Distribution Piping Systems Alaska Petroleum Institute (API) 5L, Specification for Line Pipe API 1104, Welding of Pipelines and Related Facilities.
There may be instances in which Donlin Gold requests variances, modifications, or exceptions to particular requirements of these regulations and codes which would be determined at final design. The proposed pipeline approximately 313 miles long (503 km) would originate at the west end of the Beluga Gas Field, approximately 30 miles (48 km) northwest of Anchorage at a tie-in near Beluga located in the Matanuska-Susitna Borough and would run to the Donlin Gold mine located in Southwest Alaska. The route initiates at the Beluga Natural Gas Pipeline (BPL) (natural gas source) which would be designated milepost 0 (MP), within the Susitna Flats State Game Refuge, and the pipeline would receive booster compression supplied by one compressor station located at approximately MP 5 of the pipeline just outside the north boundary of the refuge. No additional compression along the pipeline route would be required. The route then proceeds north, traversing the east flank of Little Mount Susitna to the Skwentna River (MP 48), and then parallels the Skwentna River westerly to Puntilla Lake (MP 100). The route crosses the Alaska Range through Rainy Pass (MP 113) and Rohn (near MP 132). Beyond Rohn, the route turns southwest near Farewell (MP 155), paralleling the Alaska Range until crossing the Kuskokwim River (MP 238). Beyond the Kuskokwim River, the route primarily follows ridgelines for more than 80 miles (129 km) toward the west, to the proposed Donlin Gold mine site that is the pipeline terminus at approximately MP 313, about 10 miles (16 km) north of the village of Crooked Creek. The pipeline route crosses an area with no significant preexisting infrastructure and does not follow any existing utility corridors. The 14-inch (356 mm) natural gas pipeline would be designed to transport approximately 50 million standard cubic feet per day (mmscfd) of natural gas (1,415,842 m3pd). The compressor station would be supplied with electric power by extending an existing transmission line to the facility. The power transmission line would be constructed to the compressor station from Beluga as shown in Appendix A and Figure 6-1. Donlin Gold would install a fiber optics cable from Beluga with the power transmission line to the metering station at pipeline MP 0 where it would then be installed in the buried mode with the pipeline to the compressor station and on to the mine site. The pipeline would be regulated by the U.S. Department of Transportation (USDOT) under Title 49 of the Code of Federal Regulations, Part 192 – Transportation of Natural Gas and Donlin Gold
3-1
July 2012
Plan of Development Donlin Gold Project
Project Description
Other Gas by Pipeline: Minimum Federal Safety Standards (49 CFR 192). The pipeline would be designed, constructed, and operated in accordance with the applicable requirements of 49 CFR 192 and would incorporate pig launching and receiving facilities (receipt, midpoint, and delivery), approximately 19 mainline block valves (MLVs), cathodic protection, leak detection, a supervisory control and data acquisition (SCADA) system, and a fiber optics cable to the mine site. The pipeline would be designed to operate at up to 1,480 pounds per square inch gauge (psig), maximum allowable operating pressure (MAOP). The minimum delivery pressure required at the mine would be 550 psig—subject to final hydraulic considerations. Preliminary hydraulic analysis using a worst case hydraulics scenario was completed for the entire pipeline. The results of this analysis indicated that the pipeline would be able to transport the required amount of gas without over pressurization and still deliver the gas at the required pressure at the pipeline terminus at the Donlin Gold mine site. Final pipeline hydraulics, based on a centerline from the natural gas receipt point to the mine delivery location, would be confirmed during the first phase of detailed design. The design life of the proposed pipeline is 30 years; however, design life may be extended with additional maintenance and repair. Resources used to define the route and evaluate alternates included high-resolution orthophotography, light detection and ranging (LIDAR) data (1-meter elevation contours), Google Earth satellite imagery, high-level infrared imagery, U.S. Geological Survey (USGS) topographic maps at 1:250,000 and 1:63,000 scale, USGS surficial and bedrock geology maps, and Alaska Department of Natural Resources (DNR) maps. Fieldwork included overland snowmachine and numerous aerial reconnaissance trips to further refine the routing and conduct on-the-ground inspections of terrain and major river crossings. The first aerial reconnaissance flight, which took place during the 2008 study, obtained continuous global positioning system (GPS) linked videographic imagery of the route from a low altitude. Detailed engineering and environmental studies of the proposed route were conducted in the years following the initiate route definition in 2008
3.1
Commodity to be Transported and Purpose
The proposed Donlin Gold pipeline would receive natural gas from the BPL and transport the gas to an endpoint at the mine. The pipeline would be installed as a subsurface line except at two active fault locations that would supply gas to provide heating and generate electricity to power the industrial equipment and, possibly, the heavy equipment at the mine. The primary composition of the gas is assumed to be similar to that used within the Cook Inlet pipeline network and is shown in Table 3-1. Table 3-1: Composition of Gas to be Transported Component
Unit
Typical
Contractual Limit
Methane
Mol%
98.851
TBD
Carbon dioxide
Mol%
0.541
TBD
Nitrogen
Mol%
0.539
TBD
Ethane
Mol%
0.063
TBD
C4+
Mol%
0.006
TBD
C4+ = all hydrocarbons having more than four carbon atoms TBD = to be determined
Donlin Gold
3-2
July 2012
Plan of Development Donlin Gold Project
Project Description
Other characteristics of the gas are expected to be: • • • •
Specific gravity: 0.5618 Typical water content: 2.5 to 3.5 lbs per million standard cubic feet (mmscf) Maximum water content: 4 pounds per mmscf Energy content: 1,000 British thermal units (Btu).
The quantity of natural gas that can be transported through the mainline is 50 mmscfd, with a MAOP of 1,480 lb. per square inch gauge (psig). Refer to Section 8.2.5 and Table 8-3 for more information.
3.2
Pipe to be used for Transportation of Natural Gas
The Donlin Gold natural gas pipeline requires the use of an estimated 319 miles (513 km) of pipe. Per USDOT, Pipeline and Hazardous Materials Safety Administration (PHMSA) requirements, pipe of the appropriate thickness would be used based upon location class. Federal requirements stipulate the minimum wall thickness for a specific line class. The line class used for this pipeline is class 1, with a corresponding design factor of 0.72. It was determined that pipe with a wall thickness below 0.30 inch (7.62 mm) would be very difficult to transport and handle without resulting in pipe damage (denting). No wall thickness below 0.300 inch (7.62 mm) was selected for the 14-inch (356 mm) pipe. Another criterion used for wall thickness was the use of standard American Petroleum Institute (API) Specification 5L, wall thicknesses. The yield strength used for the 14 inch (356 mm) pipe is 52,000 lb. psi. A 14-inch (356 mm) diameter (outside diameter), API-5L X-52 PSL2 pipe, with a maximum allowable operating pressure of 1,480 lb. psi gauge would be used. The baseline pipe wall thickness (WT) is 0.312 inch (7.9 mm). Geotechnical hazards such as thaw settlement and frost heave would require additional wall thickness, and 0.344-inch (8.7 mm) or 0.375-inch (9.5 mm) WT is specified in areas where these hazards are present. Pipe to be laid in areas requiring additional strength during pressure testing because of large elevation changes or requiring buoyancy control in wetlands would have 0.375 inch (9.5 mm) WT, and saddlebags or screw anchors would not be needed. For horizontal directional drill (HDD) installations, aboveground fault crossings, and other high-hazard areas, 0.406-inch (10.3 mm) WT is specified.
PIPE INFORMATION Location
Wall Thickness (inches)
Pipe Diameter (inches)
Maximum Allowable Operating Pressure (psi)
Mainline
0.312
14
1,400
Est. Amount of Pipe (miles) Lengths: TRL 64 ft maximum, 60 ft minimum and 62 ft average 45.3 (72.9 km)
0.344
118.2 (190.2 km)
0.375
126.3 (203.3 km)
0.406
28.9 (46.5 km)
Pipe lengths: TRL (total random length) 64 ft maximum (19.5 m), 60 ft (18.3 m) minimum and 62 ft (18.8 m) average
Donlin Gold
3-3
July 2012
Plan of Development Donlin Gold Project
3.3
Project Description
Timeline of Proposed Project
Donlin Gold estimates a 2 year pipeline installation schedule and 3 year overall project construction schedule, including infrastructure buildout and ROW stabilization, rehabilitation and reclamation. This approach is predicated on pipeline contractor mobilization in the summer (S 0.5) following project permit receipt, and start of pipe lay in (S 0.5) at the mine site. Actual dates are dependent on receipt of permits. Details are provided in Appendix F. See note on Table 3-2 for explanation of “S” and “W” use in tables and text. 3.3.1
Planned Commencement Date for Construction
The planned commencement date for construction would be dependent upon receipt of project authorizations for construction, which is currently estimated to be 2015. Preliminary work including early material site development, construction of Pipe Storage Yards (PSY) and camp pads, construction of airstrips and airstrip upgrades, camp mobilization, camp construction, and installation of construction communications would begin during the winter before the summer of pipeline contractor mobilization. Pipe haul to the PSYs would begin approximately 1 year before the first winter of pipeline construction, except in Spread 6, where pipe hauling would be just ahead of ROW preparation but after the civil contractors have established access. The pipe haul to the PSYs would be part of the pipeline contractors’ scope of work. The two pipeline construction contractors would be scheduled to mobilize in summer (S 0.5), based on receipt of project permits in the fall of W 0.0. The pipeline contractor for Spread 1 that mobilizes up the Kuskokwim River to the proposed Donlin Gold mine site would begin ROW grading immediately upon mobilization in late June (S 0.5) and proceed with all pipe installation activities. The Spread 1 civil contractor would mobilize in (S 0.5) and would begin infrastructure development and ROW clearing during the winter and spring of (W 1.0), including the following primary activities: • • • •
Development of material sites Bedding and padding production Construction of access roads to barge landings, campsites, airstrips, ROW, and material sites Construction of temporary construction access bridges and gravel workpad at the three George River crossings.
In the summer preceding any winter or summer construction, some preliminary civil work would be completed. Such work would include access road construction, gravel workpad construction (where possible), and production of bedding/padding material. These activities are best accomplished in summer. 3.3.2
Estimated Construction Time
Donlin Gold estimates a 2 year pipeline installation schedule and 3 year overall project construction schedule, including infrastructure buildout and initial ROW stabilization, rehabilitation and reclamation. The proposed pipeline would be constructed using two pipeline construction spreads and generally working during two winters and two or three summer construction seasons:
Donlin Gold
3-4
July 2012
Plan of Development Donlin Gold Project
Project Description
•
Pipeline construction would be divided into the two spreads, one 128 miles (206 km) in length and one 185 miles (298 km) in length.
•
Each spread would be awarded to a single pipeline contractor that would work over a period of 2 years to install the pipeline: −
Spread 1 (MP 313–MP 128) would be further broken into four sections that would vary in length from 5 to 71 miles (8 to 114 km)
−
Spread 2 (MP 0–MP 128) would be further broken into three sections that would vary in length from 15 to 52 miles (24 to 84 km)
−
Each section would be scheduled for installation during a single winter or summer season as shown in Table 3-2 and in more detail in Appendix F: Construction Plan and Schedule
•
Construction of access roads and gravel workpads, and production of bedding and padding material would be done primarily during the season that precedes the pipeline construction season, whether winter or summer.
•
Pressure testing and final reclamation of winter sections would always take place during the spring shoulder season and/or the summer after pipe lay. Nevertheless stabilization, rehabilitation and reclamation activities would progress to the extent feasible and prudent as construction progresses.
The construction season for any particular section is based on terrain, geotechnical conditions, most efficient ROW construction mode, season length, accessibility, and other factors. 3.3.3
Planned Commencement Date for Operation
The planned date to commence operation of the natural gas pipeline to support the proposed Donlin Gold mine project is estimated to be in S 2.5, in 2018. 3.3.4
Duration of Pipeline Operation
The pipeline is expected to be in operation for at least the productive life of the Donlin Gold proposed mine. The anticipated mine life is 25-30 years. The engineering design life of the pipeline is 30 years. The actual operational life of the pipeline is dependent on and may be extended by operational and maintenance upkeep and repair.
Donlin Gold
3-5
July 2012
Plan of Development Donlin Gold Project
Project Description
Table 3-2: Spread Execution Squence
From Milepost
To Milepost
Length (Miles)
Season*
Daily Lay Rate (linear feet)
6
313.0
244.8
68.2
S0.5
5,416
July
August
69
October
October
5
244.8
187.4
57.4
W1
4,388
November
January
70
March
April
3c
133.0
128.0
5.0
S1.5
4,023
June
July
7
July
September
4
133.0
187.4
54.4
W2
4,571
January
January
63
March
April
Section
Start for ROW Work
Start for Pipe Lay
Pipe Lay Duration (Number of Days)
Complete for Pipe Lay
End-of-Season
Spread 1
Subtotal Spread 1
185.0
Spread 2 1
0.0
49.0
49.0
W1
4,793
November
January
54
March
April
3a
100.0
113.0
13.0
W1
4,793
March
March
15
April
April
3b
113.0
128.0
15.0
S1.5
4,023
June
July
20
July
September
2
100.0
49.0
51.0
W2
3,982
November
January
68
March
April
Subtotal Spread 2
128.0
Total Route
313.0
ROW = right of way *Seasons in the pipe lay construction sequence have been designated as winter (W) or summer (S), followed by a number: winters are numbered W1 and W2, and summers are numbered S0.5, S1.5 and S2.5. S1.5 falls between W1 and W2. Pipeline mobilization is scheduled for S0.5 and pipeline commissioning is scheduled for S2.5.
Donlin Gold
3-6
July 2012
Plan of Development Donlin Gold Project
3.4
Project Description
Estimated Number of Persons to be Employed
Table 3-3: Number of Persons Employed Peak Construction Work Force
650 personnel
Operation and Maintenance
Minimum of 4 full time personnel
Termination/Final Reclamation
50 personnel minimum
There would be a minimum of 4 personnel operating or maintaining the pipeline. They would be located at the proposed Donlin Gold mine project site, and/or in Anchorage. At the mine personnel would be housed in the camp housing facility and if located in Anchorage no housing would be provided
3.5
Financing Requirements for the Proposed Project
Table 3-4: Cost of Proposed Natural Gas Pipeline COST ITEM
ESTIMATED COST (Million $) $4.4 $580.1
Land Costs Materials/Construction-Pipeline • Materials • Construction Materials/Construction-Facilities
• •
• Materials • Construction Project Infrastructure Transmission Line (TL) & Fiber Optic Cable (FOC) Other Project costs and Allowances
• •
$106.2 $473.9 $29.8 $18.8 $11.0
$179.9 $4.4 (cost only to compressor station) $218.1
Total Materials Construction and Installation
$1,016.7
•
Total Materials
•
•
Total Construction and Installation
•
Annual Operation and Maintenance
$125.0 (does not include TL or FOC) $484.9 (does not include TL or FOC) $96.0 ($3.2 per year for 30 years)
Termination/Final Reclamation
$9.6
Estimated Total Cost
$1,122.3
Donlin Gold LLC is a limited liability company owned by Barrick Gold U.S. Inc. and NovaGold Resources Alaska, Inc. The pipeline would be owner financed. Figure 3-1 provides the corporate organizational structure showing Donlin Gold LLC and its parent companies. 3.5.1
Corporate Organization Structure
At the end of 2007, NovaGold Resources, Inc. and Barrick Gold U.S. Inc., a subsidiary of Barrick Gold, formed the Donlin Creek LLC (equally owned by both partners)to oversee development of the Donlin Gold project. In 2011, Donlin Creek LLC changed its name to Donlin Gold LLC.
Donlin Gold
3-7
July 2012
Plan of Development Donlin Gold Project
Project Description
Figure 3-1: Corporate Organization Structure
3.6
Natural Gas Distribution Line
The proposed pipeline would be a distribution line that would connect to the existing gas pipeline distribution system approximately 8.5 miles (14 km) north of the Beluga Power Plant, near Beluga. The line would then be routed across the Alaska Range to a receipt point (outlet metering facility) at the proposed Donlin Gold mine site, a large volume customer. The proposed pipeline route is shown in Figure 1-1 and in Appendices A and F. There are no plans at this time for future connections at intermediate points along the pipeline route. Any future connections to the pipeline whether for transporting or as off-takes of natural gas would be evaluated on a case-by-case basis. Factors that would be considered in determining the technical and economic feasibility of such cases may include as applicable, but are not limited to: • •
Donlin Gold
Implementation of quality control measures to help ensure that any new product to be transported is compatible with the existing gas being transported Location of connection
3-8
July 2012
Plan of Development Donlin Gold Project
• • • • •
• •
3.7
Project Description
Impact to pipeline operations - rate, pressure, estimated total quantity, continuity, and control of flow into and out of the pipeline Impact to existing use and pipeline capacity Leak detection monitoring and surveillance requirements Measurement/custody transfer requirements Compliance with applicable safety, environmental and relevant state and federal pipeline regulations and laws including Regulatory Commission of Alaska (RCA) regulation Regulatory and Lease requirements. Economic feasibility of installing the new connection including compensation for changes to operational costs
Surface and Subsurface Attributes
The proposed pipeline would be buried except for aboveground sections of the pipeline and aboveground pipeline appurtenances or ancillary equipment. The pipe and equipment would include the aboveground pipeline sections, each approximately 1,300 feet in length where the pipeline crosses known active faults (at MP 6- Castle Mountain Fault and MP 149.5- the Denali-Farewell Fault), the metering stations at the tie-in point (MP 0) and the terminus (approximately MP 313), the pigging receiver and launcher near Farewell (MP 153.6), the compressor station (MP 5), and the ancillary aboveground piping and associated valves at the 15 remote mainline block valve (MLV) locations (aboveground block valves would be located at 20 mile (32 km) intervals along the line). Appendix E provides engineering typicals for both buried and abovegrade pipeline modes. Burial modes would be trenches or HDD. Minimum depth of cover requirements for the pipeline in accordance with 49 CFR 192 are shown in Table 5-2. Fault crossings would be above grade with the pipe supported on lateral supports as shown in the engineering typicals in Appendix E. The proposed fiber optic cable would be carried on the electric transmission supports to the metering module at the start of the gas pipeline, MP 0, then in buried mode to the compressor station and the remaining pipeline route to the mine, except at the two active fault crossings where the cable would be located abovegrade with the pipeline.
3.8
Length/Width of ROW; Area Needed for Related Activities
Donlin Gold would use a 1,000 ft (305 m) study area on land along the proposed pipeline alignment. The study areas would be located 500 ft (152 m) from each side of the centerline for the proposed pipeline route alignment. Within the state and federal study areas Donlin Gold would apply for and clear a 100 foot wide (30.5 m) temporary construction ROW following its proposed alignment to install the pipeline and fiber optic cable, recognizing that the fiber optic cable may require authorization separately from the pipeline ROW. The 1,000 ft (305 m) study areas would provide Donlin Gold with the flexibility to adjust the pipeline alignment and temporary construction ROW, if necessary, within the study area especially to approximately MP 166 as the area is more challenging for routing. Donlin Gold would establish the temporary construction ROW of 100 ft (30.5 m) that would include a nominal 50 ft temporary (15 m) workspace strip parallel and adjacent to what would be the permanent 50 ft (15 m) ROW. Any area that would be needed within the 1,000 ft (305 m) study area that has not been evaluated for the state or federal historical
Donlin Gold
3-9
July 2012
Plan of Development Donlin Gold Project
Project Description
preservation purposes or other purposes would be reviewed before requesting use or as otherwise directed by the applicable agency. The temporary construction ROW on Cook Inlet Regional Incorporation (CIRI) and Calista lands would be 100 ft (30.5 m) as well. Additional temporary workspace areas outside the 100 ft (30.5 m) temporary construction ROW would be needed at water body crossings and at other locations where additional workspace would be required for safe pipeline construction or materials staging. Additional workspace may be restricted at sensitive environmental or cultural areas. Temporary access roads would be 24 ft (7 m) wide or narrower, where needed, with appropriate temporary use areas. The width of the proposed permanent easement for long-term O&M of the pipeline would be 50 ft (15 m) on state land and approximately 51 ft (16 m) on Bureau of Land Management (BLM) managed land (50 ft plus the width of the pipe). The ROW would be increased to accommodate the compressor station and any other permanent adjunct needs. The actual ROW area needed for the final ROW would be determined in the final as-built survey. Section 4.4, Table 4-1 and Appendices A and B provide additional information related to the disturbance areas. The permanent ROW on CIRI and Calista lands would be 50 ft (30.5 m).
3.9
Ancillary to an Existing Right-of-Way
The proposed pipeline would originate from the BPL and would not cross or parallel any existing pipeline, powerline, or other utility throughout its route to the mine site tie-in. The proposed pipeline would not cross any existing maintained public roads or railroads. Donlin Gold recognizes that there are existing or issued rights-of-way, including RS-2477 routes and Section Line Easements (SLE’s) that may be impacted by the proposed pipeline project. Land status information including location of existing rights-of-way is shown in Appendix A
3.10
Alternative Routes and Locations
3.10.1
Pipeline
The pipeline route, approximately 313 miles (503 km) in length, has been located and evaluated based on currently known technical, environmental, cultural, and economic considerations. Another consideration was minimization of private and native-owned land that would be crossed. The criteria discussed in this section address these considerations. Resources used to define the route and potential alternates included high-resolution orthophotography, LIDAR data (1-meter elevation contours), historical high-level infrared imagery, USGS topographic maps at 1:250,000 and 1:63,000 scale, USGS surficial and bedrock geology maps. Fieldwork included overland snowmachine and numerous aerial reconnaissance trips to further refine the routing and to conduct on-the-ground inspections of terrain and major river crossings. The first aerial reconnaissance flight, which took place during the 2008 pre-feasibility study, obtained continuous videographic imagery of the route from a low altitude. Comprehensive field surveys, geotechnical sampling, and hydrological and environmental studies were conducted in 2010 to assist in fine-tuning the route. During summer 2010, three two-person crews were in the field to validate the desktop routing that had been completed in early 2010. Each crew included a construction superintendent and another person with a survey background. The crews were equipped with a mobile mapping device with an integral GPS that provided sub-meter accuracy (this was not a survey-grade GPS system). The crews were tasked with walking the alignment and verifying that the selected alignment was constructible. If there was an opportunity to move the alignment slightly to better facilitate construction, the crew made and documented
Donlin Gold
3-10
July 2012
Plan of Development Donlin Gold Project
Project Description
the alignment change. Proposed alignment changes were reviewed by pipeline engineering and geotechnical team members on a daily basis during field activities. Accepted changes were documented in the geographical information system (GIS) database and field geotechnical drilling crews were directed to new sampling locations. The crews also ensured that the proposed, cleared ROW would be able to facilitate the movement of pipeline construction supplies, because there would be no permanent access road along the full length of the pipeline alignment. In areas identified as in excess of 12% longitudinal slope, shoofly access road routes were evaluated and documented by the field crews to better facilitate travel along the ROW. Selection of the most technically suitable and constructible route involved the optimization of a number of considerations. The following general criteria were used in this routing process: • • • • • • • •
• •
Minimization of total pipeline length Minimization of the number of water and wetlands crossings that would be needed Avoidance of geotechnical hazards Avoidance of hydrological hazards Avoidance of known areas of environmental and cultural concern, including known wetlands and cultural resource sites Avoidance of areas with potential land use conflicts Optimization of seasonal construction schedules Minimization of construction in areas with steep slopes, permafrost terrain, marshes and bogs, river crossings, and difficult access, and in other areas where construction would be challenging Minimization of visual impacts Route segment alternatives were evaluated at Theodore River, Little Mt. Susitna, Round Mountain, Goodman Pass, Egypt Mountain, St. Johns Hill, Windy Fork, Big River, Tatlawiksuk River, Kuskokwim River, Moose Creek, and in the area of the Kuskokwim Hills.
Although many adjustments were made, the major segment alternatives are discussed below and/or included in Figures 3-2 through 3-13. 3.10.2
Theodore River Alternate Route
The Theodore River alternate route (Figure 3-2) was evaluated and selected as it allowed the pipeline route to be moved to dryer slope areas from the low lying flatter areas to reduce stream crossings and wetland disturbance. 3.10.3
Little Mt. Susitna Alternate Route
The Little Mt. Susitna alternate route (Figure 3-3) was evaluated and selected as it relocated to the pipeline route from lower wetland areas with higher more fish bearing stream crossings to more of an upland route with improved constructability. 3.10.4
Round Mountain Alternate Route
The Round Mountain route (Figure 3-4) traverses the northeast side of Round Mountain along the Happy River valley (Figure 3-3). This route would have connected the selected
Donlin Gold
3-11
July 2012
Plan of Development Donlin Gold Project
Project Description
route between MP 95.25 and MP 99.5, south of Puntilla Lake. This route was not considered because of the presence of unstable, ice-rich soils along steep sideslope terrain, which was identified in the 2010 geotechnical program. 3.10.5
Goodman Pass Alternate Route
The Goodman Pass route (Figure 3-5) represents a crossing of the Alaska Range to the Rainy Pass route (Figure 3-2). This route would begin at approximately MP 113 to the South of Rainy Pass and connect back to the preferred route at approximately MP 133 just north of Rohn. This alternate route was carefully reviewed, and the results of this analysis are documented in detail in a separate report (CH2M Hill 2010). The Goodman Pass alternate route was not considered for several reasons, including the following: The Clean Water Act (CWA) requires that if there is more than one alternative to an action, the alternative that has the least impacts to waters of the United States (U.S.), including wetlands, be selected unless there are compelling reasons such as significant environmental issues associated with the selected alternative. The Goodman Pass route has 22% more impacts to waters of the U.S. than the Rainy Pass route, thus the Rainy Pass route has been identified as the preferred route. • • • • • 3.10.6
Length approximately 6 miles (10 km) greater than the Rainy Pass route Construction issues related to very steep terrain through a constrained, narrow valley Pipeline installation in the bottom of an active stream channel Pipeline installation across geotechnical hazards (thaw-unstable, ice-rich side slopes with slumping soils) Paralleling the South Fork Kuskokwim River through the active, meandering channel floodplain. Egypt Mountain Alternate Route
The Egypt Mountain route (Figure 3-6) was evaluated and selected as it allowed the route to move to a higher area which would be dryer with less permafrost and wetlands. It allows the pipeline route to pass through a small valley through the mountains rather than wetter lowlands drainage areas. 3.10.7
St. John’s Hill Alternate Route
The St. John’s Hill route (Figure 3-7) was evaluated and selected as it allowed the route to be moved upslope closer to the mountains, dryer with less permafrost and wetlands. The route also allowed for smaller creek crossings. 3.10.8
Windy Fork Alternate Route
The Windy Fork route (Figure 3-8) was evaluated and selected as it provided improved approaches to the river crossing and reduced the amount of earthwork required to complete installation of the pipeline and associated access roads. This route also shortened the alignment and generally moved it so that the route requires a smaller cut coming out of the river valley and moved the pipeline alignment upslope into dryer areas with less wetlands and permafrost.
Donlin Gold
3-12
July 2012
Plan of Development Donlin Gold Project
3.10.9
Project Description
Big River Alternate Route
The Big River route (Figure 3-9) was evaluated and selected as it provided an easier exit that requires a smaller cut coming out of the river valley and moved the pipeline alignment upslope into dryer areas with less wetlands, permafrost, and smaller stream crossings. 3.10.10
Tatlawiksuk River Alternate Route
The Tatlawiksuk River route alignment (Figure 3-10) was evaluated and selected as it allowed the pipeline to be routed through an area with more suitable ground conditions. 3.10.11
Kuskokwim River Alternate Route
The Kuskokwim River route (Figure 3-11) was evaluated and selected as it provided better access to upland areas and straightened the pipeline alignment. This alternate route also reduced the number of stream crossings necessary for construction purposes. 3.10.12
Moose Creek Alternate Route
The Moose Creek route (Figure 3-12) was evaluated and selected as it allow for straightening the pipeline alignment and reduced the overall route distance while staying in the upland area. Additionally this alternate route improved access for equipment and would reduce the amount of construction activity. 3.10.13
Kuskokwim Hills Alternate Route
A more southern route was proposed in 2008 between the Kuskokwim River and the mine terminus (Figure 3-13). During the 2010 summer field season, it was proposed to use a more northern route through this area. The northern route reduced the length of the proposed pipeline by approximately 5 miles (8 km) and avoids potential land use conflicts on private lands. There are areas along the southern route where it was considered more difficult to construct the pipeline than along the more northern route, because of low lying areas and additional wetland impacts. 3.10.14
Alternative Route Assessments for the Electric Transmission Line
Three potential routes were reviewed for the aerial power transmission line from the Beluga Power Plant to the pipeline compressor station. The first alternate route is a nearly direct line between the Beluga Power Plant and the compressor station. The second would ensure that the power transmission line did not go into the Susitna Flats State Game Refuge. The third essentially parallels the existing Chugach Electric Association (CEA) high-voltage transmission lines until it reaches the point near the proposed Donlin Gold pipeline tie-in to the BPL at MP 0 and then follows the pipeline ROW to the proposed gas compressor station. The third option was selected because there is a need for power and communications at the BPL tie-in. This route also would reduce the amount of clearing required inside the Game Refuge by following existing utility corridors and would allow the fiber optic cable to be buried in the ROW with the Donlin Gold gas pipeline to the compressor station and on to the mine site.
Donlin Gold
3-13
July 2012
26
27
28
29
30
T21N R12W
MP-48 T21N R11W MP-47 32
9
8
7
MP-45
30
31
6
29
32
5
MP-45
33
4
27
34
3
26
35
2
18
24
25
36
19
30
31
8
17
20
9
16
10
15
T19N R12W 21
22
11
14
23
30
29
35
36
31
32
34
33
25
21
20
36
1
30
31
12
13
24
7
18
19
26
25
33
T21N R9W
35
36
34
1
1
2
2
3
3
4
4
5
5
6
6
11
12
11
10
10
10
9
9
8
8
7
12
7
12
11
14
13
14
15
14
15
16
16
17
17
18
18
13
13
23
24
23
22
22
21
21
20
20
19
19
24
24
26
25
26
27
27
28
28
29
29
30
30
25
25
MP-40
31
36
36
35
35
34
34
33
33
32
32
6
1
1
2
2
3
3
4
4
5
5
7
8
9
12
12
11
11
10
10
18
17
16
15
14
13
13
19
20
21
22
23
24
24
30
29
28
27
26
31
32
33
34
35
3
2
MP-44
22
MP-43
27
28
29
32
MP-42
MP-41
34
33
26
35
MP-41 MP-40 36
5
3
4
2
8
17
20
31
MP-39
1
MP-38
6
MP-38 9
7
9
10
11
12
16
15
14
13
18
17
23
24
19
20
8
MP-36
22
MP-37 16
T19N R10W
T19N R11W 21
MP-36 14 MP-35 15 MP-35 23 MP-34 21 MP-34 22 MP-33 26
MP-33
28
28
29
29
30
30
25
25
28
26
26
29
27
27
27
32
33
34
35
36
31
32
32
36
31
34
34
35
33
33
MP-31
5
4
3
2
6
SCALE:
Mileposts
0
0.875 1.75
0
1.25 2.5
3.5 mi
Proposed Natural Gas Pipeline Alignment Theodore River Alternate Route
T20N R9W
T20N R10W
23
MP-39 6
27
28
1
MP-37 7
25
2
MP-42
28
26
3
15
T20N R11W MP-43
19
24
23
22
21
20
36
35
4
16
17
18
T20N R12W 19
31
32
27
28
MP-46
13
14
15
16
17
29
33
MP-44 18
30
T21N R10W
34
MP-47 5 MP-46
6
12
11
25
26
27
28
MP-48
1
2
10
9
8
7
36
35
3
4
5
6
MP-49
31
34
33
32
29
MP-50
25
5 km
MP-32
35
25
MP-32 36
T19N R9W
1
6
5
THEODORE RIVER ALTERNATE ROUTE
4
25
FIGURE:
3-2
DONLIN GOLD PROJECT
Seward Meridian, UTM Zone 5, NAD83 DG: Theodore River.mxd, 07/23/12, R01
20
21
29 28 32
29 32 5 8 18 17 19 20 30 29 31 32 6 7 18 19 30 36 31 1 6 12 7 13 18
10
9 16
15
11 14
22
27
28
34
33
3
4
10
9
15
16
12 13 24
23
25
26
36
35
1
2
12
11
13
14
T17N R12W 22
21
27
28
34
33 4
5
9
8 17
16
21
28
29
33
32
4
5
36
35
10
11
15
22
27 34 3
16
18 19 30 31 6 7 18 19 30
14
23 26 35 2
10
11
15
14
12 13 24 25 36 1 12 13
34
33
32
10
9
17
15
16
T18N R11W
20 29 32
17
15
16
19 30 31 6 7 18
9
8
16
21
28
29
33
32
4
5 8
13
15
22
27 34
14 23 26 35 2
11 14
32
17
12 13 24 25 36 1 12
8
7 18 19 30 31 6 7
17 20 29 32
16
15
T16N R10W
18
15
5
7
8
9
10
18
17
34
MP-23
MP-22
19
21
30
29
28
9
28
27
25
30
29
28
33
34
35
36
31
32
4
3
2
1
6
5 8
22
23
24
19
26
25
30
29
28
27
26
25
36
31
32
33
34
35
1
6
5
4
3
12
7
8
9
18
17
19
2
17
13
24
MP-20
T19N R7W
15 22
4 9
16 21
12
7
8
9
10
14
13
18
T18N R6W
17
16
15
23
24
19
20
21
22
27
26
25
30
29
28
27
9
10
11
15 22
16
17
21
20
T18N R7W
33
34
35
36
31
32
34
32
33
31
4
3
2
1
3
5
4
6
5
1
6
2
9
10
11
10
8
9
7
8
12
7
11
12
10
17
16
15
16 15
18
17
13
18
14
13
15
14
16
20
21
22
24
19
20
21
22
23
23
28
27
26
25
30
29
28
27
29
33
34
35
36
31
32
33
34
32
T17N R8W
T17N R7W
T17N R6W
24
19
20
21 22
26
25
30
29
28 27
35
36
31
32
33 34
5
4
3
2
1
4
6
5
1
6
2
8
9
9
7
8
12
7
11
12
10
11
9
10
8
17
16
18
17
13
16
18
14
13
16
15
14
17
15
18
T16N R6W
20
23
20
21
23
19
19
22
24
24
21
22
20
21
19
29
28
28
30
29
25
30
26
25
28
27
26
29
27
30
32
33
31
32
36
31
35
36
34
35
33
34
32
33
31
5
4
6
5
1
6
2
1
4
3
2
5
3
6
4
1
10
11
7
8
9
8
12
7
8
9
7
18
17
16
19
20
21
MP-16
13 14 MP-15
MP-14 24
MP-10
3
1
3
11
2
4
2
4
MP-17
MP-11
5
3
36
6 7
25
T16N R8W
35
3
6
4
5
2
MP-12
33
34
7
34
32
33
5
T19N R6W
30 31
36
28
MP-18 31
27 26 MP-13 34
25
35
29
30
1
10
26
30
25
MP-19
T18N R8W
36
33
MP-9
6 km
21
12
T15N R9W MP-9
0 1.5 3
20
35
MP-12
MP-11
Proposed Natural Gas Pipeline Alignment
19
23
MP-13
4 mi
24
MP-16
T16N R9W
2
23
3
4
26
1
18
35
22
0
13
MP-17
16
18 19
14
34
MP-15
13
16
26
17
14
17
MP-18
11
15
18
15
14
13
27
21
16
12
MP-21
8
7
11
23
7
12
10
14
12
11
9
MP-22
2
10
8
11
5
T15N R10W
7
22
20
21
1
MP-19
33
32
18
2
15
16
20
13
3
MP-23
6
14
6
4
MP-24
T17N R9W
31
32
5
MP-25 3
6
29
31
35
22
4
MP-24
30
36
34
MP-26 27
32
31
25
26
33
35
T18N R9W
28
SCALE:
Little Mount Susitna Alternate Route
12
19
17
Mileposts
10
11
24
9
13
6
23
5 8
10
9
1
1
3
4
5
6
3
2
33
36
35
34
33
32
31
29
MP-25
25
32
MP-27 21
30
24
26
9
MP-28 16 20
19
13
23
17
31
T19N R8W
8
8
MP-26
12
14
27
18
1
11
22
28
29
36
2
T17N R10W 21
25
35
15
16
24
26
10
9
7 13
4
5
6
MP-29
12
23
3
4
1
T19N R9W
32
31
MP-31
MP-30 MP-30
14
34
33
36
11
27
28
20
30
22
21
8
19
2
15
16
5
18
1
11
29
7
35
36
27
28
29
30
25
26
27 34
28 33
29
30
MP-32
MP-31
T18N R10W
20
6
36
3
15
31
25
10
16
30
24
T15N R11W 9
17
10
19
17
34
10
9
MP-33 25
26
27
3
4
8
18
12
33
5
7
1
2
T16N R11W
20
36
35 3
4
25
26
34
5
24
23
27
33
17
14
22
28
32
18
11
T17N R11W 21
13
2
10
9
29
7
35
3
4
20
6
26
34
33
8
23
27
28
12
14
22
21
5
11
32
6
1
2
T19N R10W
31
36
35
28
29
30
25
26
3
4
31 1
2
3
T15N R12W 9
17
25
26
T16N R12W
20
8
24
23
T19N R11W
8
7
27
28
5
6
1
T18N R12W
21
31
36
2
3
4
35
20 29
r
20
34
19 30
ve Ri
17
T19N R12W
33
24 25
tna
8
23 26
n Ye
5
22 27
36
9
10
T15N R8W
T16N R7W
T15N R7W
12
10
11
12
14
13
13
15
14
17
16
15
18
16
13
17
14
18
15 22
23
24
19
20
21
22
23
24
19
20
21
22
23
24
11
LITTLE MOUNT SUSITNA ALTERNATE ROUTE
T15N R6W
FIGURE:
3-3
DONLIN GOLD PROJECT
Seward Meridian, UTM Zone 5, NAD83 DG: Little Mount Susitna.mxd, 07/23/12, R01
8
9
10
17
16
15
11
MP-99
12
MP-100
MP-98
14
7
8
9
10
18
17
16
15
20
21
22
28
27
33
34
13
MP-99
p Hap
21
24
23
22
T23N R19W
r ive
20
yR
MP-97
MP-96
MP-98
MP-97 29
28
27
19
MP-96 30
25
26
T23N R18W
MP-95
29
MP-95 MP-94 32
33
5
4
34
36
35
31
32
MP-94 3
2 SCALE:
1
6
0.25 0.5
1 mi
ROUND MOUNTAIN ALTERNATE ROUTE
0 0.375 0.75
1.5 km
DONLIN GOLD PROJECT
Mileposts Proposed Natural Gas Pipeline Alignment Round Mountain Alternate Route Seward Meridian, UTM Zone 5, NAD83
5
0
4
3
FIGURE:
3-4 DG: Round_Mountain.mxd, 07/23/12, R03
8 P-- 11338 MP M 37 -1 MP
366 -- 113 MPP M
23
24
19
20
21
22
23
24
25
30
29
28
27
26
25
MP-28 MP-27
33
34
35
MP-27
36
31 4
3
2
6
1
5
4
3
2
1
17
16
15
14
13
18
17
16
15
14
13
24
19
20
21
22
23
24
19
20
21
22
23
24
19
20
21
22
23
24
25
30
29
28
27
26
25
30
29
28
27
26
25
30
29
28
27
26
25
35
36
31
33
34
35
36
31
32
33
34
35
36
31
32
33
34
35
36
3
2
1
6
4
3
2
1
6
5
4
3
2
1
6
5
4
3
2
1
10
11
12
7
8 22559 P-- 11 MP M
10
11
12
7
8
9
10
11
12
7
8
9
10
11
12
15
14
13
18
1244 P-- 12 MP M T25N R21W 17
16
14
13
18
17
16
15
14
13
18
17
16
15
14
13
22
23
24
19
20
21
22
20
21
22
23
24
19
20
21
22
23
24
30
29
28
27
26
25
30
29
28
27
26
25
31
32
33
34
35
36
31
32
33
34
35
36
22
21
27
28
29
MP-26
34
33
32
MP-26 MP-25
6
23
T26N R22W
4
5
26
2732 -1 MP
MP-25
11
16
15
14
13
18
17
16
15
14
22
23
24
19
20
21
22
23
T25N R24W
21
27
6
5
35
4
30
36
29
31
3
2
28
32
1
27
33
6
5
19 MP-22 20 MP-22 MP-21 25 MP-21 30 29
24
26
34
36
MP-20
35
4
3
9
10
11
12
7
8
9
10
18 17
16
15
14
13
18
17
16
T24N R23W
15
20
22
19 20
30 29
31 32
6
7
5
8
21
28
33
4
9
22
27
34
3
10
23
26
35
2
11
T23N R24W
24
25
36
1
12
19
30
31
6
7
29
32
5
8
21
28
33
4
9
2
MP-19 MP-18
27
34
3
10
31
T23N R23W
11
14
32
1
MP-17
13
23
25
35
36
11
1
12
27
26
25
30
29
28
27
26
34
35
36
31
32
33
34
35
919 11 PM 24
25
36
33 5
6
4
8
7 MP-17
17
2
10
11
16
15
14
1
6
5
4
3
12
7
8
9
10
13
18
17
16
15
MP-15 20
MP-15 30
3
T24N R22W
9
MP-16
18
19 24 MP-16
26
2
28
MP-18 12
23
T25N R22W
21
15
24
19
20
21
2
28
32
5
8
25 26 30 MP-13 MP-12 34 35 MP-11 31 33 36 MP-10
4
2
3
10
9
T23N R22W
11
MP-9 1
6
29
28
32 33
8
5
18
24 23
MP-3 26
MP-2 25
19
11
9
10
T24N R20W
1
6
5
4
3
2
12
7
8
9
10
11
17
16
15
14
20
P- 21 M
22
23
13
18
21
22
23
24
19
29
28
27
26
25
30
29
17
5 T24N R19W 10
20
3
2
1
6
5
9
10
11
12
7
8
T23N R21W
2
14
MP-0
30
3
15
8
MP-1
4
T25N R19W
16
7
36
34
4
7
12
27
13
14
MP-6 MP-5 35
MP-7 5
6
1
M MPP - 11112 11 - 1 66
22
27 29
6
7
23
MP M P-- 11 1177
MP-14
MP-14
31
22
21
T24N R21W
88 -- 1111 MPP M
T25N R20W
T26N R19W
P-- 110088 MP M
8
T24N R24W
17
T26N R20W
1122 P-- 11 MP M
7
34
25
16
18
MP-23
13
im R iver
33
26
7
u s ko k w
28
T25N R23W
MP-24 8 9 MP-24 MP-23
12
M MPP -- 11 2233 M MPP -- 11 2222 M MPP -- 11 2211
10
MP -9
9
MP -11 MP -10
8
MP -12
7
MP -13
12
5 2 266 P-- 11 MP M
20 -1 MP
11
SF
10
o rk K
9
T26N R21W
MP -1 15 M MPP -- 11 1144 M MP P-- 111 133
32
18
5 PM
31
13
-6 MP
36
14
-7 MP
35
30
15
-8 MP
34
T26N R23W
16
MP -1 33 MP -1 32 M MPP -- 11 3311 M MPP- 13 1300
33
26
17
M P4
27
18
14
2299 P-- 11 MP M
T26N R24W
28
13
15
04 - 1 27 M28P 3 10 P33 M 34
26
35
31
32
33
34
35
36
31
32
4
3
2
1
6
5
4
3
9
10
11
12
7
8
9
10
11
T23N R20W
T23N R19W
01 -1 P M 2
17
16
15
14
13
18
17
16
15
14
13
18
17
16
15
14
13
18
17
16
15
14
13
18
17
16
15
14
13
18
17
16
15
14
20
21 28
22
23
24
19
20
21
22
23
24
19
20
21
22
23
24
19
20
21
22
23
24
19
20
21
22
23
24
19
20
21
22
23
29
SCALE: Populated Places Proposed Natural Gas Pipeline Alignment
0
1
2
4
6 mi
Goodman Pass Alternate Route #1
0
Goodman Pass Alternate Route #2 Seward Meridian, UTM Zone 5, NAD83
2
4
8 km
GOODMAN PASS ALTERNATE ROUTES
FIGURE:
3-5
DONLIN GOLD PROJECT DG: Goodman_Pass.mxd, 07/23/12, R04
1 PM MPMP-
M MMP P P--- 9 MPP M
97 MPMP- 97
22
16
M P10 2
21
3355 -- 11 17 MPP18 M 4 13 P M 19 20
M MPP -- 11 0066
13
M MPP -- 110 077
14
M MP P-- 110099
15
M MP P-- 11 1100
16
MP-- 11 MP 1111
17
M MP P-- 112 288
18
MP -3
13
MP -2
14
MP -1
15
MP -0
16
20
29
21
28
MP-151 MP-150
MP-151 MP-152
MP-150 MP-149 27
T28N R24W
34
24
19
MP-147
MP-148 26
21
22
23
24
29
28
27
26
25
35
36
2
1
11
12
14
13
MP-146
25
30
MP-149
35
20
T28N R23W MP-148
MP-145
31
36
32
33
34
R wi m uskok
33
23
S Fork K
32
22
MP-144 MP-147
ive
4
3
r
5
2
1
6
MP-146
8
9
10
11
12
7
T27N R24W
5
4
MP-143
3
MP-145 MP-144
8
MP-142 9
T27N R23W
MP-143
10
MP-141 MP-142
17
16
15
14
13
18
17
16
15 MP-140
MP-141 20
21
22
23
24
19
1 mi
Proposed Natural Gas Pipeline Alignment Egypt Mountain Alternate Route Seward Meridian, UTM Zone 5, NAD83
0
0.5
1
21
22
EGYPT MOUNTAIN ALTERNATE ROUTE
SCALE:
Mileposts 0 0.25 0.5
20
2 km
23
24
FIGURE:
3-6
DONLIN GOLD PROJECT DG: Egypt_Mountain.mxd, 07/23/12, R04
30
29
28
31
32
33
27
26
25
30
35
36
31
29
T28N R26W 34
28
27
33
34
T28N R25W 32
MP-155 MP-156
MP-156
MP-157 6
5
4
3
2
MP-158 6
1
MP-157 5
MP-159
8
9
12
MP-160
7
8
10
T27N R25W
MP-161
MP-163 17
9
MP-159
11
MP-162
T27N R26W 18
MP-161
10
3
MP-158
MP-160
7
4
MP-162 16
MP-163
15
14
13
18
17
16
15
23
24
19
20
21
22
MP-164 MP-165
19
30
20
29
21
22
28
27
26
ST. JOHNS HILL ALTERNATE ROUTE
SCALE:
Mileposts Proposed Natural Gas Pipeline Alignment St. Johns Hill Alternate Route Seward Meridian, UTM Zone 5, NAD83
0 0.25 0.5 0
0.5
1 mi 1
2 km
FIGURE:
3-7
DONLIN GOLD PROJECT DG: St_Johns_Hill.mxd, 07/23/12, R04
14
13
18
17
MP-164
MP-165
MP-165
T27N R27W
T27N R26W
MP-166 23
24 MP-167
MP-166 19
20
30
29
MP-168
26
25
SCALE:
Mileposts Proposed Natural Gas Pipeline Alignment Windy Fork Alternate Route Seward Meridian, UTM Zone 5, NAD83
0 0
0.125 0.25 0.2
0.4
0.5 mi 0.8 km
WINDY FORK ALTERNATE ROUTE
FIGURE:
3-8
DONLIN GOLD PROJECT DG: Windy Fork.mxd, 07/23/12, R01
32
33
25
35
34 T26N R31W
30
34
36
31
32
T26N R30W
33
35
36
31
29
T26N R29W 32
g Bi
3
2
1
6
5
4
3
r ve
4
Ri
5
2
1
6 MP-185
8
17
9
10
16
11
15
14
T25N R31W 20
MP-197 29
32
1
21
MP-196
22 MP-195 MP-197
28
33
6
13 MP-193 MP-195
MP-194
23 MP-196
27
34
12
26
35
5
4
7
8
18 MP-191 MP-192 17 MP-194 MP-193
24
25
36
3
19
30
7
8
9
10
16
2
MP-186
33
34
6
5
13
12
7
8
SCALE:
Mileposts Proposed Natural Gas Pipeline Alignment Big River Alternate Route
0 0
Seward Meridian, UTM Zone 5, NAD83
0.5
1
0.75 1.5
2 mi 3 km
34
35
MP-185
5 MP-186
4
3
2
7
8
9
10
11
18
17
16
15
14
T25N R29W 23
26
35
4
24
19
20
21
22
23
25
30
29
28
27
26
36
31
32
33
34
35
3
2
1
6
12
7
T24N R30W
11
MP-184
MP-187
MP-188
14
22
27
26
MP-189
15 MP-190
MP-191
28
1
MP-187
MP-188
21
32
11
12
33 MP-183
27
MP-182
MP-184
T25N R30W
MP-192
29
31
10
MP-189
MP-190
20
T24N R31W 12
9
28
9
10
11
BIG RIVER ALTERNATE ROUTE
5
4
8
9
T24N R29W
FIGURE:
3-9
DONLIN GOLD PROJECT DG: Big_River.mxd, 07/23/12, R04
21
22
la Tat
29
MP-214
28
MP-216
T24N R34W
MP-215
wiks u k
MP-213
27
26
MP-214
0
MP-212
MP-213
32
23
Riv er
20
33
34
35
36
TATLAWIKSUK RIVER ALTERNATE ROUTE
SCALE:
Mileposts Proposed Natural Gas Pipeline Alignment Tatlawiksuk River Alternate Route Seward Meridian, UTM Zone 5, NAD83
0 0
0.125 0.25 0.25
0.5
0.5 mi 1 km
FIGURE:
3-10
DONLIN GOLD PROJECT DG: Tatlawiksuk_River.mxd, 07/23/12, R04
2
1
6
5
4
MP-240 11
MP-241
12 7
MP-239
MP-238
MP-239 8 9
T23N R39W
T23N R38W MP-242
MP-240
MP-241
MP-243
14 13
18
17
KUSKOKWIM RIVER ALTERNATE ROUTE
SCALE:
Mileposts Proposed Natural Gas Pipeline Alignment Kuskokwim River Alternate Route Seward Meridian, UTM Zone 5, NAD83
0 0.125 0.25 0
0.25
0.5
16
0.5 mi 1 km
FIGURE:
3-11
DONLIN GOLD PROJECT DG: Kuskokwim_River.mxd, 07/23/12, R04
15
14
13
18
17
16
15
14
13
18
22 23
24
19
20
21
22
23
MP-263 27
T23N R42W
MP-264
26
MP-264 MP-265
T23N R41W
25 30
MP-263
29
MP-262 MP-262 MP-261
MP-259 MP-260 28
MP-259 MP-258 27
36
2
T22N R42W
11
31
1
5
9
1 mi
Proposed Natural Gas Pipeline Alignment Moose Creek Alternate Route
0 Seward Meridian, UTM Zone 5, NAD83
25
30
MP-256
0.5
1
35
36
2 km
31
3 2
10
11
1
6
12
MOOSE CREEK ALTERNATE ROUTE
SCALE:
0.25 0.5
34
T22N R41W
4
8
0
MP-255
26
MP-257
33
7
Mileposts
MP-258
MP-261
32
6
12
19
MP-256
MP-257
MP-260 35
24
FIGURE:
3-12
DONLIN GOLD PROJECT DG: Moose_Creek.mxd, 07/23/12, R04
13
14
T22N R47W
22
23
27
34
3
10 15
24
26
35
2
18
8
9
19
25
36
31
1
14
12 13
20
30
6
T21N R47W 11
17 MP-302
7
29
32
5
8
15 MP-299
33
4
34
3
T21N R46W 9
10
18
23
M MP P-- 22885 5
M MP P-- 22886 6
23
24
19
2
11
28
29 32
31
27
33
5
26
34
4
25
35
3
2
19
28
32
6
12
21
29
31
1
20
33 4
23
27
26
34
35
8
9
0
1
0
1.5
2
10
Seward Meridian, UTM Zone 5, NAD83
3
24
25
36
k or F E.
11
12
7
6 km
14
21
22
28
G
23
34
33
17
16
15
20
21
29
28
32
33
5 8
4
22
27
34
T21N R44W 9
5
4
12
7
8
9
13
18
17
16
19
35
36
25
23
26
35
21 22
6
5
4
7
8
9
10
18
17
16
15
20
21
22
30
29
28
27
31
32
33
34
24
19
36
20
15
28 27 6 29 27 MP-279 P M 32 31 MP-280 33 34
13
25
T23N R43W
30
12
14
T22N R44W
33
6
24
11
32
T24N R43W
31
2 MP-283 MP-282 3 MP-284 1
4
28
1
26
27
9 MP-285 MP-286 10
8
30
6
11
15
5
19
31
10
T23N R44W
20
32
18
1
4 mi
Proposed Natural Gas Pipeline Alignment Kuskokwim Hills Alternate Route
13
2
16
29
7
2
SCALE: Mileposts
12
3
9
17
3
T21N R45W
5
7
22
31
6 1 MP-289 MP-290
T22N R45W
8
30
36
MP-295 MP-294 11 8 10 MP-291 9 MP-293 MP-292 18 17 16 15 14
30
36
25
4
29
M MP P-- 227777
g or
6
24
26
35
Ge
13
14
22
27
22
12 MP-296 7
MP-298
21
21
36
M MPP -- 22 8800
20
18
35
MP -
30
1
11
T22N R46W
28
36
2
10
16 MP-300
T23N R45W
13
34
Riv - 281 er
25
35
3
MP-303 15
26
34
4
14
7
33
30
3
T22N R43W
5
2
1
6
10 3
KUSKOKWIM HILLS ALTERNATE ROUTE
T21N R43W 4
M M
M MPP -- 227 733
5
15
12
5
M MP P-- 22 8822
27
33
16
11
6
25
T24N R44W
rg e
32
7
17
19
10
1
26
M MPP -- 22 7755
12
18
24
9
2
32
27
44 P-- 2277 MP M
11
13
23
8
3
31
28
788 P-- 227 MP M
31
28
7
4
29
eo
29
22
12
5
34
30
799 -- 227 MPP M
0000 -- 33 MPP M
01 -3 MP
10
14
6
25 36
MP -2 83
30
MP-305 1 6 MP-304
2
15
21
4 3
11
T23N R46W
20
1
M MP P-- 22 8877
10
16
33
2
26 35
MP -2 84
25
MP-307 36 35 MP-306
33 34
17
19
P-- 229988 MP M 9 29 PM
26 27 MP-308
9
T24N R45W
32
2888 P-- 28 MP M
24
3
31
36
2899 MP-- 28 MP
23
18
9977 P-- 22 MP M
22
13
8
55 -- 2299 MPP M
21
7
4
P-- 229922 MP M
14
T23N R47W
5
P-- 229944 MP M
15
T24N R46W 35
6
12
34
P-- 229933 MP M
16
11
33
r
10
1
32
iv e
2
31
M MP P-- 2299 00
9
36
eR
35
M MP P-- 2299 11
34 3
MP-- 296 MP 296
33 4
3
FIGURE:
3-13
DONLIN GOLD PROJECT DG: Kuskokwim_Hills.mxd, 07/23/12, R04
M M
Plan of Development Donlin Gold Project
3.11
Project Description
Safeguards for Persons, Property, and Public and the Environment
Donlin Gold LLC is committed to conducting business in a manner that is compatible with the environment and the needs of the general public in the area in which the proposed pipeline would be constructed and operated. Dolin Gold intends to protect the safety, security, and health of its employees, those involved with the construction, operation, maintenance and termination of the proposed pipeline, and the public. Donlin Gold’s primary objective is to ensure the proposed pipeline’s integrity, address leak prevention, establish procedures and plans for surveillance, inspection and monitoring, and to plan for response in the case of any emergency relating to the pipeline or workers during construction, operation, maintenance, and termination. The project is subject to strict state and federal laws that provide safeguards for persons, property, the public and the environment. Project specific permits and authorizations are required under state and federal laws for construction, operation, maintenance, and termination. Critical permits and authorizations required for this project are the State Pipeline Right-of-Way Lease under Alaska Statutes (AS) 38.35; Bureau of Land Management Grant of Right-of-way; CWA Section 404 permit from the U.S. Army Corps of Engineers (COE); and, CWA Section 401 permit from the Alaska Department of Environmental Conservation (ADEC). Other permits and authorizations support the issuances of the right-of-way lease and grant. 3.11.1
Safety of Workers
Donlin Gold would implement or have implemented a worker safety plan program (Health, Safety and Environment Plan) for the proposed pipeline project construction, operation, maintenance and termination that also would address the safety of workers. Safety considerations during construction are discussed in Section 8.4 and safety consideration during operations and maintenance in Section 11.3 of this document. Before being dispatched to the field, all personnel would receive health, safety, and environment (HSE) training. The training program would focus on applicable state or federal regulations as well as project-specific permit conditions and mitigation plans. The training would include environmental and cultural sensitivity issues. A project orientation would be conducted that would focus on personnel safety and health, camp rules, prohibited items (for example, pets, drugs, alcohol, and firearms), mobilization, wildlife interaction, waste management, medical and emergency response, fire prevention, suppression and related topics. Safety training would be a major component of the orientation. Donlin Gold would develop other plans that would include the safety of workers such as a Fire Prevention and Suppression Plan, and Wildlife Avoidance and Human Encounter/Interaction Plan (see Section 3.11.10 for list of some plans). A compliance monitoring program would be used during all project phases. Components of the program would include: • • •
Donlin Gold
Ensure that onsite personnel understand regulatory requirements Establish a compliance matrix that describes routine permit related inspections and other activities Ensure that the Permits and Environmental Compliance Monitoring Program is being properly implemented.
3-26
July 2012
Plan of Development Donlin Gold Project
Project Description
An Emergency Response Plan would be developed to outline potential hazards and corrective actions. Specific emergencies that would be addressed would include but not limited by: • • • • • • • 3.11.2
Serious illness or injury Fatality Fire or explosion Pipeline rupture or emergency Earthquake Wildfires fires Bomb threat, terrorism or other criminal act. Public Health and Safety
Design, administrative, and operational controls would be developed and implemented to prevent and abate hazards and to protect the health and safety of all persons affected by the activities performed in connection with the construction, operation, maintenance and termination of the pipeline. A threat or hazard to public health and safety would be associated with release of natural gas only during operation of the pipeline. There are no other significant events that can be identified to pose serious hazards to public health and safety during the construction phase provided that the public also exercises reasonable caution and obey hazard warnings or directions when nearing or traversing construction areas or temporary use areas even if construction personnel may be award of or assisting in their presence. Construction and Operations Practices Established, safe construction practices, together with health and safety programs, would be used to guard the health and safety of the workforce and the public during construction and operation of the pipeline. Donlin Gold would observe and comply with applicable federal, state, and local laws and regulations related to public health and safety, including federal PHMSA regulations pursuant to 49 CFR 192. These federal regulations provide stringent standards for pipe materials, pipe design, pipe components, pipe welds, pipeline construction, corrosion protection, pipeline pressure testing, and operation and maintenance. Access Limited potential exists for general public access to the pipeline ROW because of the remoteness of the area and the seasonal means of transportation to get to ROW. Donlin Gold recognizes that that portion of the pipeline project in the Matanuska Susitna (MatSu) Borough receives regular winter use from Anchorage, MatSu Borough and local area residents and that this use would be temporarily interrupted by the project. Through its Public Outreach Plan Donlin Gold would provide notice of pipeline construction activities and information on how the public could coordinate access needs with construction activities. In these and other areas where construction activities would impact existing access routes Donlin Gold would provide alternate access or allow for controlled access within or across the construction area. This would include ADL 222930/RST-199, the main transportation route in the region. There would no doubt be people that would want to use the right-of-way during pipeline operation but efforts would be made to discourage such use if that use may put the integrity Donlin Gold
3-27
July 2012
Plan of Development Donlin Gold Project
Project Description
of the pipeline system at risk. During construction access to the ROW would be controlled. Communities in the general area would be consulted about construction and maintenance activities to aid in the identification of means to avoid potential conflicts with subsistence users and local travelers. Appropriate notices, warning signs, flagging, barricades, and other safety measures would be used to facilitate pipeline construction, operation, maintenance and termination activities, or to protect the public and wildlife from hazards associated with pipeline construction, operation, maintenance, and termination activities. Any existing roads, trails (including RS-2477s) or other public improvements encountered during construction, operation, maintenance and termination would be protected and if damaged restored to the extent possible including provisions for suitable permanent crossings where the ROW crosses existing trails. Refer to Section 11.9.5 for information regarding heavy equipment pipeline crossing. Donlin Gold would prohibit its employees and contractors from operating project related equipment off the pipeline ROW or off any of the other authorized temporary use areas. Spills and Leaks Risks relating to spills during construction or gas pipeline leaks during pipeline operation would be reduced by implementing appropriate procedures and prevention programs during construction and proper leak detection procedures and an effective inspection, monitoring and response program during operation. The primary types of releases may include a leak or a pipeline rupture as discussed in the following. Pipeline Leaks Pipeline leaks would include a relatively small leak of natural gas that may or may not be detected by monitoring pipeline pressure drops. The source of leaks may include areas where the pipe is spliced, at emergency blowdown locations, or at the metering building or compressor station. The primary threat would be that if an ignition source was introduced in the vapor plume resulting in an explosion or fire. A gas leak might be detected during routine maintenance inspections required by USDOT (49 CFR 192 requires a minimum of twice yearly patrols and yearly leakage surveys for the pipeline), by detection of the sound of leaking gas or with hand held gas meters. The natural gas would not contain odorants and would likely not be detected by smell. Once detected the source of the leak would be identified and repairs would be implemented. Pipeline Ruptures Pipeline ruptures may occur as a result of physical damage to the line as a result of excavations in the vicinity of the line, as a result of a leak that ignites and explodes, or possibly as a result of an earthquake or other natural or human caused event. Pipeline ruptures would be detected by pipeline monitoring equipment and the location of the rupture can be determined by direct visual observations. With a rupture the line would be immediately shut down and appropriate actions would be taken to determine the cause of the incident. Repairs of the line would be conducted as permitted by regulatory agencies. Inspections and Maintenance Measures to protect public health and safety during pipeline operation include an ongoing inspection and maintenance program as part of regulatory compliance and the Pipeline Surveillance and Monitoring Plan as well as the Operation and Maintenance Plan. Donlin Gold
3-28
July 2012
Plan of Development Donlin Gold Project
Project Description
Pipeline The pipeline would be buried except where the pipeline would cross two active faults each for a distance of approximately 1,300 ft (396 m). There would also be control valves located at 20 mile (32 km) intervals along the pipeline, and a pigging station, metering station and compressor station. Thus, there would be very limited exposure to the pipeline itself along the ROW. Signage Signs would be placed at appropriate locations along the pipeline and at locations required by 49 CFR 192 warning the public of associated hazards and providing the operator’s name and 24-hour–a-day contact information. Because the pipeline would cross state, federal, CIRI and Calista lands as well as being located in part within borough boundaries additional signage may be required besides that of the pipeline regulatory agencies. Donlin Gold would coordinate the development of a Signage Plan with the appropriate entities to address concerns if signage became an issue. (See Section 8.6) Public Outreach/Public Awareness Donlin Gold would established a Public Outreach Plan with the communities in the general area through which public safety concerns, access to the area for subsistence use, emergency assistance, and other safety-related issues would be addressed. The public would be able to obtain information and be aware of ongoing activities prior to traveling in construction areas as well as what procedures to follow for contacting Donlin regarding access across or along the construction area. 3.11.3
Public or Private Property
A small number of private parcels exist adjacent to the proposed pipeline ROW. Efforts were made to route the pipeline so as not to cross privately owned parcels. Within the proposed ROW there are lands owned by Calista and CIRI. Arrangements would be necessary to traverse these lands with the pipeline. All remaining lands are public lands managed by the state or federal government. Cook Inlet Energy, LLC holds Oil and Gas Lease ADL 390749 between approximately MP 2.5 and MP 5 and Union Oil Co. of California holds Oil and Gas Lease ADL 63048 at the beginning of the pipeline around MP 0. From MP 0 part way to MP 5 the pipeline is within the Susitna Flats State Game Refuge. Any existing roads, trails (including RS-2477s) or other public improvements encountered during construction, operation and maintenance would be protected and if damaged restored to the extent possible. Major events that potentially could cause serious and irreparable harm or damages to public or private property would be a result of a pipeline rupture and explosion or a major fuel spill. An explosion, fuel spill or construction or maintenance incident could result in harm or damage including a fire effecting nearby public or private property and/or loss of life. A pipeline rupture was discussed in Section 3.11.2 above. An Emergency Response Plan would be developed to address such potential hazards and corrective/response actions.
Donlin Gold
3-29
July 2012
Plan of Development Donlin Gold Project
Project Description
During Construction During construction, impacts would be avoided, minimized, and/or mitigated by various methods, including the following: • • • •
Compliance with applicable regulations and permits issued for the project Schedule winter construction to minimize damage to landcover, wetlands and waterbodies Construction would be monitored by trained personnel to minimize disturbance to construction areas Appropriate approved plans would be in place to address construction activities.
During Operation and Maintenance During operation and maintenance, impacts would be avoided, minimized, and/or mitigated by various methods, including the following: •
Compliance with applicable regulations and permits
•
The pipeline would be monitored regularly during operations
•
Planned or unplanned pipeline repairs or maintenance would be completed in a manner that would minimize impacts to public or private property
•
After construction a comprehensive pipeline surveillance, inspection and monitoring program as well as a maintenance program would be implemented. The goals of these programs would not only be to ensure pipeline operating integrity and safety, but to also prevent, identify, and respond to all situations that pose a significant risk of damage to the environment.
During Termination As stated in Section 12.1, a detailed Pipeline Abandonment Plan and procedures would be developed prior to termination of pipeline operations. Abandonment procedures would be based on applicable regulatory requirements at the time and would be designed to minimize impacts to public and private property in coordination with the land owner. For additional information regarding land status along the proposed pipeline route refer to Appendices A and B. 3.11.4
Vegetation or Timber
The primary incidents that could result in serious harm or damage to vegetation include fire that spreads to adjacent vegetation or spills of fuel or other liquids that could kill or damage vegetation. Inappropriate handling of vegetation or timber could also result in potential infestation of bark beetles or issues. Equipment used during construction may also result in damage to vegetative cover. If there was a stabilization, rehabilitation or reclamation failure, vegetation may be effected depending location and extent of damage. Donlin Gold would take all actions necessary or appropriate for the prevention and suppression of fires in accordance with applicable law and instructions from appropriate authorities. Prior to any clearing operations Donlin Gold would notify the appropriate authority of the amount of merchantable timber, if any, which would be cut, used for construction purposes, made available for others, or destroyed. All work would be performed in accordance with relevant permit and lease stipulations and in a manner to prevent infestation of bark beetles or other potential problems consistent with the Donlin Gold Timber Utilization Plan. Donlin Gold
3-30
July 2012
Plan of Development Donlin Gold Project
Project Description
Donlin Gold anticipates that the majority of timber cut from the construction ROW would be used during construction or in reclamation, however if timber is available Donlin Gold would review reasonable and practicable options for disposal of remaining timber consistent with the Timber Utilization Plan. 3.11.5
Fish or Other Wildlife or Their Habitat
All debris resulting from clearing operations and construction that may block stream flow, delay fish passage, contribute to flood damage, or result in streambed scour or erosion would be removed. Logs would not be skidded or yarded across any watercourses or stored within 300 ft (91 m) of any watercourse without approval from appropriate authorities. Appropriate plans, including the Wildlife Avoidance and Human Encounter/Interaction Plan, the Erosion and Sediment Control Plan, other applicable plans listed in POD Section 3.11.10 and construction and operating procedures would be in place to ensure protection of fish, wildlife and their habitats. Construction, operation, maintenance and termination activities would be carried out following approved plans and consistent with the regulatory requirements and the stipulations of federal and state authorizations. Construction of stream crossings on streams with anadromous fish would follow plans and design measures that would reduce impacts to migrating fish and to spawning habitat. Donlin Gold would prohibit its employees and contractors from hunting, fishing, trapping, shooting, and camping within the right-of-way or using project equipment for those purposes. Following construction, the pipeline would be reclaimed and would not significantly change big-game trails across the ROW but would provide open access along the ROW for wildlife. 3.11.6
Restoring Areas of Vegetation or Timber
Areas of vegetation or timber damaged or harmed directly or indirectly by the construction, operation, maintenance or termination of all or any part of the proposed pipeline would be identified and corrective action taken, as appropriate and consistent with the approved Stabilization, Rehabilitation and Reclamation Plan, other applicable plans, and applicable regulatory requirements or if outside of the area authorized for construction, as directed by the land owner. Corrective action would typically involve documenting the specific location of the damage, conducting an inspection and rehabilitating the disturbed area in a manner approved by the applicable regulatory agencies or land owner. Design and construction measures would be taken to avoid unnecessary damage to the project area and adjacent land. During Construction All areas of the construction ROW would be stabilized, rehabilitated and reclaimed consistent with the state and federal law and the approved Stabilization, Rehabilitation and Reclamation Plan for the proposed pipeline project. If it became necessary to restore an area outside of the construction area authorized, such work would be accomplished as directed by the appropriate agency or land owner. During Operation and Maintenance For operation and maintenance as well as for safety purposes the 50 ft (15 m) permanent ROW on state, CIRI and Calista lands and 51 ft (15.5 m) ROW on federal land would be Donlin Gold
3-31
July 2012
Plan of Development Donlin Gold Project
Project Description
cleared of shrubs at approximately 10-year intervals or as required to preserve pipeline integrity and allow for ongoing surveillance and monitoring activities as well as maintenance as may be required. During operation and maintenance any unplanned damage to the vegetation resulting from pipeline activities would be identified and corrective action taken to ensure stabilization and rehabilitation of the disturbed area, as appropriate for the situation identified and following applicable plans, procedures and regulatory requirements or if outside of the area authorized, as directed by the appropriate agency or land owner. 3.11.7
Erosion and Rehabilitation of Areas Eroded
All areas of the construction ROW would be stabilized, rehabilitated and reclaimed consistent with state and federal laws and the approved Stabilization, Rehabilitation and Reclamation Plan for the proposed pipeline project. An Erosion and Sedimentation Control Plan would be developed before the start of construction and would specifically define erosion control procedures to be applied along the pipeline ROW. In addition, a Storm Water Pollution Prevention Plan (SWPPP) would be developed as required by the APDES permit. This would address erosion control measures, reclamation and mitigation measures to control erosion and storm water runoff during and after construction. Continued ground surveillance and corrective erosion control and vegetation maintenance would be employed throughout construction of the project. Normal drainage patterns would be maintained where practical. The Stabilization, Rehabilitation and Reclamation Plan, the Erosion and Sedimentation Control Plan, and final design plans would include best management practices (BMPs) and storm drainage design to control surface flow along the crowned trench and the project ROW where necessary. 3.11.8
Ensure Compliance by Contractors and Subcontractors
In order to ensure compliance with the safeguards and stipulations of the ROW authorizations, all contractors would be pre-qualified to verify that they have an Operations Integrity Management System in place. In addition, a Quality Control Plan would be developed to identify any potential issues and verify that all work is performed in a manner to maintain the quality of the pipeline and related facilities, and to make sure all work is performed in accordance with relevant permit and lease stipulations. Donlin Gold would require its contractors and subcontractors to adhere to 100% compliance with permit stipulations and regulations, as well as to Donlin Gold’s policies, procedures and expectations. Compliance is ensured by contractor management, including the following: •
A contractor qualification evaluation for past Health, Safety and Environmental performance before contract award
•
Pre-job contractor meetings designed to identify expectations on contractor Health, Safety and Environmental Performance
•
The Integrity Management System (or equivalent) would contact requirements for inspections and audits of pipeline construction, operation, and maintenance, including those requirements that are the responsibility of contractors to adopt and enforce
•
Provisions incorporating safeguards and stipulations of the ROW authorizations, and required compliance with those standards, would be incorporated into contracts and subcontracts for construction, operation, and maintenance of the pipeline
•
Any contractor or subcontractor not complying with the safeguards and stipulations of the ROW authorizations may be subject to disciplinary action.
Donlin Gold
3-32
July 2012
Plan of Development Donlin Gold Project
Project Description
A Permits and Environmental Compliance Program would be prepared for project use during construction, operation, maintenance and termination. The purpose of the program would be to ensure compliance with project permits and applicable environmental laws and regulations. The program would be prepared after project permits and other authorizations are obtained so that permit obligations can be included and explained. The program would provide procedures for permit and regulatory compliance, including the requirements of the ROW authorizations, reporting, monitoring, and any plans. In addition, the program would detail Donlin Gold’s environmental policies and performance expectations. See Sections 8.5 and 11.16. 3.11.9
Quality Control and Procedures for Inspecting and Testing the Pipeline
The proposed Donlin Gold natural gas pipeline would be designed, constructed, operated, and maintained in accordance with the requirements of the PHMSA within the USDOT and applicable authorization requirements. These requirements are intended to ensure the safe transportation of natural gas, including adequate protection for the public from natural gas pipeline failures. The proposed Donlin Gold pipeline would meet or exceed these requirements. To ensure compliance with the safeguards and stipulations of the ROW authorizations, all contractors would be pre-qualified to verify that they have an Operations Integrity Management System in place. In addition, Donlin Gold would implement a Quality Management Program that would: •
Apply to and remain in effect during construction, operation, maintenance and termination
•
Identify the processes needed to be undertaken and the methodologies to ensure the processes are effective
•
Ensure the resources are dedicated to support the operation and monitoring of the processes
•
Monitor, measure, and analyze processes and implement corrective actions to processes if necessary.
The Quality Management Program would include a Quality Manual and Quality Control Plan including policies and objectives. Donlin Gold, including its agents, employees, and contractors would comply with the approved Quality Management Program. This program in conjunction with the Permits and Environmental Compliance Program would serve to identify any potential issues and verify that all work is performed in a manner to maintain the quality of the pipeline and related facilities, and to make sure all work is performed in accordance with relevant permit and lease stipulations. The Operation and Maintenance Plan/Manual and Pipeline Surveillance and Monitoring Plan would provide more detailed information on proposed inspection and monitoring procedures. A detailed Pressure Testing Plan would be prepared during final design. Also see Sections 8.3.29 and 8.5 for more information. Project activities planned to ensure overall pipeline quality are described below. Field Design Changes There may be a need for design changes in the field during the actual construction process based on the conditions encountered in the field. Field design changes would be documented on the drawings and in the specifications. Procedures would be developed and used during project construction and operation. Donlin Gold
3-33
July 2012
Plan of Development Donlin Gold Project
Project Description
Construction Inspection Inspections would be conducted in accordance with the Pipeline Integrity Management System and approved contractor Quality Assurance and Control Plans. In addition, a system would be developed and implemented to react quickly and efficiently to any deviations to identified standards. Inspectors trained and qualified would monitor construction activities. A set of complete records would be kept for reference during pipeline operation and maintenance and for future projects involving the pipeline. Materials and Procedures Control Suitable materials would be employed in construction of the pipeline. Strict quality control would be required of all suppliers. Field welds on the pipeline would be inspected using nondestructive testing during construction. Throughout construction, inspectors would be employed to ensure that the approved welding procedures are followed. Operations and Maintenance Once the pipeline is operational, it would be periodically inspected using in-line inspection tools- intelligent inspection pigs. The O&M Plan and Pipeline Surveillance and Monitoring Plan would provide details about inspection pigging, and would define the types and frequency of inspection pigs to be run through the pipeline. The first inspection pig run would establish baseline pipeline conditions. Subsequent pig runs would be scheduled to monitor and detect change from the baseline conditions. The frequency of the pig runs would be evaluated based on results from previous pig runs and on operating experience and requirements. Please refer to Section 11.10. 3.11.10
Special Safeguards to Protect the Interests of Individuals Living in the General Area for Subsistence Purposes
Plans and procedures to protect the interests of individuals living in the general area of the proposed right-of-way who rely on the fish, wildlife and biotic resources of the area for subsistence purposes would be integrated into the general construction, operation, maintenance and termination activities. Donlin Gold proposed mitigation measures for impacts to subsistence activities would be addressed in its Subsistence Users Plan of Cooperation. This Plan would: •
Identify locations where subsistence activities occur, and coordinate activities in these areas to the maximum extent practicable during the short span of construction activities
•
Schedule work to limit or reduce conflict with subsistence activities when possible
•
Notify workers that subsistence activities are or may be ongoing in an area and direct them to limit or reduce actions to the extent practicable that may affect the activities.
Develop and implement a Wildlife Avoidance and Human Encounter/Interaction Plan for the construction and operation of the pipeline to avoid impacts to subsistence species whenever possible especially during the short duration of construction. Donlin Gold would develop a number of plans and procedures for construction, operation, maintenance and termination of the proposed project, many of which would apply directly or indirectly to protect the environment, including fish, wildlife, and biotic resources that are used for subsistence and subsistence activities. The following are some of the plans and Donlin Gold
3-34
July 2012
Plan of Development Donlin Gold Project
Project Description
procedures that would be developed and implemented. In some cases, these plans may be combined: • • • • • • • • • • • • • • • • • • • • • •
Quality Control Plan Site Security Plans Spill Prevention Counter Control Plan (SPCC) Facility Response Plan (FRC) Erosion and Sedimentation Control Plan Storm Water Pollution Prevention Plan Material Site Mining and Reclamation Plans Blasting and Use of Explosives Plan Wildlife Avoidance and Human Encounter/Interaction Plan Comprehensive Waste Management Plan Stabilization, Rehabilitation, and Reclamation Plan Non-native Invasive Plant Prevention Plan Timber Utilization Plan Operations and Maintenance Plan Fire Prevention and Suppression Plan Emergency Response Plan Public Outreach Plan Pipeline Surveillance and Monitoring Plan Health, Safety and Environment Plan (Includes Safety Plan/Program) Subsistence Users Plan of Cooperation Commercial Lodges Plan of Cooperation Annual Report to State Pipeline Coordinator’s Office (SPCO).
A SCADA system would be implemented to collect measurements and data along the pipeline, including flow rate through the pipeline, operational status, pressure, and temperature readings. 3.11.11
Special Safeguards to Protect the Interests of Commercial Lodges
Plans and procedures to protect the interests of commercial lodges in the general area of the proposed right-of-way would be integrated into the general construction, operation, maintenance and termination activities when reasonable and where practicable. Table 3-5 and Figure 3-14 identify lodges within five miles of the proposed ROW. Donlin Gold proposed mitigation measures for impacts to commercial lodge operations would be addressed in its Commercial Lodges Plan of Cooperation. This Plan would: •
Identify locations where commercial lodges operations occur, and coordinate activities in these areas to the maximum extent practicable during the short span of construction activities
•
Schedule work to limit or reduce potential conflict with commercial guiding/lodge activities when possible recognizing that construction must be scheduled taking into account seasonal and environmental conditions and may interfere with lodge activities in proximity of the ROW
Donlin Gold
3-35
July 2012
Plan of Development Donlin Gold Project
•
Project Description
Notify workers that commercial lodge activities are or may be ongoing in an area and direct them to limit or reduce actions to the extent practicable that may affect the activities
Donlin Gold would develop and implement a Wildlife Avoidance and Human Encounter/Interaction Plan for the construction and operation of the pipeline to avoid or at least limit impacts to specific species especially during the short duration of construction when encounters are most likely to occur. Table 3-5: Commercial Lodges COMMERCIAL LODGES WITHIN 5 MILES (8 km) OF PROPOSED PIPELINE CORRIDOR Name
Location
Distance from Alignment
Main Season
Type of Business
TalVista Lodge
61.8610 N 151.4048 W
1.8 mile (2.9 km)
Summer/Winter
Guided fishing, snowmachining
Talaview Lodge
61.8607 N 151.3973 W
1.8 mile (2.9 km)
Summer
Guided fishing
TalStar Lodge
61.8575 N 151.3957 W
1.9 mile (3 km)
Summer
Guided fishing
Talachulitna River Lodge
61.8565 N 151.3904 W
1.9 mile (3 km)
Summer
Member owned fishing and recreation
Shell Lake Lodge
61.9483 N 151.5424 W
1.8 mile (2.9 km)
Winter (Summer business is fly-in only)
Restaurant/bar, snowmachining
Winter Lake Lodge
61.9870 N 152.0766 W
0.8 mile (1.3 km)
Summer/Winter (Current flight avoidance area around Finger Lake)
Heli-skiing/tours, fishing, Iditarod checkpoint
Rainy Pass Lodge
62.0904 N 152.7344 W
0.6 mile (1 km)
Summer/Winter (Project lodging in 2010, 2011, 2012; otherwise flight avoidance area)
Guided hunting, recreation, Iditarod checkpoint
Farewell Lake Lodge
62.5417 N 153.6207 W
4.4 mile (7 km)
Inactive (lodge and out buildings burned in 2010
Guided hunting, lodging
Donlin Gold
3-36
July 2012
m
n l mo Sa
R ive
r
Ri ver
DENALI STATE PAR K
R25
R24 MP-150 R23 MP-155 MP-145 MP-160
R22
R21
R20
R18
R19
rk Ye n tn aR iv e r
o
R26
MP-165 MP-140
MP-170
R15
r
MP-120
na nt Ye
LAKE C REEK RECR EATION R IVER
MP-115 MP-110 MP-105
MP-100
MP-90 MP-85
R26
R25
R24
R24
R23
R23
R22
R21
R20
TalStar Lodge
R22
R18
R19
R16
R17
MP-65
Skwentna Ri ve r r ive R14
R21
R19
R20
R18
R17
TalStar Lodge
R15
R14
MP-60
Skwentna MP-55 R12
SEE INSET R13
R9
R10
MP-50 MP-45
R9
R10
R11
MP-40 MP-35 MP-30
TALA CHUL ITNA RECR EATION R IVER
INSET
MP-25
0.5 mi
LODGE LOCATIONS
SCALE: Populated Places
Mileposts
Lodges
Proposed Natural Gas Pipeline Alignment
0
5
0
7.5
10
20 mi
Federal Administrative Boundaries State Wildlife, Park, Forest and Other Use Areas
15
30 km
FIGURE:
3-14
DONLIN GOLD PROJECT DG: PER0316.mxd, 07/23/12, R02
iver ek aR re ntn rC Ye de an ex Al
R27
R25
Shell Lake Lodge
Tala chu l i er t na R iv
R28
R26
MP-70
Ha y es
R27
Talaview Lodge
MP-75
R
TalVista Lodge
MP-80
Cr ee k ke La
Winter Lake Lodge
MP-95
er Ri v
Rainy Pass Lodge
na Ri
r ve
Proposed Donlin Gold Natural Gas Pipeline Alignment
MP-125
it
l
MP-130
K ah
Ca mp Cr ee k
R9
R10
R11
R12
R13
ek re eC La k
D E N A L I N AT I O N A L PA R K A N D P R E S E R V E
MP-135
PETERSVILL E RECREAT IONAL MI NING A REA
P et ers Cree k
W es tF
Farewell
i ve East For k Y entn a R
rk Fo dy in W
Farewell Lake Lodge
Plan of Development Donlin Gold Project
Right-of-Way Location
4.0
Right-of-Way Location (ROW)
4.1
Legal Description
The proposed pipeline ROW would cross federal, state, and Alaska Native corporation lands. Appendix A provides land status information for the entire pipeline route. Appendix B identifies in detail each parcel by landowner along the construction corridor of the proposed ROW. Table 4-1 provides estimated acreage calculation for construction. Two Alaska Native Regional Corporations own land traversed by the proposed pipeline and the proposed electric transmission line. Calista owns both surface and subsurface estate from approximately MP 307 to the pipeline terminus at the mine site. CIRI owns surface and subsurface estate from approximately MP 144 to MP 154, which is located between the South Fork of the Kuskokwim and the Sheep Creek/Farewell area. CIRI also owns the surface estate, including sand and gravel near Beluga where the first four miles of the proposed transmission line is located. Figure 4-1 shows the location of potential construction use area for Beluga.
4.2
Site-specific Engineering Surveys for Critical Areas
Site-specific engineering surveys are necessary for critical areas, defined as those areas requiring special design or mitigation, such as areas with permafrost, unstable slopes, river crossings, fault crossings, and high erosion potential. Donlin Gold has conducted specialized surveys for these areas. Results of these studies are documented in the feasibility report and summarized in Appendix C and Appendix D. The studies were used to aid in selection of the optimal route, to identify construction methods, and to develop the specialized engineering design required for certain segments of the pipeline.
4.3
River Crossings
A listing of stream and river crossings is provided in Appendix D. Typical drawings of stream crossings are included in Appendix E. Waterbody crossings are also discussed in more detail in Sections 8.1.5, 8.2.1 and specifically 8.3.15 and 8.3.16.
Donlin Gold
4-1
July 2012
TL-2
TL-1
Beluga Power Plant
TL-0
Potential Beluga Camp (10.80 acres)
Ex ten t
of
Ae ri
al
Ph
o to gr
ap h
y
Ex ten t
of
Ae ri
al P
ho
tog
rap
hy
Potential Beluga Storage (15.05 acres)
Potential Beluga Pipe Yard (14.26 acres) Beluga Barge Landing
SCALE: 0 0.5
0
0.75
Proposed Electric Transmission Line (Mileposts "TL")
Beluga Power Plant
Beluga Camp
Proposed Electric Transmission Line
Barge Landing
Storage and Pipe Yard
2 mi
1
1.5
3
km
Aerial Photography: 2003 Quickbird Seward Meridian, UTM Zone 5, NAD83
BELUGA CAMP, STORAGE & PIPE YARD AREAS
FIGURE:
4-1
DONLIN GOLD PROJECT DG: PER0284.mxd, 07/11/12, R03
Plan of Development Donlin Gold Project
4.4
Right-of-Way Location
Calculation of Estimated right-of-way Acreage
Estimated total acreage for the state and federal ROW and the Alaska Native Claims Settlement Act (ANCSA) Corporation lands for temporary construction purposes is shown in Table 4-1. The area calculation for the temporary construction right-of-way is estimated at 3,780 acres (1,530 ha), recognizing that this estimate is based on a nominal width of 100 ft (30 m) and the actual ROW will be dictated by construction requirements with necessary variance adjustments made in the field within the 1,000 ft (305 m) study area on state, federal land, Calista and CIRI lands. During construction ancillary facilities would require an additional estimated 4,108 acres (1662.5 ha). The 100 ft (30 m) temporary construction ROW would be reduced to the permanent ROW width following construction. The permanent ROW will be 50 ft (15 m) on state land except at the compressor station which would have an addition 1.8 acres (0.7 ha), 51 ft 2 inches (15.5 m) on federal land and 50 ft (15 m) on ANCSA Corporation lands and is estimated at 1,909.8 acres (772.9 ha) total. The electric transmission line easement would be approximately 13.3 miles long (21.4 km) and 30 ft (9 m) wide for an estimated 48.7 acres (19.7 ha) of which 14.3 of the estimated acres (5.9 ha) are Alaska Native Settlement Claims Act (ANSCA) lands and an estimated 34.4 acres (13.9 ha) are state lands. This includes the distance and acreage for the transmission line from the Donlin gas pipeline metering station (MP 0) to the compressor station (MP 5) which is a distance of about 5 miles (8 km) and approximately 18.2 acres (7.4 ha) of state land. Table 4-1: Estimated Acres Calculation Study Area 1,000 ft ROW (acres)
Construction ROW
Ancillary Facilities (acres)
100 ft ROW (acres)
Final ROW
Ancillary Facilities (acres)
Permanent ROW (acres)
Length (miles)
Pipeline Federal Land
11,788.8
536.9
1,174.9
881.9
600.9
96.9
State Land
24,227.0
981.8
2,426.0
3,171.6
1,215.5
200.6
1,841.0
20.5
180.0
54.3
91.8
15.1
37,856.8
1,539.2
3,780.9
4,107.8
1,908.2
312.6
ANCSA Land Estimated Total: Transmission Line State Land
15.9
22.4
34.4
9.4
ANCSA Land
14.3
14.3
14.3
3.9
Estimated Total:
30.2
36.7
48.7
13.3
Compressor Station State Land
1.8
Note: Permanent ROW is 50 ft (15 m) on state land, 51 ft 2 in (15.5 m) on federal land and 50 ft (15 m) on ANSCA Land. Transmission Line ROW would be 30 ft (9 m) on state and ANSCA lands.
Donlin Gold
4-3
July 2012
Plan of Development Donlin Gold Project
5.0
Pipeline Design Factors
Pipeline Design Factors
The design of the proposed pipeline would be in accordance with USDOT regulations under 49 CFR 192 – Transportation of Natural Gas and Other Gas by Pipeline: Minimum Federal Safety Standards. The pipeline would be designed, constructed and operated in accordance with the applicable requirements of 49 CFR 192 for subsurface pipelines and related appurtenances (compression stations, pig launching and receiving facilities, MLVs, cathodic protection, leak detection, and a SCADA system. The proposed pipeline system would incorporate pig launching and receiving facilities (receipt, midpoint, and delivery site), 19 MLVs, cathodic protection, leak detection, and supervisory control. Boost compression would be supplied by one compressor station located at approximate MP 5. No additional compression along the pipeline route would be required.
5.1
Technical Summary
Table 5-1 presents the pipeline design standards, including wall thickness and pressure standards. Final pipeline hydraulics, based on a centerline from the receipt point to the mine delivery location, would be confirmed during the first phase of detailed design. Table 5-1: Project Specific Design Criteria Pipeline Material
API 5L X52, PSL2 and Project Specifications
Pipe size
14-inch OD mainline
Pipe wall thickness
0.312-inch – mainline pipe, minimum 0.344-inch – mainline pipe 0.375-inch – mainline pipe (geohazard areas) 0.406-inch – mainline pipe (geohazard areas) 0.406-inch – HDD crossings
Pipe joint length
62 feet average
Pipe manufacturing process
HF ERW
Maximum allowable operating pressure
1,480 psig @ 100°F
Donlin Gold mine delivery pressure
550 psig
ANSI flange rating valves and fittings
ANSI Class 600
Mainline pipe yield strength
52,000 psi
Design flow rate
40 to 50 mmscfd
Typical construction right-of-way width
100 feet
Permanent easement
50 feet
Design temperature (ambient)
-40°F minimum (above grade, north of Skwentna River) -20°F minimum (above grade, south of Skwentna River) -20°F minimum (below grade)
Donlin Gold
5-1
July 2012
Plan of Development Donlin Gold Project
Pipeline Design Factors
Table 5-1 (Continued): Project Specific Design Criteria Pipeline Material
API 5L X52, PSL2 and Project Specifications 100°F maximum (above grade)
Gas temperature
20°F minimum 100°F maximum
Design life (nominal)
30 yearsa
a
The nominal design life may be extended through additional maintenance and repairs. °F = degrees Fahrenheit ANSI = American National Standards Institute API = American Petroleum Institute HDD = horizontal directional drill HF ERW = high-frequency, electric-resistance-welded mmscfd = million standard cubic feet per day OD = outer diameter psi = pounds per square inch psig = pounds per square inch gauge
5.2
Toxicity of Pipeline Product
Toxicity is the degree to which a substance is able to damage an organism that it is exposed to. Toxic and hazardous substances are regulated, generally based on their use. The agencies and regulations relevant to the pipeline product include: •
The U.S. Department of Labor, Occupational Safety and Health Administration (OSHA), regulates occupational exposures to chemical and physical agents
•
The Toxic Substances Control Act (TSCA) established requirements and authorities for identifying and controlling toxic chemicals that are hazardous to human health and the environment. As required under Section 8(b) of TSCA, the U.S. Environmental Protection Agency (EPA) maintains a list of chemicals that are in commercial use within the U.S. this list is called “the TSCA inventory of chemical substances” more commonly, “the TSCA inventory”.
The product to be conveyed by the proposed pipeline is sales-quality natural gas composed of more than 98.8% methane. Methane is biologically inactive and not considered toxic. Other small but measurable components include nitrogen and carbon dioxide, which are also not considered toxic. Table 3-1 shows the gas composition.
5.3
Anticipated Operating Temperatures
The proposed pipeline would operate as an ambient-temperature pipeline for its entire length, with the exception of the first 10 to 15 miles (16 to 24 km). An ambient-temperature pipeline is a pipeline with operating temperatures that closely approach the seasonal temperatures of the surrounding ground. The proposed pipeline operating temperature would be governed by the combined influence of Joule‐Thompson cooling associated with gas pressure drop, pipe wall heat transfer between gas and surrounding soil, and heat input from gas compression. The first 10 to 15 miles (16 to 24 km) of the pipeline would be slightly higher in temperature, where the pipe would transition from discharge temperature at the compressor station to surrounding soil temperature. The discharge temperature at the compressor station would
Donlin Gold
5-2
July 2012
Plan of Development Donlin Gold Project
Pipeline Design Factors
depend on inlet gas temperature and air temperature but would be limited to no more than 100 degrees Fahrenheit (°F) (37.8°C). The temperature of the proposed pipeline would follow seasonal ground temperature at low-flow rates. At full capacity, because of the relatively small diameter of the pipe, the cooling associated with gas pressure drop would not result in significant non‐ambient pipeline operation.
5.4
Depth of Pipeline
This pipeline would be buried, except at the compressor station, pigging facilities, and fault crossings. Some ancillary, small-bore pipe would be aboveground at mainline valve assemblies and valve locations. Burial modes would be trenches or HDD. The pipeline would exit the ground and be placed on support structures through the two known fault crossings. The aboveground length of these crossings is estimated to be approximately 1,300 ft (396 m) for each. Minimum cover requirements, in accordance with 49 CFR 192, are shown in Table 5-2. Certain stream or drainage crossings would be installed by trenching to a greater depth (up to 10 ft [3 m] below thalweg) for scour protection. Table 5-2: Minimum Cover Requirements Minimum Cover (inches) No Rock
Rock Trench
Standard trench
30
18
Drainage or ephemeral waterways
48
24
Greater burial depths would be achieved in areas where the proposed pipeline would be installed using HDD methods. HDD is generally used on major river crossings that are difficult to accomplish with traditional trenching equipment and methods, at crossing locations that support high-value or sensitive fish habitats, and in areas of geohazards where trenching is not feasible because of unstable slopes. The HDD method uses specialized equipment to drill pipeline crossing beneath a stream or riverbed or under rough topography. The equipment, which operates outside the active stream channel and HDD crossings, does not disturb the bed or banks of the stream that is being crossed
5.5
Permanent Width or Size
The permanent width or size of the main proposed pipeline ROW would normally be 50 ft (15 m) through state lands and 51 ft (15.5 m) through federal lands. On all Native Corporation land through which the proposed pipeline traverses the permanent width or size of the right-of-way would also be 50 ft (15 m). The estimated length and width of the electric transmission line portion of the permanent ROW that runs from the Chugach Electric’s Beluga Power Plant to MP 0 at the BPL is approximately 8.3 miles (13.4 km) long and 30 ft (9 m) wide, and then the electric transmission line ROW runs on to the compressor station at MP 5. The compressor station parcel would also be included as part of the permanent pipeline ROW as would any other permanent areas. The permanent ROW would be cleared of shrubs at approximately every 10 years or as required.
Donlin Gold
5-3
July 2012
Plan of Development Donlin Gold Project
5.6
Pipeline Design Factors
Temporary Areas Needed
A nominal 100-foot (30.5m) width would be cleared and used temporarily for construction purposes within a 1,000 ft (305 m) study area needed during construction of the proposed pipeline. In addition to the 100 ft (30.5 m) temporary construction area, additional workspace would be needed for safe pipeline construction at HDD locations. Also areas for staging materials and equipment, barge landings, camp facilities, airstrips (discussed in more detail in Section 8.2.8), and access roads would be needed to support construction. The actual width of the temporary construction ROW within the corridor would be dictated by construction needs and any areas not evaluated already for cultural resources would be reviewed prior to clearing. Appendix A shows location of necessary additional workspace or other temporary use locations. Refer to Table 4-1 for estimated acreage calculations footprint by land jurisdiction. Appendix B provides the legal descriptions for temporary use areas. Section 8.2.8 discusses land requirements in more detail.
Donlin Gold
5-4
July 2012
Plan of Development Donlin Gold Project
Additional ROW Components
6.0
Additional Right-of-Way Components
6.1
Connection to Existing Right-of-Way
The proposed Donlin Gold pipeline would originate from the BPL ROW. Between this point and the mine site, the pipeline would run cross-country and would not parallel any other existing pipelines, utility lines, or improved roads. The DNR recognizes the Iditarod Trail and RS-2477 routes as transportation corridors. The Iditarod Trail/RST-199 is the main ground transportation route for access to private land, recreation, commercial activities, etc. in the area. See Section 8.1.2 for more detailed discussion of Iditarod. Please refer to Appendices A and B for information regarding existing rights-of-way.
6.2
Existing Components on or off Public Land
There are no existing facilities or any designated utility corridors along the proposed pipeline route. However, DNR in its planning process for the Susitna-Mat Su area plan recognized the potential for proposed Donlin Gold pipeline.
6.3
Possible Future Components
It must be recognized that the Donlin Gold gas pipeline is a distribution line the purpose of which is to transport natural gas for operational use at the Donlin Gold mine site. At this time, no additional facilities or components are planned. The addition of off-takes to provide gas to communities or to other entities along or beyond the route is a possibility. However, such additions would be considered based on Donlin Gold’s own requirements, the community or other need, and technical and fiscal feasibility and may be developed on a case-by-case basis. If additional gas supply is required for operation of the mine, an additional compressor station could be added to increase gas volume. The location would have to be determined but it is anticipated that it could be located at or about MP 153.6. See Section 3.6.
6.4
Location and Description of Compressor Station
One compressor station would be required to boost the gas pressure for delivery to the mine site. Based on current design, a single compressor station would provide sufficient compression for the gas throughput. The current location of the compressor station would be approximately 5 miles (8 km) north of the tie-in to the BPL in the Matanuska-Susitna Borough at pipeline MP 5. The 2-acre (.81 ha) facility would be unmanned, with fully automated equipment operated by a remote-control system. A 10-foot-high (3.1 m) chain link fence would surround the site with lockable, operable gates that meet the egress requirements of 49 CFR 192 for security. All exterior mainline valves at the compressor station would be fitted with locks, and all module doors would be lockable. Surveillance cameras would be located to alert operators if there was intrusion into the fenced areas or into the modules. These would operate 24 hours a day, 7 days a week. The site would include a helicopter landing pad. Figure 6-1 is a compressor site location map that also shows the powerline alignment. This location was selected to avoid placing the compressor inside the Susitna Flats State Wildlife Refuge. Section 8.2.5 provides more detail on the compressor station design and operational requirements. See Appendix A for specific location and land status for the compressor station.
Donlin Gold
6-1
July 2012
Plan of Development Donlin Gold Project
Additional ROW Components
An alternate site inside the Susitna Flats State Wildlife Refuge is still being evaluated. If the compressor station was placed at the BPL at MP 0 it would eliminate the need for the additional length and impact of the transmission line along the ROW to MP 5, eliminate the need for the compression station work camp at that site, and potentially reduce the overall size of the area of disturbance required as access to the MP 0 site could be by existing road. If this alternate site were to be used, there would also be a reduction in overall reclamation requirements for reclaiming the construction camp site, and in final reclamation for removal of the transmission line for an additional five miles and combined compressor station and the metering facility. Depending on design and engineering requirements, there would likely be a reduction in the actual number of acres impacted and in the overall cost as well.
6.5
Location and Description of Electric Transmission Line
Electrical power to the compressor station would be provided by a 25-kilovolt (kV), crosscountry power line originating at the 385-megawatt CEA power plant at Beluga. The routing of the medium voltage (MV) transmission line proposed 30 ft (9 m) easement would follow the CEA high-voltage transmission line corridor to the BPL tap point. At the tap point, which is the start of the proposed Donlin Gold pipeline, a 15-kilovolt-ampere transformer would be mounted to the transmission line to supply utilization-level voltage to a gas metering module. Figure 6-1 which is a compressor site location map shows the power line alignment. The location of the transmission line and land status is also shown on the strip maps in Appendix A. The 30 ft (9 m) easement width was selected to minimize impacts and remain, to the extent possible, within the existing CEA transmission line corridor. Installation of the distribution line is approximately 13.5 miles (22 km) in length, running north from the Beluga Power Plant, the northwest to the gas compressor station. The line would be constructed using Douglas fir treated wood poles 40 to 60 ft (12 to 18 m) in length using the standard (Matanuska Electric Association (MEA) construction details and American National Standards Institute (ANSI) 05.1 standards. Pole spacing is estimated at 325 ft (99 m), for a total estimated quantity of 220 poles. Twenty-two of these poles were estimated for drill and would be set at a depth to 10 ft (3 m). Thirty-three of these poles are expected to be placed in soils suitable for direct embedment, and the other 165 poles were estimated for driven H-pile (HP8X40) attachment because of the presence of swampy areas and uncertain terrain conditions. The conductor size would be 4/0 ACSR because of the original 1/0 ACSR allowed design tension given the span lengths.
Donlin Gold
6-2
July 2012
Plan of Development Donlin Gold Project
6.6
Additional ROW Components
Location and Description of Fiber Optic Cable and Repeater Station
The fiber-optic cable (whether a 48-strand, figure-8 fiber optic cable or otherwise would be determined during final design) would extend aboveground from the General Communications Inc. (GCI) module at Beluga power plant to the metering station at the pipeline tie-in to the BPL at pipeline MP 0 via the electric transmission line support structures (installed below the distribution neutral in compliance with National Electric Safety Code (NESC) clearance requirements) as located in Figure 6-1. From the metering station the fiber optic cable would be buried with the pipeline to the compressor station at MP 5 then in the buried mode with the pipeline, except where both would be above grade at the fault crossings, on to the mine site. The details for installation of the fiber optic cable in the buried and aboveground modes would be determined during final design and engineering. A repeater station would be required and a potential location would be at approximately MP 44 although other options are being evaluated. The estimated total length of the fiber optics cable route is 322 miles (518 km). The actual location of the repeater station would be decided during final design. Emissions from heating the repeater station facility would be minimal, if any, and would be determined during final design.
6.7
Location and Description of Sand and Gravel Sites
Potential sand and gravel sites are discussed in Section 8.2.8 and are identified in Table 85. The location of material barrow sites and land status is shown on the strip maps in Appendix A. There would be a need for substantial amounts of sand and gravel for temporary road access, pipeline workpads, pipeline bedding and padding, pads for compressor station, airfields, campsites, and laydown yards. Approximately 63 material site locations have been identified. Sites would normally include a screening plant but not wash plants. The final volumes of granular materials and development plans for each site would be determined during final design. Material sites and quantities as well as any batch/processing plant would be authorized on state and federal land under separate authorizations and not under the ROW. Material sales and land use permits would be required. Also final requirements for location of material processing plants, if any, would be determined during final design.
6.8
Location and Description of Pig Launcher/Receiver Facilities
The pig launcher and receiver barrels would be designed to be able to launch or receive both maintenance pigs and inline inspection pigs (smart pigs). There would be three launchers and three receivers on the project. The launchers would be located at the BPL tiein (MP 0), the compressor station (MP 5), and the Farewell launcher/receiver site (MP 153.6). The receivers would be located at the compressor station, the Farewell launcher/receiver site, and the pipeline terminus at the mine site. All these facility sites would be fenced with a sliding gate and lock to provide some protection from animals and people. The pigging receiver and launcher near Farewell (MP 153.6) would include some aboveground piping, valves, and valve operators. The valves or operators at this location would be fitted with locks, as would the pig launcher and receiver doors. The site would be approximately 160 ft (49 m) x 50 ft (15 m) with a fenced area of approximately 200 ft (61 m) x 100 (31 m). All barrels and associated abovegrade piping would be designed so that they can be vented to atmosphere to relieve any internal gas pressure. The intent is that, after the pipeline
Donlin Gold
6-4
July 2012
Plan of Development Donlin Gold Project
Additional ROW Components
operators have used the barrels and associated piping, the barrels would be vented to atmosphere and left in an unpressurized condition until the next pigging operation. The pressure containment design of the barrels and associated piping is prescribed by 49 CFR 192 and other codes and standards referenced therein. The doors on the barrels would be stamped in accordance with Section VIII of the ASME Boiler and Pressure Vessel Code. Each launcher or receiver would have a trolley structure above the end of the barrel for hoisting the pigs into and out of the barrels
6.9
Location and Description of Metering Stations
The metering stations at the pipeline tie-in (MP 0) and at the pipeline terminus metering station (approximately MP 313) at the mine site would include some limited aboveground piping and a module housing the metering equipment are shown in Figure 6-2. The tie-in location would be fenced with sliding gate and lock, and any mainline manual valves would be fitted with locks. The pipeline terminus would have locks on all the manually operated mainline valves. The metering modules would have locking man-doors, as would the launcher or receiver doors at these locations. Also refer to Sections 8.2.3 and 8.2.4 for additional information. Appendix A shows the location and land status of the metering station at MP 0.
Donlin Gold
6-5
July 2012
MINE TIE-IN SITE PLAN SITE INFORMATION
PAD: 100'-0" x 100'-0" AREA: APPROX. 0.25 ACRES
EXISTING PIPELINE TIE-IN SITE PLAN SITE INFORMATION
PAD: 120'-0" x 53'-0" AREA: APPROX. 0.15 ACRES
UNITS AND WEIGHTS
80'x100' HELIPAD VALVE VAULT 12' x 12' METERING SKID 10'x15'x13' TALL PIG LAUNCHER: 2500 LBS PIPING 1000 LBS LAUNCHER DOOR MONORAIL
UNITS AND WEIGHTS
STATION BLOWDOWN 30'x12' PIG RECEIVER: 2500 LBS PIPING 1000 LBS RECEIVER DOOR V 102 20'x15' PLATFORM METERING SKID 10'x15'x13' TALL CONTROL MODULE 8'x8'
SCALE:
NOT TO SCALE
FIGURE:
METERING STATIONS
6-2
DONLIN GOLD PROJECT DG: PER0319.mxd, 07/16/12, R01
Plan of Development Donlin Gold Project
6.10
Additional ROW Components
Location and Description of Mainline Block Valves
Valves would be placed at intervals of no more than 20 miles (32 km). In total, there would be 19 block valves with locations shown in Table 6-1 and in Appendix A. There would be four facility locations at fixed block valve locations: the BPL tie-in, the compressor station, the Farewell launcher/receiver site, and the pipeline terminus at the mine site. The valves located at the BPL tie-in, the compressor station, and the pipeline terminus would be able to be remotely operated, function as emergency shutdown (ESD) valves, and be automatically operated by a SCADA system. The ESD valves would also be able to be manually operated by activation of an ESD switch at any of the three sites and be manually closed by an operator onsite if necessary. The remaining 15 MLV locations that would not be associated with pipeline facilities would have valve operators, small-bore piping, and associated valves positioned aboveground. All of these valves would be manually operated. The valves and operators would be fitted with locks and a signpost similar to the pipeline MP markers, with MP number sign MLV-XX, representing the MLV number. Reflective tape would be positioned on the suggested signpost, and there may be other visual aids with reflective tape to alert travelers along the ROW of the presence of the valve stations. There are no structures planned for these MLV sites. The 25 x 25 ft (7.6 x 7.6 m) MLV sites would be fenced and would have sliding gates with locks. It was determined that the use of crack arrestors on the pipe was not required for this pipeline because of the wall thickness of the pipe and the relatively low yield strength of the steel (API 5L X52 PSL2 pipe would be used). The pipe wall required for pressure containment is slightly less than 0.250 inches (0.6 cm), but because of pipe handling issues prior to installation the thinnest wall thickness pipe in the system is 0.312 inches (0.79 cm)”. With the additional wall thickness of the pipe and the ductility of the X52 pipe it was assumed for the purposes of the feasibility study that crack arrestors would not be required. This issue would be reviewed during final design.
Donlin Gold
6-7
July 2012
Plan of Development Donlin Gold Project
Additional ROW Components
Table 6-1: Mainline Valve Location Summary No.
TAG
MP (Approx.)
1
MLV-01
0.00
2
MLV-02
5.00
3
MLV-03
25.00
4
MLV-04
44.00
5
MLV-05
63.00
6
MLV-06
83.00
7
MLV-07
100.00
8
MLV-08
116.77
9
MLV-09
136.00
10
MLV-10
153.60
11
MLV-11
173.06
12
MLV-12
192.70
13
MLV-13
211.99
14
MLV-14
229.00
15
MLV15
249.00
16
MLV-16
269.00
17
MLV-17
289.00
18
MLV-18
301.00
19
MLV-19
313.67
Donlin Gold
6-8
July 2012
Plan of Development Donlin Gold Project
Government Agency Involvement
7.0
Government Agency Involvement
7.1
Entities that have Regulatory Authority or would be affected by the Proposed Project
Specific federal, state, and local government agencies have regulatory authority over different aspects of the pipeline project. The scope of regulatory decision-making includes the authorities listed in Table 7-1. Table 7-1: Federal, State and Local Agencies with Regulatory Authority Federal Agencies U.S. Department of the Interior–Bureau of Land Management U.S. Army Corps of Engineers U.S. Coast Guard U.S. Environmental Protection Agency U.S. Department of Transportation –Pipeline and Hazardous Materials Safety Administration–Office of Pipeline Safety U.S. Fish and Wildlife Service National Marine Fisheries Service Federal Aviation Administration State Agencies Alaska Department of Natural Resources •
State Pipeline Coordinator Office
•
Office of History and Archaeology
•
Division of Forestry
•
Division of Mining, Land and Water
Alaska Department of Environmental Conservation Alaska Department of Fish and Game Alaska Department of Health and Social Services Alaska Department of Labor and Workforce Development Alaska Department of Public Safety-Fire Marshall Alaska Department of Transportation and Public Facilities Local Agencies Matanuska-Susitna Borough Kenai Peninsula Borough
There are also a number of federally recognized tribes along the proposed pipeline route with whom government-to-government consultation would be required during the NEPA process, as shown in Table 7-2.
Donlin Gold
7-1
July 2012
Plan of Development Donlin Gold Project
Government Agency Involvement
Table 7-2: Federally Recognized Tribes along the Pipeline Route by Region Region Southwest AlaskaKuskokwim River
Community
BIA Recognized Tribe
Crooked Creek
Native Village of Crooked Creek
Georgetown
Native Village of Georgetown
Red Devil
Native Village of Red Devil
Sleetmute
Native Village of Sleetmute
Stony River
Native Village of Stony River
Southwest AlaskaYukon-Kuskokwim Delta
Lime Village
Lime Village
Southcentral Alaska
Knik
Knik Tribe
Tyonek
Native Village of Tyonek
McGrath
Native Village of McGrath
Nikolai
Nikolai Village
Shageluk
Native Village of Shageluk
Takotna
Takotna Village
Telida
Telida Village
Louden
Louden Tribel Council (Galena)
Anvik
Anvik Village
Grayling
Village of Grayling
Holy Cross
Holy Cross Village
Interior Alaska
7.2
Communications Protocol
7.2.1
State Agency Coordination
The SPCO has established a set protocol for coordinating communications involving projects that are within the State Pipeline Coordinator’s authority. Figure 7-1 graphically depicts the flow of communication to and from the SPCO for state agency coordination. 7.2.2
Federal Agency Coordination
It is anticipated that the BLM would be the federal coordinating agency and the COE would be the lead agency for the NEPA process.
Donlin Gold
7-2
July 2012
SCALE:
NA
COMMUNICATION PROTOCAL FOR STATE AGENCY COORDINATION
FIGURE:
7-1
DONLIN GOLD PROJECT DG: PER0279.mxd, 08/30/11, R01
Plan of Development Donlin Gold Project
7.3
Government Agency Involvement
List of Project Authorizations
A substantial effort would be required to obtain all necessary project authorizations before beginning construction activities. These authorizations are identified in Table 7-3 and organized by subject. No Federal Energy Regulatory Commission (FERC) Section 7(c) application is required because the proposed action is intrastate and, therefore, outside FERC jurisdiction. 7.3.1
State ROW Lease Required Documents
Figure 7-2 identifies documents that are required once the State Right-of-way Lease is issued and before the SPCO would accept an application for an overall Notice to Proceed (NTP) with the project on state land under the ROW Lease. Documents required once the overall NTP is received but before an application would be accepted for an NTP for a specific construction segment; documents required to be submitted with an application for an NTP for a specific construction segment documents that are required to be submitted before actual startup and documents that would be required annually following startup required on an as needed basis during operation and required at the end of life of the project. The SPCO may request documents under the terms and conditions of the lease or authority that may not be listed in this chart.
Donlin Gold
7-4
July 2012
SCALE:
NA Source: Alaska Gas Development Authority
STATE ROW LEASE REQUIRED DOCUMENTS
FIGURE:
7-2
DONLIN GOLD PROJECT DG: PER0281.mxd, 08/30/11, R01
Plan of Development Donlin Gold Project
Government Agency Involvement
Table 7-3: Permits and Authorizations Permit Type
Agency
Citation
Activity
Acquisition Time
Notes
Land Use 1
Federal pipeline grant of ROW BLM and associated temporary use permits
43 CFR 2880, and the Mineral Leasing Act of 1920; 43 CFR 2800 and the Federal Lands Policy and Management Act
ROW for new pipeline through federal lands.
3 years
Submittal of SF 299 application(s)for ROW(s) initiates the BLM's NEPA process
2
State pipeline ROW lease
DNR SPCO
AS 38.35 11 AAC 80.005
Pipeline ROW lease for a new pipeline on state lands..
3years
.
Discharge into Waters of the US 3
Preliminary jurisdictional determination
USACE
33 CFR 331.2
To determine the presence of wetlands (waters of the U.S.).
90 days after submittal of Jurisdictional Determination
A Final Jurisdictional Determination is issued after the selected alternative is identified in the ROD.
4
Dredged or fill material
USACE
33 CFR 323 (Section 404 of CWA
Placement of fill or dredged material into waters of the U.S. (wetlands).
3 years
Submittal of USACE permit application initiates the COE's NEPA process.
5
Dredged or fill material
ADEC
18 AAC 70 (Section 401 of CWA)
Water Quality Certification for a permit for placement of fill or dredged material into waters of the U.S. (wetlands).
3 years
Section 401 would be obtained concurrent with the Section 404 permit.
Permit Applications To Be Submitted During EIS Process Navigable Waters and Water Use 6
Permits For Structures or Work USACE In or Affecting Navigable Waters of The United States
33 CFR 322 (Section 10 of the Rivers Authorization for certain structures or work in or affecting navigable waters of the United States, including docks, and Harbors Act of 1899) wharf, piers and other structures.
3 years
Included in Section 404 permit application
7
Construction of dams/ dikes or U.S. Coast Guard bridges/causeways in navigable waters
33 CFR, Subchapter J Section 9 of the Rivers and Harbors Act of 1899; General Bridge Act of 1946
Construction of any dam or dike in a navigable river or navigable water of the U.S. must be permitted by USACE. Construction of any bridge or causeway in a navigable river or navigable water of the U.S. must be permitted by DOT.
3 years
Included in section 404 permit application
8
State Navigable Waters Determination
DNR
AS 38.05.127
State would make navigable waters determine.
ADF&G
AS 16.05.871 (Habitat)
Permit is necessary for activities that use, divert, obstruct, pollute, or change natural flow of specified anadromous fish streams. Permit is necessary for activities that use, divert, obstruct, pollute, or change natural flow of non- anadromous fish streams that have resident fish.
90 days
Concurrent with state pipeline ROW lease processing.
Wildlife 9
Fish passage and habitat protection
AS 16.05.841 (Passage)
10
Bald and golden eagles
USFWS
50 CFR 22 Bald and Golden Eagle Protection Act
Any activity that could "take" a bald or golden eagle, their eggs, feathers or nest as defined within the Eagle Protection Act.
N/A
Not a permit - consultation required
11
Migratory birds
USFWS
50 CFR 21 Migratory Bird Treaty Act
Project activities that require consultation regarding effects to migratory bird species.
N/A
Not a permit - consultation required
12
Wildlife protection measures
ADF&G
5AAC92 5, AAC 95.900
Design and construction of pipeline to avoid significant alteration of caribou and other large ungulate movement and N/A migration patterns.
Donlin Gold
7-6
Not a permit - consultation required under NEPA State ROW Lease would require a Wildlife Interaction Plan
July 2012
Plan of Development Donlin Gold Project
Government Agency Involvement
Table 7-3 (Continued): Permits and Authorizations Permit Type
Agency
Citation
Activity
Acquisition Time
Notes
13
Endangered, Threatened, or Candidate Species
USFWS
50 CFR 402 Section 7 of the ESA
If proposed activity affects species listed under the ESA, obtain agreement with USFWS about scope of studies to determine project's probable effect on Threatened and Endangered Species.
N/A
Not a permit - consultation required under ESA.
14
Essential Fish Habitat (EFH)
NMFS
50 CFR 600 Magnuson-Stevens Act provisions
Federal agencies are required to consult with NMFS on any action that may result in adverse effects to EFH.
N/A
Not a permit - consultation required under NEPA
15
Fish collection
ADF&G
AS 16.05.340(b)
Required of anyone who wants to collect or hold alive any live fish, shellfish, or aquatic plants or their gametes (except gold fish and decorative tropical fish) for purposes of science, education, propagation, or exhibition
30 days
Typically required for field studies
Archaeological 16
Archeological Resources BLM Protection Act Permit (ARPAP)
16 USC 470; activities that require cultural resource surveys on federal land.
Activities that require cultural resource surveys on federal land.
30 days
17
Alaska cultural resource
DNR/SHPO
AS 41.35.080
Permit is required for investigation, excavation, gathering, or removal of any historic, prehistoric, or archaeological resources of the state.
30 days
Typically required for field studies only
18
Section 106 consultation
DNR/SHPO
36 CFR Part 800, National Historic Preservation Act (NHPA)
Any project funded, licensed, permitted, or assisted by the federal or state government.
N/A
Not a permit - consultation required under NEPA
19
Section 106 consultation with State Historic Preservation Office (SHPO)
Tribal entities
36 CFR Part 800, NHPA
Any project funded, licensed, permitted, or assisted by the federal government.
N/A
Not a permit - consultation required under NEPA
20
Preservation of historic, prehistoric, and archaeological resources
DNR/SHPO
AS 41.35.070 (OHA), SHPO, Alaska Historic Preservation Act
Any project located on state lands.
90 days
Concurrence required from OHA and SHPO
Land Use 21
Casual and temporary Use Permits
BLM
43 USC 1701(FLPMA); Mineral Leasing Act of 1920 Section 28 43 CFR 2920
Project Activities that would require access to or for temporary use of federal lands.
22
Special area permit
ADF&G DNR
5 AAC 95.420, 5 AAC 95.700-770
Activities, except for lawful hunting, trapping, fishing, viewing, and photography occurring in state game refuges, 90 days sanctuaries, critical habitats, state recreation areas, across designated wild and scenic rivers, or through state parks require a special area permit. Use of helicopter or motorized vehicle requires a permit.
23
Land use and/or zoning
MSB
MSB Comprehensive Plans and Zoning
Activities occurring within MSB and on MSB lands.
60 days
24
Land use and/or zoning
KPB
KPB Comprehensive Plans and Zoning
Activities occurring within KPB and on KPB lands.
60 days
N/A
Coastal Zone management Program not applicable at time document was prepared Miscellaneous - Consultations, Stipulations, and Requirements 25
Environmental justice
All federal agencies Executive Order (EO) 12898
Activities that may disproportionately affect minorities and low-income populations (for example, subsistence).
26
Protection of Subsistence Users and Resources
State and Federal
AS 38.35.100
Mitigate impacts to users and resources
27
Health Impact Assessment
DHSS
Not a State statutory requirementassociated with EIS
Assess potential impacts of the project on health in the general area
28
Wetlands protection consideration
All federal agencies Executive Order (EO) 11990
Donlin Gold
Agencies must take action to minimize the destruction, loss, or degradation of wetlands.
7-7
Not a permit - consultation required under NEPA
Not a permit N/A
Not a permit - consultation required under NEPA
July 2012
Plan of Development Donlin Gold Project
Government Agency Involvement
Table 7-3 (Continued): Permits and Authorizations Permit Type
Agency
Citation
Activity
Acquisition Time
Notes
Preconstruction, Construction, and Operation Permits Water Use 29
Floodplain management
All federal agencies Executive Order (EO) 11988
Agencies must take action to reduce the risk to flood loss; minimize the impact of floods on human safety, health, and welfare; and restore and preserve the beneficial effects served by floodplains.
30
Permit to appropriate water
DNR
11 AAC 93.040 - 140
Application for water for camp use.
31
Temporary water use
DNR
11 AAC 93.220
Temporary water use, ice armoring, and pipe testing for period of less than 5 consecutive years.
32
Fish habitat protection
ADF&G
AS 16.05.871 or AS 16.05.841
Water withdrawal from fish bearing waterbodies.
33
APDES Construction Stormwater Permit
ADEC
18 AAC 83
Discharge of pollutant from a point source into waters of the U.S.
Not a permit - consultation required under NEPA
Alaska is fully authorized to administer the EPA's NPDES program. 18 AAC 83.005 – 18 AAC 83.990 implements the Alaska Pollutant Discharge Elimination System (APDES) point source wastewater discharge program in a manner that meets the purposes of AS 46.03 and in accordance with 33 U.S.C. 1342 (Clean Water Act, sec. 402) and the requirements adopted by reference at 18 AAC 83.010.
34
Non-domestic wastewater disposal
ADEC
18 AAC72.500-.900
Discharges to land, surface water, or groundwater in Alaska.
Hazardous Material and Waste 35
Approval from local landfill operators to deposit nonhazardous solid waste
MSB
MSB regulations
Handling of solid waste at local landfills.
36
Generator ID number
EPA
40 CFR 262, RCRA, (18 AAC 62.210 adopted by reference)
All companies that treat, store, dispose of, transport, or offer for transport regulated waste must obtain an EPA ID number.
37
Transportation and disposal of EPA hazardous waste
40 CFR 262, RCRA (18 AAC 62.210 adopted by reference)
Follow requirements regarding transportation, treatment, and disposal of hazardous waste.
38
Hazardous chemical inventories
EPA
40 CFR 302, CERCLA, Title III Superfund Amendments and Reauthorization Act
Reporting, planning requirements for facilities that handle, store, and/or manufacture hazardous materials.
39
Hazardous chemical inventories
Alaska Department AS 26.23.073, AS 26.23.077 of Military Affairs
Reporting, planning requirements for facilities that handle, store, and/or manufacture hazardous materials.
ADF&G
5 AAC 92.033
Permit to take, relocate, haze, or destroy birds or their eggs or nests, mammals or reptiles for public safety purposes.
18 AAC 50.065 (b)-(f)
General requirements for open burning, also ensure that (1) material is kept dry, (2) noncombustible’s are separated, (3) draft is present, (4) combustibles are separated from grass and peat, and (5) combustibles are not allowed to smolder.
Wildlife 40
Public safety
Air Quality 41
Air quality requirements for ADEC open burning (vegetation from ROW)
Transportation 42
Transportation of hazardous materials
ADOT&PF
17 AAC 25.200
Transportation of hazardous materials, hazardous substances, or hazardous waste by vehicle.
43
Airport operation
Federal Aviation Administration
14CFR139
An Airport Operating Certificate must be obtained to construct, align a new airport, or activate an airport.
Donlin Gold
7-8
This permit may not be applicable for proposed activities
July 2012
Plan of Development Donlin Gold Project
Government Agency Involvement
Table 7-3 (Continued): Permits and Authorizations Permit Type 44
Agency
Citation
Activity
Oversized and overweight vehicles (pipe hauling)
ADOT&PF
17 AAC 25.300
Oversize and overweight vehicle permit.
45
Domestic wastewater discharge permit and plan approval
ADEC
18 AAC 72 11 AAC 83
Permit and plan approval required before domestic wastewater system can be constructed, installed, operated.
46
Domestic wastewater discharge permit and plan approval
ADEC
18 AAC 72.010, 200, and 215
Permit and plan approval required before domestic wastewater system can be constructed, installed, operated.
47
Drinking water plan approval
ADEC
18 AAC 80.200
Camps—human consumption.
48
Food service (camps)
ADEC
18 AAC 31.020
Permit for food service facilities serving 10 or more people per day.
49
Solid waste management
ADEC
18 AAC 60
Handling of solid waste at camp locations and final disposition.
Acquisition Time
Notes
Camp
Miscellaneous 50
SPCC
EPA
40 CFR 112 Oil Pollution Prevention
SPCC must be available for review. Discharge of oil from non-transportation-related onshore facilities onto or upon navigable waters of the U.S. Includes interstate and intrastate onshore pipeline systems including pumps and appurtenances as well as inline or breakout storage tanks needed for continuous operation of a pipeline system.
51
Natural gas pipeline safety
Pipeline and Hazardous Materials Safety Administration
49 CFR 190-192
Transportation of Natural Gas by Pipeline Safety and Reporting Requirements.
52
OSHA Regulations
ADOL/WD
AS 18.60.180, 8 AAC
Assurance that project related activities meet standards and regulations for occupational health and safety.
53
Fire Marshall Permit
ADPS
AS 18.70.080, 13 AAC 50.027
Permit and plan approval by State Fire Marshal for construction of facilities
54
Mineral Material Sales Contract
BLM
Mineral Leasing Act and other applicable laws 43 CFR 3600
Use of gravel, sand and/or rock from sources on federal land.
55
Material Sale Contract
DNR
AS 38.05
Use of gravel, sand and/or rock from sources on state land.
56
Land Use Permit
DNR
AS 38.05
Land Use Permit is required for any material batch or processing plant on State land
57
Fuel Systems
ADPS
2009 IFC
All fuel systems being developed to support port and airport operations during pipeline construction and operations must be reviewed and found to conform with the 2009 International Fire Code (IFC) requirements.
58
Explosive Storage
ADPS
2009 IFC
Although explosive blasting is not anticipated to be used in the project, if used the storage magazine type, location and any barricade requirements must meet IFC requirements.
59
Transport of Explosives Permit and License
U.S.BATF
If explosives are used in the project it would require a permit and license from the U.S. Bureau of Alcohol, Tobacco, and Firearms for use and transport.
60
Letters of Nonobjection/Agreement
DNR/Permittee
Letters of non-objection or agreements from ENSTAR Natural Gas Company (ENSTAR), CEA and GCI for the tieins to existing authorized facilities will be required (Note: Final authorization for the ENSTAR Beluga Line has not been issued).
61
Concurrence
DOTPF/DNR/SHPO
Concurrence needed for segments of project that potentially affect the Iditarod National Historical Trail.
62
Right-of-Way
DNR/BLM/ private land owners
Authorizations/agreement to install fiber optic cable and construct repeater station
DOTPF/ FAA
DOTPF/FAA concurrence would be required at public airstrips
63
Donlin Gold
7-9
July 2012
Plan of Development Donlin Gold Project
Government Agency Involvement
Table 7-3 (Continued): Permits and Authorizations NOTES: ADEC = Alaska Department of Environmental Conservation ADF&G = Alaska Department of Fish and Game DNR = Alaska Department of Natural Resources ADOLWD = Alaska Department of Labor and Workforce Development ADOT& PF = Alaska Department of Transportation and Public Facilities ADPS = Alaska Department of Public Safety APDES = Alaska Pollutant Discharge Elimination System AS = Alaska Statute BLM = U.S. Department of Interior, Bureau of Land Management CERCLA = Comprehensive Environmental Response, Compensation, and Liability Act of 1980 CFR = Code of Federal Regulations CWA = Clean Water Act DOT = U.S. Department of Transportation EFH = Essential Fish Habitat EIS = environmental impact statement EO = Executive Order EPA = U.S. Environmental Protection Agency ESA = Endangered Species Act ID = identification
Donlin Gold
KPB = Kenai Peninsula Borough LOA = Letter of Authorization ODPCP = Oil Discharge Prevention and Contingency Plan MMPA = Marine Mammal Protection Act MSB = Matanuska-Susitna Borough N/A = not applicable NEPA = National Environmental Policy Act NHPA = National Historic Preservation Act NMFS = National Marine Fisheries Service OHA = Alaska Office of History and Archaeology RCRA = Resource Conservation and Recovery Act ROD = record of decision ROW = right-of-way SHPO = State Historic Preservation Office SPCC = spill prevention control and countermeasure plan USACE = U.S. Army Corps of Engineers USFWS = U.S. Fish and Wildlife Service
7-10
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
8.0
Construction of Facilities
8.1
Construction Planning Considerations
8.1.1
Remote Cabins/Residential Areas
The proposed pipeline would be constructed in very remote locations, and there would be relatively little construction near residential areas. There are scattered homesites and homesteads between MP 49 and MP 100, but the proposed pipeline ROW would not encroach on any of this private property. In developing the proposed pipeline preferred alignment Donlin Gold has avoided privately own parcels. In addition, where future land disposals were identified, efforts were made to avoid or reduce any impact on those areas. Onestone Lake Subdivision, Shell Hills Subdivision, Happy Valley Remote Recreation Cabin Staking Area, Porcupine Butte Remote Recreation Cabin Staking Area and other land status information and authorizations are shown in Appendix A in proximity to the pipeline ROW. 8.1.2
Iditarod Trail
The Iditarod Trail consists of a main trail approximately 938-miles (1,510 km) in length and numerous connecting trails. The main trail originally connected the ice-free port of Seward with the mining and trade center of Nome, an ice-locked port from October to June. The Iditarod and its connecting trails, which were and remain primarily winter trails, provided access to three major Alaska mining regions – the Cook Inlet Country, the Inland Empire (between Iditarod and Ruby), and the Seward Peninsula. The Iditarod Trail was named after the Interior gold rush settlement and mining district of the same name that was accessed by the Trail (BLM 1986 Comprehensive Management Plan [CMP]). Between 1908, when the U.S. Army’s Alaska Road Commission blazed the main trail, and the 1930’s, the Iditarod Trail served as one of three main cross-Alaska routes. The decline of mining after World War I and the introduction of the airplane for mail and freight service caused a decrease of trail use (BLM 1986 CMP). The Iditarod National Historic Trail (INHT) was established in 1978 when the National Trails System Act of 1968 was amended to include National Historic Trails. The term “Iditarod” is now principally associated with the Iditarod Sled Dog Race, which completed its first run to Nome in 1973. Other sled dog, snowmachine and human-powered endurance races also take place today on portions of the Iditarod Trail. These races include: the Northern Lights 300, Knik 200 and Junior Iditarod sled dog races; the Iron Dog snowmachine race which began in 1984, and the Iditarod Invitational whose participants include nordic skiers, mountain bikers, snowshoers and runners and is a successor race to the former Iditaski race which began in 1984 and was followed by the Iditabike and Iditasport events (BLM 1986, CMP Iditarod, and Iditarod Invitational websites). Not all of these race events occur on all, or any in some instances, of the approximately 75-mile (121 km) long section of the Iditarod Trail that is in proximity to the proposed Donlin Gold Project pipeline. The sections of the Iditarod Trail that are proximate to the proposed pipeline and which are described in Table 8-1 below typically experience their most frequent use from February until breakup. The sections of Trail described in Table 8-1 east of Rainy Pass typically experience more frequent early winter use than the section from Rainy Pass through the Alaska Range and the Dalzell Gorge to Rohn.
Donlin Gold
8-1
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Many Iditarod Trail (Trail) users, with the notable exception of the Iditarod Sled Dog Race, avoid the steep and challenging section of Trail through the Dalzell Gorge and opt for the southern connecting trail through Ptarmigan Pass. The proposed pipeline route would intermittently adjoin and, in a few locations, intersect the INHT, but only on State land between the Talachulitna River in the Shell Hills area and the South Fork of the Kuskokwim River. The proposed pipeline route would be located either in the immediate vicinity of or cross the INHT or Iditarod Race Trail, which is an established State Public Access Easement, for approximately 74.5 miles (120 km) between MP 49 and MP 143. In this area there is a section of approximately 19.5 miles (31 km) where the proposed pipeline and the Iditarod Trail deviate from each other. Between approximately MP 53 where the Trail heads north to Onestone Lake, and MP 72.5 which is approximately two miles east of Finger Lake, the proposed pipeline lies to the south of and further from the Iditarod than in the remainder of the pipeline segment lying between MP 49 and MP 143. The portion of the proposed pipeline right-of-way between MP 49 and MP 143 would be located entirely on State-owned lands. The proposed pipeline route would not cross or coincide with the INHT on federal, Native Corporation-owned or other private land. The State administers the INHT right-of-way where it does cross or coincide with State land. On portions of the state land crossed or adjoined by the proposed pipeline route there is a 400-ft (122 m) wide right-of-way for the INHT and a 400 ft (122 m) wide State Public Access Easement for the Iditarod Race Trail. For much of the approximately 74.5 miles (120 km) that the proposed pipeline is in proximity with the Iditarod Trail, the INHT and the State Public Access Easement are co-extensive. The proposed pipeline route follows or adjoins the INHT or Race Trail as shown in Table 8-1 below.
Donlin Gold
8-2
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Table 8-1: Proximity of Pipeline to Iditarod Trail
1.
2.
Approximate Pipeline Route Mile Post (MP)
Description of location in proximity to Iditarod
From MP 49
First crossing by pipeline route of Trail(s) just west of the Skwentna River crossing
To MP 53
Trailheads north to Onestone Lake and the Shell Hills and the pipeline route stays south, closer to the Skwentna River as it goes through the Shell Hills Subdivision.
From MP 72.5
A couple of miles east of Finger Lake the Trail comes in from the north and the pipeline route once again is in proximity with the Trail. There are some deviations between the two between this location and approximately MP 109 east of Rainy Pass.
To MP 109
3.
Estimated Distance
4 miles (6.4 km) of Trail/pipeline route proximity
36.5 miles (58.7 km) of general vicinity proximity
From MP 109
This location is just east of Rainy Pass and the point where the Ptarmigan Valley- Hells Gate Connecting Trail heads south and the northern or Rainy Pass- Dalzell Gorge primary Trail continues through Rainy Pass and the Dalzell to Rohn and the South Fork of the Kuskokwim. From this location through the mountains and across the South Fork of the Kuskokwim, the Trail(s) and pipeline are proximate to each other with much co-location (easement/ROW and pipeline ROW width) and crossings.
To MP 143
At this location, the pipeline and Race Trail depart from each other. The pipeline and INHT depart from each other at approximately MP 141.
Total miles
34 miles (54.7 km) of close proximity, overlap (at least with respect to easement/ROW width) or co-location with numerous crossings 74.5 miles (119.8 km) total distance where the pipeline route and Trail(s) follow or adjoin each other.
Management of the Iditarod Trail on State Land In 1987, the state entered into a Memorandum of Agreement (MOA) with the BLM concerning the INHT. In the MOA, the State agreed to manage the INHT system located on State lands “according to the laws, regulations, and policies directing each state…agency….” and “in a manner which protects and interprets historic values.” Under the MOA, the 1986 INHT CMP is the common guide to be utilized for managing the Trail. However, “Nothing in (the MOA) shall affect or interfere with the fulfillment of the obligations and rights of the parties to manage the lands and programs administered by them in accordance with their other land management responsibilities.” The State consults the CMP as a guide for managing the historic values of the INHT, to the extent agreed to in the MOA, however, the State has its own land planning and management processes that arise from State laws, regulations and policies. Donlin Gold
8-3
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Current Situation The pipeline route and the Iditarod Trail both traverse the tight topography of the Rainy Pass area between the Happy River and the Dalzell Gorge. As a result, a number of crossings of the Iditarod Trail as well as possible co-location with the proposed pipeline would be necessary. The consolidation of the sometimes-separate map depictions of the INHT and the Race Trail in Rainy Pass would eliminate the unnecessary avoidance of a trail that exists only on the map and not on the ground. Donlin Gold could request an interpretation by the Iditarod Historic Trail Alliance, at least with respect to specific areas in the Dalzell Gorge and Rainy Pass area, that the INHT and the State’s GPS-located Public Access Easement are in fact one trail on the ground. This would avoid confusion for Donlin and improve the State’s ability to manage the Trail in this area. Mitigation Measures for consideration Mitigation measures would be identified and evaluated through the permitting process in consultation with stakeholders and the appropriate agencies. Physical mitigation measures may include co-location of the proposed pipeline with the Iditarod Trail where appropriate to reduce multiple crossings of the Trail by the pipeline and thereby reduce the possibility that the pipeline right-of-way may become used as a separate trail. Appropriate signage that clearly distinguishes the Trail from the pipeline right-of-way at points where the pipeline crosses the Trail can serve to guide Trail users to stay on the Trail and off of the pipeline right-of-way where the two are not co-located. Another possibility would be to revegetate a narrow strip of the pipeline ROW where it crosses the Trail to help steer and keep Trail users on the Trail. Today, nonprofits, agencies and communities work together on trail projects to mark, brush and improve segments of the Trail. They also work together to construct and manage shelter cabins. Portions of the Iditarod Trail are used throughout the winter by communities as a transportation route. Some segments of the Trail are not marked, and are overgrown with brush and in need of realignment to improve travel safety. Providing funds for Trail work and development of community support, or undertaking Trail improvement projects associated with the portion of the Trail where it is in proximity with the pipeline may be a mitigation option. 8.1.3
Active Faults
There are two active faults that the pipeline route crosses that have been identified. These are the Denali-Farewell Fault and the Castle Mountain Fault. During any future event on these faults, permanent ground displacement from fault movement is expected to be primarily horizontal rather than vertical. After considering the information regarding these faults, the engineering design for the crossing of these two active faults would place the pipeline in the abovegrade mode. Each of the two crossing sections would be approximately 1,300 ft (.4 km) in length as shown in Appendix A. See Section 8.3.22 for additional information. 8.1.4
Wetlands
In routing the pipeline, stream crossings and wetlands areas were avoided to the extent possible. Design and construction methods were also modified to avoid or reduce wetland impacts where practical and include methods such as constructing the portions of the
Donlin Gold
8-4
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
pipeline in low-lying areas during winter months when the ground is frozen and protected by snow cover. Table 9-1 provides wetlands relative abundances. 8.1.5
Waterbodies
Construction effects on fish and fish habitat areas would be minimized by selection of stream crossing techniques that provide the appropriate level of protection for the specific habitat sensitivity. In-water work windows can be used to minimize effects on fishery resources during sensitive life-cycle stages. The use of appropriate stream bank rehabilitation and reclamation techniques and BMPs would prevent long term effects on fish and fish habitats within the project area. Pipeline crossings of watercourses would be achieved by buried methods. The method selected would depend on the season of crossing, terrain, and geotechnical and environmental conditions and based upon the presence of fish resources and engineering needs. The typicals for these methods are provided in Appendix E. Each stream crossing would be conducted in a manner and during a time period that avoids or minimizes potential fishery effects. HDD crossings were determined based on the following: 1) Is this a significant sized river that presents engineering/other challenges for trenching 2) Is there significant traffic on the river 3) What is the proposed season for construction and trenching (if not drilled), summer or winter 4) What is the technical feasibility of drilling, can it be done with current technology 5) Is this a river that has significant fish runs and or/other environmental considerations that would mandate evaluating the use of HDD 6) What is the cost of HDD at the crossing Pipeline stream crossings would be accomplished using one of the following crossing methods: HDD, open-cut dry flume, open-cut dam and pump, flowing water open-cut, nonflowing water open-cut, or small creek crossing. Typical winter crossings of water courses where there is no surface flow would be by open cut. Where feasible, the crossing would be open-cut; otherwise, the crossing would be achieved by HDD based on the above evaluation criteria. Smaller drainages would be installed by open-cut, where practical. See Sections 8.3.15 and 8.3.16 for more detailed discussion regarding water body crossings. See Appendix E for typical water crossing methods. Bore depth for HDD would be determined based on environmental and geotechnical information provided in Appendix C and Appendix D. Appendix E also provides stream crossing bridge typicals that would be employed during construction and would be determined based on the stream, presence of fish resources and engineering needs. Water withdrawal from lakes and streams for ice road construction or for hydrostatic testing would be planned and executed in accordance with the requirements of the appropriate permits and authorizations. See Section 8.2.8 for information regarding water uses and potential sources. 8.1.6
Access
Through its Public Outreach Program Donlin Gold would provide information regarding pipeline construction activities and how to coordinate access needs with construction activities. In areas where construction activities would impact existing access routes Donlin Gold would provide alternate access or allow for controlled access within or across the Donlin Gold
8-5
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
construction area. This would include ADL 222930/RST-199, the main transportation route in the region, Section 17(b) easements and other currently used trails. See Section 3.11.2, 9.1, 10.8, and 11.9.6 for more information. Alaska Department of Fish and Game (ADF&G) has indicated that it may require measures to limit public access along that portion of the ROW within the Susitna Flats State Game Refuge (SFSGR), depending on the final route design. The Iditarod Trail serves as the primary land route for access from the east side of the Alaska Range to the hunting grounds for a March bison hunt and other purposes. During construction there would temporary impacts to this access route however, these impacts would be addressed by providing alternative or controlled access along the construction ROW to minimize impacts and accommodate travelers to the extent reasonable possible. Impacts to other existing trails, section line easements and any other authorized access route should be minimal as access across the ROW would remain following construction and accommodated during the construction of the pipeline. 8.1.7
Susitna Flats State Game Refuge
As stated in Section 8.1.6, ADF&G may require measures to limit public access along that portion of the ROW within the SFSGR, depending on the final route design and location. It is necessary to route the electric transmission line to power the metering station at MP 0, the start of the pipeline. The power line then is required to go on to the compressor station. Consideration should be given to relocating the compressor station to MP 0 instead of MP 5 to reduce potential impacts on the SFRGR. 8.1.8
Construction Communications Details
Details for communications during construction would be developed at final design to ensure that all project requirements are identified and are addressed including those of Donlin Gold and contractors.
8.2
Construction Execution
Pipeline components include the pipeline, compressor station, metering stations, pig launching and receiving facilities, and temporary facilities that would be used for construction such as material sites, access roads, work pads, airfields, and construction camps. In addition, there would be construction of the electric transmission line from Beluga to the compressor station and the fiber optic cable. With the installation of the fiber optic cable would be the need to construct the repeater station. Because of the lack of developed access infrastructure and because of soft and wet soil conditions, construction would occur primarily during winter under the frozen conditions needed to support equipment along the ROW. To address the technical aspects presented by varying terrain, seasonal conditions, and overall remoteness of the proposed pipeline project, a pipeline construction sequence and schedule has been developed by construction spread. Segmentation of the proposed pipeline route has been planned with the intent of ensuring construction within a given section can be completed in a single construction season. Two main construction spreads would be used, one operating on the west side of the project from Dalzell Gorge in the Alaska Range to the mine site and one operating from Dalzell Gorge on the east to the beginning of the pipeline at the tie-in point to the BPL. The overall construction schedule would span approximately 3 years, with the first year including ROW civil work and mobilization of material and equipment. Construction practices would be tailored for the installation season. The ROW would be cleared of vegetation before grading and pipeline Donlin Gold
8-6
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
installation. Appendix F includes detail construction schedule and work season information. Appendix G identifies construction ROW modes, summarizing practices and sequencing for various seasons and terrain types. Installation of the fiber optic cable and repeater station would be coordinated and appropriately sequenced with pipeline construction activities to avoid possible pipeline installation delays. Table 8-2 shows the pipeline construction execution sequence. Winter construction is planned for the following areas: • •
MP 0 to MP 113 MP 134 to MP 245.
Summer construction is planned for the following areas: • •
MP 113 to MP 134 MP 245 to MP 313 (terminus at Donlin Gold mine).
Separate pipeline contractors under the management of a single construction management entity would execute construction on each of the two spreads. The preliminary civil infrastructure work would be conducted by independent civil contractors familiar with civil work in Alaska, under contract to the construction management entity. Facilities including the compressor station and metering facilities would be constructed by a facilities contractor, also under contract to the construction management entity. The majority of the facilities components would be prefabricated offsite and then shipped to the work site as modules and set in place. The construction management entity would be responsible for overall project execution, including: • • • • • • • •
Project schedule Project costs Compliance with design and specifications Environmental safeguards established by federal and state agencies and included in permit stipulations Project quality management/inspection Health, safety, and environmental concerns/requirements Project documentation Applicable labor and employment standards.
To ensure compliance with the standards, all contractors would be pre-qualified to verify that they have an Operations Integrity Management System (or equivalent) in place. In addition, a Quality Control Plan would be developed to identify construction related issues and verify that all work is performed in a manner to maintain the quality of the pipeline and related facilities, and to make sure all work is performed in accordance with relevant permit stipulations. 8.2.1
Overview of Construction Execution
The proposed Donlin Gold pipeline would traverse a wide variety of terrain types and climatic regions and would require careful and detailed planning of construction to meet project schedule, control costs, ensure safety of construction crews, and reduce potential environmental impacts of associated with pipeline installation. The varying geotechnical conditions, hydrologic regimes, geohazards, and habitats along the pipeline route make it essential that multiple construction scenarios be evaluated and that contingencies for changes in weather and environmental conditions (i.e., contractors must be prepared to Donlin Gold
8-7
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
address short periods of warm weather during winter months that could create problems with construction through wetlands, degrade ice roads and shorten the available work period from ice or snow roads) along the route be dealt with effectively during construction. The construction plan and schedule are based on an approximately 3-year pipeline construction period (two winter and two or three summer seasons plus a preliminary civil works program). The proposed pipeline project comprises two spreads see Table 3-2. The following briefly summarizes the scope of work for the two spreads: •
Pipeline construction would be divided into two spreads, one 128 miles (206 km) in length that would be east of Dalzell Gorge and one 185 miles (298 km) in length that would be west of Dalzell Gorge
•
Each spread would be awarded to a single pipeline contractor that would work over a period of 2 years to install the pipeline: -
Spread 1 (MP 313 – MP 128) would be further broken into four sections that would vary in length from 5 to 71 miles (8 to 114 km)
-
Spread 2 (MP 0 – MP 128) would be further broken into three sections that would vary in length from 15 to 52 miles (24 to 84 km)
-
Each section would be scheduled for installation during a single winter or summer season.
•
Construction of access roads and gravel workpads, and production of bedding and padding material would be done primarily during the season that precedes the pipeline construction season, whether winter or summer
•
Pressure testing and final reclamation of winter sections would always take place during the spring shoulder season and/or the summer after pipe lay
•
The construction season for any particular section would be chosen based on terrain, geotechnical conditions, most efficient ROW construction mode, season length, accessibility, and other factors
•
For construction, pipe would be delivered to PSYs spaced along the ROW at 5 mile (8 km) intervals, in triple random lengths (62-foot [19 m] average), except for a very small percentage left in double random joints.
Over the period of construction, the contractors would install an estimated aggregate total of more than 28,000 joints of 14-inch (356 mm) pipe, trucked to 56 intermediate PSYs along the ROW from 5 major PSYs located as follows:
•
-
Beluga Barge Landing on Cook Inlet (MP 0 – 48)
-
Oilwell Road, north of Skwentna (MP 48 – 128)
-
Donlin Gold mine site (MP 273 – 313)
-
Kuskokwim West (MP 232 – 273)
-
Kuskokwim East (MP 232 – 128).
It is anticipated that the ROW would be constructed with an estimated 59 miles (95 km) of frost-packed wetlands, 82 miles (132 km) of ice workpad, 172 miles (277 km) of graded ROW, including 13 miles (21 km) of matted winter ROW, and 5 miles (8
Donlin Gold
8-8
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
km) of matted summer wetland crossings. The valley crossings of the three George River forks would have a granular access road across them as well. Although no granular work pad is planned for the ROW, this would be reevaluated if necessary during final design. •
Chain trenchers would excavate approximately 180 miles (290 km) of trench. No rock trench was identified during the 2010 geotechnical program; therefore, it is anticipated that no trench would be drilled and shot before excavation with backhoes. In most terrain, a composite trenching crew would use both types of equipment. A provision for rock hammering bottom of trench is provided for 4,884 linear feet (1.5 km) in Section 6 in Spread 1.
•
Current estimates call for more than 55,000 cubic yards (42,051 m3) of select backfill (bedding and padding) to be produced, hauled from material sites to the ROW, and placed under (bedding) and around (padding) the pipeline in the trench in ice-rich soils. The trench spoil would be mounded over the select backfill to provide for settlement after thawing. A total of 300 miles (483 km) of pipe would be padded with material screened from the trench spoil, with trencher cuttings where appropriate or with native trench spoil. There would be sixteen 12-inch (305 mm) MLVs to install, 8inch (203 mm) valves at the inlet meter and outlet meter modules, and ancillary piping for suction/discharge branches for the single compressor station at MP 5. There would be six launchers or receivers. There would be no sales taps to install (a sales tap is a point where gas can be extracted from the pipeline before the terminus at the mine). Of the 16 inline MLVs, all are assumed to be installed as direct-bury in native soils with no foundations or special backfill requirements unless they are located in ice-rich areas requiring select backfill for the pipeline.
•
The civil work would include an estimated 811,000 yd3 (620,054 m3) of gravel that would be mined, hauled, and placed as site pads for the compressor station, PSYs, MLVs, construction campsites, and airstrips. In addition, an estimated 757,000 yd3 (578,768 m3) of gravel would be placed for access roads. These values are estimates that would be reevaluated and refined to determine more accurately the material quantities required as the project progresses.
•
Eight-300 person pipeline construction campsites would be used, four of which would have an active camp at any given time; camps would be moved with the progression of pipeline work. Six-30 person camps would be used to support three HDD drill crews and the compressor station construction, and as fly camps at barge landings and advance camps for mainline camp moves. As pipeline construction nears completion, the pipeline construction camps would be demobilized with the pipeline equipment.
•
Waterbody crossings are classified by drainage area. There are 42 drainages greater than 10 square miles (26 km2) in area, 16 drainages 5 to 10 square miles (13 to 26 km2) in area, 78 drainages 1 to 5 square miles (2.6 to 13 km2) in area, and 122 drainages less than 1 square mile (2.6 km2) in area. Drainage crossing lengths would tend to be long because of the broad, braided floodplains where scour potential exists across the entire floodplain. The group of drainages greater than 10 square miles (26 km2) in area would include 35 open cuts: one of these would be 2 miles (3.2 km) in length, three would be 1 mile (1.6 km) in length, six would be 0.5 mile (.8 km) in length, six would be 0.25 mile (.4 km) in length, and 11 would be less than 1,000 ft (.3 km) in length; the average length would be 2,200 ft (.7 km). The drainages 5 to 10 square miles would include 16 open cuts ranging from 120 to 1,818 ft (36.6 m to .6 km) in length and averaging 535 ft (.2 km) in length. The
Donlin Gold
8-9
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
drainages between 1 and 5 square miles in area would include 78 open cuts ranging from 60 to 1,240 ft (18 to 378 m) in length and averaging 261 ft (80 m) in length. Total linear feet for all open cuts would be more than 88,000 ft (27 km), or nearly 17 miles (27.4 km). •
Seven of the 42 major crossings and Dalzell Gorge (including Dalzell Creek) are proposed as HDD crossings (the Skwentna River, Happy River No. 1 at MP 85, Happy River No. 2 at MP 110, Dalzell Gorge, Kuskokwim River, East Fork of the George River, George River, and North Fork of the George River. All the other streams are planned as open-cut crossings. No aerial crossings are planned.
Stabilization, rehabilitation and reclamation activities would be initiated concurrent with construction work whenever feasible and prudent. 8.2.2
Construction Execution Sequence
The construction plan and schedule execution sequence preceded by a preliminary civil works program required during the year before start of pipe installation would include ROW clearing and grading of a travel access road within the ROW, shoofly roads where the ROW is too steep for transport of cathodic protection and pipe, preparation of compressor station site and campsites, camp construction, PSY construction, and airstrip upgrades, barge landings as well as material site development and access roads for all of these. Table 8-2 identifies the spreads and sections with lengths and planned construction season dates.
Table 8-2: Construction Execution Sequence Spread
Section
From Milepost
To Milepost
Length (Miles)
Season*
End-of-season
1
6
313.0
244.8
68.2
S0.5
October
5
244.8
187.4
57.4
W1
April
3c
133.0
128.0
5.0
S1.5
September
4
133.0
187.4
54.4
W2
April
Subtotal Spread 1 2
185 1
0.0
49.0
49.0
W1
April
3a
100.0
113.0
13.0
W1
April
3b
113.0
128.0**
15.0
S1.5
September
2
100.0
49.0
51.0
W2
April
Subtotal Spread 2
128
Total Route Length
313
* Seasons in the pipe lay construction sequence have been designated as winter (W) or summer (S), followed by a number: winters are numbered W1 and W2, and summers are numbered S0.5, S1.5, and S2.5. S1.5 falls between W1 and W2. Pipeline mobilization is scheduled for S0.5 and pipeline commissioning is scheduled for S2.5. **This section actually runs to MP 128 but this includes approximately 2 miles where the pipe would be drilled and pulled at the Dalzell Gorge location.
Donlin Gold
8-10
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Spread 2 – East of Dalzell Gorge in Rainy Pass (Cook Inlet Side) From MP 0 to MP 100 (Sections 1 and 2 of Spread 2), scheduled for winter construction, the terrain is mixed rolling, mountainous, and flat terrain, with many areas of wetlands including hilly sections that contain perched marshes. Some water sources have been identified to enable construction of ice pads during cold periods in winter. All areas of non-wetlands or difficult terrain that would usually be selected for summer work are intermittent and because of lack of continuous ROW access, cannot be constructed in the summer. About 50% of the ROW in the first 100 miles (161 km) would require grading. A significant allowance for placement of mats in these sections has been included to mitigate against insufficient ground frost depth and/or to allow for work completion in thawing conditions in case of an early spring. From MP 100 to MP 113 (Section 3a), the terrain is mostly flat or gently slopped tundra over permafrost. Construction on this section is scheduled for late winter on a snow/ice workpad, although an all-season, granular access road is planned to be constructed from the Pass Creek camp at MP 107 − MP 113, where grade work would begin. Some grading may be required in permafrost (to be determined during detailed design), along with implementation of mitigation and reclamation, measures to prevent or inhibit thaw degradation. The summer section from MP 113 to MP 126 (Section 3b of Spread 2) includes valley bottom and sidehill in narrow mountain valley and canyon terrain. Most of this section would be graded, with significant double-benching required because of the presence of extensive sideslopes. Mats would be required in valley and wetland areas. There is no planned ROW construction from MP 126 to MP 128 because of slope stability issues, and this pipe section is planned for pipe installation using HDD methods. Spread 1 – West of Dalzell Gorge in Rainy Pass (Kuskokwim Side) From MP 313 to MP 245 (Section 6 of Spread 1, as shown in Appendix F), the terrain is hilly to mountainous and would be entirely summer construction. The route follows the ridgelines and the terrain is primarily gently rolling, with some steep knobs and valleys that would require significant shoofly road construction for movement of pipe and personnel. Only valley bottoms are classified as wetlands and would require a combination of granular fill for pipe hauling and mats for pipe lay and trench excavation. Temporary construction bridges would be required at each of the three George River crossings. This would be entirely summer construction, and pipe laying would not begin until after contractor mobilization in S 0.5. From MP 245 to MP 188 (Section 5 of Spread 1, as shown in Appendix F), the terrain is variable and includes low-grade bedrock hills similar to Section 6 transected by low wetlands, three sizable rivers (the Kuskokwim River [MP 238], the Tatlawiksuk River [MP 213], and an unnamed tributary of the Tatlawiksuk River [MP 202]). The section transitions into discontinuous permafrost and kettle and kame terrain for the 20 miles (32 km) closest to Big River. The Big River crossing is also in Section 5 of Spread 1 at the match line with Section 6. Construction on this section is scheduled for winter as a combined grading section, with some mats in the first two river bottoms during frost packing and snow/ice workpad over the permafrost terrain from MP 205 to MP 188. Some grading may be required in permafrost areas, to be determined during detailed design along with mitigation and restoration measures to prevent or inhibit thaw degradation. The kettle lakes are potential water sources. When grading is being conducted in this terrain, there is a possibility of encountering massive subsurface ice lenses.
Donlin Gold
8-11
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
From MP 188 to MP 133 (Section 4 of Spread 1, as shown in Appendix F), the terrain is flat to rolling, with some kettle and karne terrain and is transected by north-flowing streams and rivers with some high and steep banks and broad, braided floodplains. Notable river crossing locations would include: • • • • • • • •
Big River (MP 188) adjacent to the Big River camp, which can be constructed as part of Section 4 or 5 Middle Fork of the Kuskokwim River (MP 180) Unnamed (MP 174) Unnamed (MP 172) Khuchaynik Creek (MP 168.5) Windy Fork (MP 166) Sheep Creek (MP 154) Post River (MP 139.5).
This section is scheduled for winter construction as a combined grading and frost pack workpad at the rivers and stream banks and in the kettle and kame terrain. However, the majority would be snow/ice workpad over the relatively flat, intermittent-permafrost terrain. Water sources for ice roads would be the scattered kettle lakes, (similar to Section 4 of Spread 1, as shown in Appendix F), although there would be few or no sources from MP 142 to MP 165, which has favorable terrain for ice roads. If water sources cannot be developed here, consideration should be given to building a granular fill workpad in the segment. This would also allow an extended season for pipe laying and access for pressure testing and reclamation. Some grading may be required in permafrost, to be determined during detailed design along with mitigation and reclamation measures to prevent or inhibit thaw degradation. From MP 133 to MP 128 (Section 3c of Spread 1, as shown in Appendix F), scheduled for summer construction, the terrain requires a major open-cut crossing of the SFK River downstream of the confluence with the Tatina River. The proposed route then follows the Tatina River’s west bank on mostly steep sidehill with heavy trees. Most of this section would be graded with significant double-benching required because of the presence of extensive sideslopes. Mats would be required in wetland areas. Permafrost would be present, and detailed design would need to review the micro-routing to assess the potential for thermal erosion, mitigation, and reclamation in this section. 8.2.3
Beluga Tie-In to BPL
The Donlin Gold proposed pipeline would tie into the BPL portion of natural gas distribution system as the source for the natural gas. The tie-in facility would consist of a concrete valve vault around the BPL that would house the hot tap and tie-in valve. There would be a small meter module and communications shelter in addition to the associated valving and emergency shutdown valve. There would also be a pig launcher at this location. All structures, with the exception of the valve vault, are planned as pile-supported structures. Also, see Section 6.9 for site plan. 8.2.4
Terminus at Mine Site
The meter station at the mine plant site would have a liquids separation vessel (used only during pigging operations), a pig receiver, a meter building, and connection to the communications system at the mine site. All structures are currently proposed as pilesupported structures. Also, see Section 6.9 and Figure 6-2 for site plan. Donlin Gold
8-12
July 2012
Plan of Development Donlin Gold Project
8.2.5
Construction of Facilities
Compressor Station
The pipeline would be designed to deliver natural gas to the proposed Donlin Gold mine project at a rate of approximately 50 mmscfd (1.4 m3) and at a minimum pressure of 550 psig. The supply pressure from the tie-in at the BPL ranges from 720 to 800 psig. As the gas flows through the pipeline, the pressure would decrease because of friction. To meet the delivery requirements of 550 psig, one compressor station would be required to boost the gas pressure for delivery to the proposed mine site. Based on current design, a single compressor station would provide sufficient compression for the gas throughput. The compressor station would be located in the Matanuska-Susitna Borough at pipeline MP 5. This location was selected to avoid placing the compressor inside the Susitna Flats State Wildlife Refuge. Compressor station components would be modularized to minimize onsite construction and commissioning work in remote locations. To accommodate environmental conditions, the units would be placed inside building modules. Figure 6-1 is a compressor site location map that shows the powerline alignment. The compressor station would have two main components: electrically powered natural gas compression machines and after-coolers provided to reduce gas temperature following the compression process. Additional equipment necessary to support the compression process include systems to prevent overpressure and to provide rate, temperature and pressure control, trouble alarms, ESD, and fire and gas detection systems. The compressor station preliminary electrical design and building siting was developed using the area classification requirements in National Fire Protection Association (NFPA) 70. All other locations along the pipeline requiring electrical power or controls were assumed to be classified areas. The final design of the pipeline and facilities would have complete area classification drawings, and the materials to be procured and installed in the classified areas would meet the requirements of NFPA 70. Three compressors of approximately 1,000 hp each would be used to deliver natural gas at different rates and pressures, depending on the fuel consumption demands of the mine project. Only two compressors would be required in order to meet current design flow conditions; the third would function as a backup compressor. The foundations for the compressor station modules would be steel piles having a minimum diameter of 12 inches (30.48 cm) and a minimum set depth of 25 ft (8 m). The compressor station location has no permafrost. The workpad would be gravel, have a thickness of approximately 3 ft (.91 m) and be approximately 200 x 300 ft (61 x 91 m) in plan dimension. The site would include a gravel helipad complete with an aviation-quality windsock. The area would measure approximately 80 x 80 ft (24 x 24 m). The compression station facility site would be approximately 2-acres (.81 ha) and would be unmanned, with fully automated equipment operated by a remote-control system. A 10-foot-high (3 m) chain link fence would surround the site for security. Figure 8-1 shows the compressor station site plan. A permanent road to the site does not exist and no permanent access road would be built to the site; access would be by helicopter or snowmachine, depending on season and weather conditions. No provisions would be made for short- or long-term human occupancy at the site. All compression equipment would be powered by electricity. There would be no engines or open flame at the site. Electrical power to the site would be provided by a 25-kilovolt (kV), cross-country power line originating at the 385-megawatt CEA and power plant at Beluga. Because of the reliability of the electrical supply utility, there would be no need for an emergency power generator. However, emergency lighting would be supplied from a dedicated lighting panel located in the power distribution center (PDC) module. Emergency lighting throughout the pad would be connected directly to individual feeder circuits. In addition to the emergency lighting panel, emergency power would be supplied to the programmable logic center control cabinet and communications rack located in the PDC Donlin Gold
8-13
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
module. The uninterruptible power supply (UPS) (dual rectifiers, battery plant and inverter system) would have a load of approximately 10 kilowatts and would be sized to supply power to the emergency loads for 24 hours. The fire and gas system are intended to be powered by the UPS system at the compressor station. The fiber-optic communications cable would be routed to the compressor station along with the buried pipeline and from there continue to the mine site with the pipeline. The pipeline would be designed to deliver natural gas to the proposed Donlin Gold mine project at a rate of approximately 50 mmscfd (1.4 m3) and at a minimum pressure of 550 psig. The supply pressure from the tie-in at the BPL ranges from 720 to 800 psig. As the gas flows through the pipeline, the pressure would decrease because of friction. To meet the delivery requirements of 550 psig, it would be necessary to boost the pressure. The design provides for continued service at the required delivery rates and pressures with one compressor or one air cooler out of service. Therefore, the design provides at least one spare compressor and one spare air cooler. To meet those criteria and to provide a broad range of flow rate control, the design includes three compressor modules, each rated at 25 mmscfd (.7 m3) and 1,480 psig at 100 F (37.7°C). The system is designed to deliver up to 49 mmscfd (1.38 m3) at 1,400-psig discharge pressure with two compressors online and the third as a standby unit. Table 8-3 shows the operating design factors.
Table 8-3: Operating Design Factors Parameter Supply Temperature Supply Pressure Discharge Pressure Minimum Destination Pressure Flow Rate
Operating
Design
20°F to 50°F
-20°F to 100°F
720 to 800 psig
1,480 psig
1,250 psig
1,480 psig
550 psig
550 psig
47 mmscfd
Up to 73.1 mmscfd
a
The gas would be at soil temperature at burial depth. °F = degrees Fahrenheit mmscfd = million standard cubic feet per day psig = pounds per square inch gauge
The gas compressor(s) would be powered by electric motors that would be fitted with variable frequency drives (VFDs). VFDs provide the ability to adjust the speed of motors and compressors, which correspondingly adjusts the flow rate of the natural gas. Under normal operations, the gas would be piped directly to the compressor modules. The gas would then enter a suction scrubber that would capture any free liquids. Those liquids would be reinjected into the pipeline for handling at the terminus. The gas would then enter the compressors and flow to filter coalescers for removal of lubrication oil that has been carried over from the compressor cylinders. From there, the gas would be processed through an air-cooled heat exchanger (fin-fan) to reduce the gas temperature to within 20 degrees of ambient, but not less than 40°F (4.4 C). The gas would then enter the pipeline and be transported to the mine site.
Donlin Gold
8-14
July 2012
UNITS AND WEIGHTS
80' x100' HELIPAD STATION BLOWDOWN 30' x12' PIG LAUNCHER: 2500 LBS. PIPING 1000 LBS. LAUNCHER DOOR PIG RECEIVER: 2500 LBS. PIPING 1000 LBS. RECEIVER DOOR MONORAIL (3) 26' x 50' x 15' TALL MODULES: 23,500 LBS. COMPRESSOR EACH (3) 8' x 6' FIN FAN AFTER COOLERS: 7350 LBS. EACH 20' x 50' PDC BUILDING: 500 LB. AIR HANDLING UNIT, 2 EA. UNIT HEATERS @ 32 LBS. 3 EA. 1,000 HP VFD'S, MOTOR CONTROL CENTER, MAIN DISTRIBUTION PANEL, CONTROL/COMM EQUIPMENT AND 1 EACH 5400 LB. 500KVA TRANSFORMER, 3 EACH 7900 LB. 1000KVA TRANSFORMER, & 1 EACH 1680 LB. MEDIUM VOLTAGE SWITCH
FIBER OPTIC LINE
SITE INFORMATION FENCE LINE: 240'-0" x 272'-0" AREA: APPROX. 1.5 ACRES
NOTES:
SCALE:
1. NO PROVISIONS MADE FOR TEMPORARY OR PERMANENT HUMAN OCCUPANCY.
NA
COMPRESSOR STATION SITE PLAN
FIGURE:
8-1
DONLIN GOLD PROJECT DG: PER0285.mxd, 08/30/11, R01
Plan of Development Donlin Gold Project
Construction of Facilities
The compressor station would be designed, installed, operated, and maintained in accordance with the following standards: •
49 CFR 192 – Transportation of Natural Gas and Other Gas by Pipeline
•
ASME B31.8 – Gas Transmission and Distribution Piping Systems
•
All codes and standards referenced and incorporated herein by 49 CFR 192 and ASME B31.8
•
In accordance with 49 CFR 192, all pipe located with the compressor station would have a design factor of 0.50.
Architectural •
AAC
•
2009 International Fire Code
•
2009 International Building Code (IBC)
•
2009 International Mechanical Code (IMC)
•
NFPA 72, National Fire Alarm Code, 2010
•
NFPA 70; National Electrical Code (NEC) 2011.
Civil/Structural •
IBC 2009
•
American Institute of Steel Construction Manual of Steel Construction, 13th edition
•
American Society of Civil Engineers 7-05, Minimum Design Loads for Buildings and Other Structures
•
American Welding Society, Structural Welding Code D1.1, 2008
•
OSHA Title 29, Parts 1910 and 1926
•
American Society of Testing and Materials
•
American National Standards Institute
•
ASME, B.30 series
•
API Recommended Practice 2214, Spark Ignition Properties of Hand Tools, Section 2.2.
Mechanical and Piping •
49 CFR 192 – Transportation of Natural and Other Gas by Pipeline: Minimum Federal Safety Standards
•
Material Specification Standard SP-44 – Steel Pipeline Flanges
•
API 1104 – Welding Pipelines and Related Facilities
•
API 618 – Reciprocating Compressors for Petroleum, Chemical, and Gas Industry Services
Donlin Gold
8-16
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
•
API 670 – Machinery Protection Systems
•
ASME B31.8 – Gas Transmission and Distribution Piping Systems
•
ASME B16.5 – Pipe Flanges and Flanged Fittings
•
ASME Boiler and Pressure Vessel Code, Section VIII, Division 1 – Rules for the Construction of Pressure Vessels
•
ASME Boiler and Pressure Vessel Code, Section VIII, Division 2 – Rules for the Construction of Pressure Vessels – Alternative Rules
•
ASME Boiler and Pressure Vessel Code, Section IX – Welding and Brazing Qualifications.
IMC 2006 •
ASTM A106/A106M-04b – Standard Specification For Seamless Carbon Steel Pipe for High-Temperature Service
•
API Specification 6D – Pipeline Valves
•
SPC-402896-PL-02 – fusion-bonded epoxy (FBE) Coating Application
•
SPC-402896-PL-03 – abrasion-resistant overcoat (ARO) Coating Application
•
SPC-402896-PL-04 – Pipe Handling
•
SPC-402896-PL-07 – Block Valves
•
SPC-402896-PL-08 – Pipeline Construction
•
SPC-402896-PL-09 – Non Destructive Testing
•
DCA – Piping Material Class Specification for 600 ANSI
•
API 520 Recommended Practices, Part 1, Sizing Selection and Installation of Pressure Relieving Devices. 8th Edition. December 2008
•
API 520 Recommended Practices, Part 2, Sizing Selection and Installation of Pressure Relieving Devices. 5th Edition. August 2003
•
ANSI/API Standard 521, Pressure-relieving and Depressuring Systems. 5th Edition, January 2007 and Addendum. May 2008
•
ASTM Section VIII, Division 1. Boiler and Pressure Vessel Code, 2010 Edition, UG 125-140.
Electrical •
NFPA 70: 2011 NEC
•
Institute of Electrical and Electronics Engineers, Standard C2, National Electric Safety Code
•
NFPA 497: Recommended Practice for the Classification of Flammable Liquids, Gases, or Vapors and of Hazardous (Classified) Locations for Electrical Installations in Chemical Process Areas
•
NFPA 780: Installation of Lightning Protection Systems, latest edition
Donlin Gold
8-17
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
•
National Electrical Manufacturers Association
•
Underwriters Laboratories (UL). All equipment would bear the UL label, or equivalent from a nationally recognized testing agency
•
Illuminating Engineering Society of North America Lighting Handbook, latest edition
•
Electronic Industries Alliance/Telecommunications Industry Association 568B Commercial Telecommunications Wiring Standard
•
ANSI
•
National Electrical Contractors Association. 1-2006 Good Workmanship in Electrical Construction.
8.2.6
Electric Transmission Line
To meet the operational needs of the metering station and the compressor station of an estimated 2.5 MW of electrical power, a MV aboveground transmission line would be constructed to connect electrical power between the Beluga Power Plant substation and the Compressor Station at MP 5, a distance of approximately 14 miles (23 km). The transmission line would be primary metered by CEA at the substation. From the primary metering point, CEA would install a buried cable to exit the substation property and interface with the owner-constructed overhead MV transmission line. The CEA cable would terminate at the top of the MV transmission line riser pole. The routing of the MV transmission line would follow the CEA high-voltage transmission line corridor to the BPL tap point within a 30 ft (9 m) easement that Donlin Gold would obtain. At the tap point, which is the start of the Donlin Gold pipeline, a 15-kilovolt-ampere transformer would be mounted to the transmission line to supply utilization-level voltage to a gasmetering module. The transmission line would continue following the pipeline ROW between the pipeline tie-in point and the compressor station located at MP 5. The MV transmission line would approach the compressor station pad along the pipeline right-of-way, just south of the pad. Near the pad edge, the overhead transmission line would terminate with a riser pole. From the riser pole, the incoming power from Beluga power plant would be direct buried in the pad to the PDC module. Figure 6-1 and Appendix A shows the location and land status for the electric transmission line. A portion of the proposed transmission line to power the compressor station crosses private surface estate land owned by CIRI within the Kenai Peninsula Borough. CIRI’s surface estate ownership is in that portion of T13N R10W SM, where the proposed transmission line is located. 8.2.7
Fiber Optic Communication Line
The fiber optic cable would extend from the GCI communications module at Beluga power plant to the metering station at the pipeline tie-in to the BPL as shown in Figure 8-2 and Appendix A. From the metering station the fiber optic cable would be installed in the buried mode with the pipeline to the compressor station and then, except at the two fault crossings where the pipeline and cable would be above ground, on to the mine site. Details regarding installation of the fiber optic cable would be done during final design.
Donlin Gold
8-18
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
The fiber optic cable communications would be used for communication purposes including transmitting data to and from the compressor station, the meter station located at the tie-in point to the BPL, the GCI communication module at Beluga power plant, the meter station at the pipeline terminus, and the control center. 8.2.8
Ancillary Construction Support Facilities
The project would construct a variety of ancillary facilities to support construction of the pipeline. Locations of these ancillary sites are shown on the project strip maps in Appendix A. Several types of ancillary facilities that are currently being used by Donlin Gold or have been used by third parties in the past are planned for project use. Such facilities include airstrips at Beluga, Puntilla, Farewell, and the mine site; campsites at Beluga, Farewell, and the mine site; various yards for pipe or equipment storage at Beluga, Oilwell Road, Puntilla, Farewell, and the mine site; and ports with ancillary storage yards at the Port of Anchorage, the Port of Bethel, Beluga Landing, or Jungjuk Port, and others. Use of any of these sites would require negotiations and legal leases or use agreements with the owners/operators. Facilities requiring upgrading or new construction would be constructed before initiation of pipeline construction and include:
Donlin Gold
8-19
July 2012
MP-7
Fiber Optic Cable Would Continue With Pipeline To Mine Site in Buried Mode
MP-6 MP-5
Donlin Gold Gas Pipeline Compressor Station/ Electric Transmission Line Point of Termination
TL-13 MP-4 TL-12 TL-11
MP-3 MP-2
TL-10
Fiber Optic Cable in Buried Mode from MP-0 at Metering Station Tie-in with BPL to Compression Station
MP-1 TL-9 TL-8
MP-0
Donlin Gold Gas Pipeline Point of Beginning
TL-7
B
ga R el u
iver
TL-6 TL-5 TL-4
Medium Voltage Above Ground Electric Transmission Line Approximately 14 Miles
TL-3 TL-2 TL-1 TL-0
T
Fiber Optic Cable Above Ground to Metering Station Tie-in with BPL at MP-0
O O C
Potential Beluga Construction-Phase Camp Location
K
I
N
L
E
Beluga Power Plant Substation/ Electric Transmission Line & Fiber Optic Cable Point of Beginning
Storage Yard
Proposed Transmission Line (Mileposts "TL")
Proposed Natural Gas Pipeline Alignment
Beluga Power Plant
Proposed Natural Gas Pipeline Alignment (Mileposts "MP")
Proposed Electric Transmission Line
Compressor Station Storage Yard
Potential Camp Location (Location to be determined)
SCALE:
0
1
0
1.5
2 3
4 mi 6 km Seward Meridian, UTM Zone 5, NAD83
ELECTRIC TRANSMISSION LINE AND FIBER OPTIC CABLE
FIGURE:
8-2
DONLIN GOLD PROJECT DG: PER0273.mxd, 07/12/12, R05
Plan of Development Donlin Gold Project
Construction of Facilities
Airstrips Ten airstrips would be used to support pipeline construction logistics; six of these would be new airstrips that would be constructed to support the pipeline project. Each new airstrip would be located to provide efficient logistical support, minimize environmental impacts, and minimize interference with pipeline construction activities. Specific siting of the airstrips was conducted to reduce cut-and-fill required to create the runway surface. Existing airstrips would be used at four locations, although some would require upgrading to meet the project's needs. Those public airstrips would require authorization or concurrence from USDOT and Federal Aviation Administration (FAA). Also, authorization for the existing airstrips from the land owner would need to be verified. The ten airstrips to be used would be instrumental in supporting mobilization of equipment and materials for project construction and to support camp operations during construction periods. Each location would require storage for air operations and staging for pipeline construction. Actual facilities and area requirements would be determined during final design. Appendix A shows location and land statutus for airstrips and Appendix F also shows the airstrips to be used: Airport
Spread
Upgrade Required
Beluga
1
Private airport; good as is
Skwentna*
2
New construction; grade, cut, and fill
Puntilla
2
Public airstrip; upgrade runway surface
Pass Creek
2
New construction; granular fill
Tatina
1
New construction; grade cut and fill
Farewell
2
Existing airstrip; upgrade and runway surface
Big River
1
New construction; grade and granular fill
Kusko East
1
New construction; grade, cut and fill
Kusko West
1
New construction; grade, cut and fill
Donlin Mine Site
2
Existing airstrip; use as is
*Use of the existing airstrip in Skwentna was evaluated and determined to not meet Donlin Gold’s needs. Pipe storage yards/material stockpiling sites Main pipe storage/equipment staging yards are planned for Bethel, Beluga, the mine site, and near the barge landing sites on the Kuskokwim River. These yards would serve as the primary accumulation points for pipe materials for sorting and staging to the 56 PSY spaced at intervals of approximately 5 miles (8 km) along the ROW to allow for hauling and staging at the PSYs along the ROW during the civil clearing and access season, which would occur generally 1 year before the pipe laying season. The majority of the heavy equipment required for project construction would also be staged from these locations. Most of the pipeline material and equipment would come through the staging yards at Beluga and Bethel. There would be 31 PSYs located in Spread 1 and 25 located in Spread 2. A complete list of proposed PSYs and their location, including the amount of pipe for each yard is shown in Table 8-4 and are also showed on the project alignment sheets. In addition to pipe, PSYs would store mainline valves, induction bends, Donlin Gold
8-21
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
and other materials. Additionally, fiber optic cable would be stored at these sites as well. It is important that the sequencing and installation of the pipeline and fiber optic cable be coordinated as they would be buried in the same trench and trench backfilling must not be delayed. Equipment staging sites would be located close to the kickoff point for each section. These sites would be needed to receive and store equipment during periods of no construction between seasons. Staging areas would be cleared and graded before use. On completion, the site would be reclaimed. The staging area may be a gravel pad if the natural soil is not suitable. In such an instance, the gravel would be left in place and the site reclaimed upon completion.
Donlin Gold
8-22
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Table 8-4: Pipe Storage Yards TAG
NAME Beluga Yard
Starting MP
Ending MP
Number of Miles
Number of Bundles
Number of Joints
Calc Length
Act Length
Planned Pipe Source
0.0
5.0
5.0
29
464
345
N/A
Beluga
PSY-01
MP5
5.0
10.4
5.4
32
512
373
500
Beluga
PSY-02
MP10.4
10.4
13.0
2.6
15
240
179
300
Beluga
PSY-03
MP13
13.0
20.0
7.0
41
656
483
600
Beluga
PSY-04
MP20
20.0
26.0
6.0
35
560
414
600
Beluga
PSY-05
MP26
26.0
30.6
4.6
27
432
317
500
Beluga
PSY-06
MP30.6
30.6
35.6
5.0
29
464
345
500
Beluga
PSY-07
MP35.6
35.6
40.2
4.6
27
432
317
500
Beluga
PSY-08
MP40.2
40.2
44.4
4.2
25
400
290
500
Oil Well Road
PSY-09
MP44.4
44.4
48.2
3.8
22
352
262
500
Oil Well Road
PSY-10
MP49.1
48.2
52.3
4.1
24
384
283
500
Oil Well Road
PSY-11
MP52.3
52.3
57.8
5.5
32
512
380
600
Oil Well Road
PSY-12
MP57.8
57.8
61.3
3.5
21
336
242
500
Oil Well Road
PSY-13
MP61.3
61.3
66.6
5.3
31
496
366
500
Oil Well Road
PSY-14
MP66.6
66.6
69.0
2.4
14
224
166
300
Oil Well Road
PSY-15
MP69
69.0
73.8
4.8
28
448
331
500
Oil Well Road
PSY-16
MP73.3
73.8
77.4
3.6
21
336
248
500
Oil Well Road
PSY-17
MP77.4
77.4
84.6
7.2
42
672
497
600
Oil Well Road
PSY-18
MP85.1
84.6
89.1
4.5
26
416
311
500
Oil Well Road
PSY-19
MP89.1
89.1
94.9
5.8
34
544
400
500
Oil Well Road
PSY-20
MP94.9
94.9
99.3
4.4
26
416
304
500
Oil Well Road
PSY-21
MP99.3
99.3
107.4
8.1
47
752
559
700
Oil Well Road
PSY-22
MP107.4
107.4
112.4
5.0
29
464
345
500
Oil Well Road
PSY-23
MP112.4
112.4
117.2
4.8
28
448
331
500
Oil Well Road
PSY-24
MP117.2
117.2
124.5
7.3
42
672
504
550
Oil Well Road
PSY-25
MP124.5
124.5
128.0
3.5
21
336
242
500
Oil Well Road
Donlin Gold
8-23
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Table 8-4 (Continued): Pipe Storage Yards TAG
NAME
Starting MP
Ending MP
Number of Miles
Number of Bundles
Number of Joints
Calc Length
Act Length
Planned Pipe Source
PSY-26
MP131.8
128.0
131.8
3.8
22
352
262
500
Oil Well Road
PSY-27
MP138.0
131.8
138.0
6.2
36
576
428
500
Kusko East
PSY-28
MP145.3
138.0
145.3
7.3
42
672
504
600
Kusko East
PSY-29
MP151.0
145.3
151.0
5.7
33
528
393
500
Kusko East
PSY-30
MP156.0
151.0
156.0
5.0
29
464
345
500
Kusko East
PSY-31
MP160.6
156.0
160.6
4.6
27
432
317
500
Kusko East
PSY-32
MP164.6
160.6
165.5
4.9
29
464
338
500
Kusko East
PSY-33
MP171.0
165.5
171.0
5.5
32
512
380
500
Kusko East
PSY-34
MP176.1
171.0
176.1
5.1
30
480
352
500
Kusko East
PSY-35
MP179.5
176.1
179.5
3.4
20
320
235
500
Kusko East
PSY-36
MP188.1
179.5
188.1
8.6
50
800
593
650
Kusko East
PSY-37
MP196.0
188.1
196.0
7.9
46
736
545
650
Kusko East
PSY-38
MP 202.0
196.0
202.0
6.0
35
560
414
600
Kusko East
PSY-39
MP208.0
202.0
208.0
6.0
35
560
414
600
Kusko East
PSY-40
MP213.1
208.0
213.1
5.1
30
480
352
500
Kusko East
PSY-41
MP218.4
213.1
218.4
5.3
31
496
366
500
Kusko East
PSY-42
MP222.6
218.4
222.6
4.2
25
400
290
500
Kusko East
PSY-43
MP229.5
222.6
229.5
6.9
40
640
476
600
Kusko East
Kusko East
229.5
239.1
9.6
56
896
662
N/A
Kusko East
PSY-44
MP244.0
239.1
244.0
4.9
29
464
338
500
Kusko West
PSY-45
MP248.5
244.0
248.5
4.5
26
416
311
500
Kusko West
PSY-46
MP252.9
248.5
252.9
4.4
26
416
304
500
Kusko West
PSY-47
MP258.8
252.9
258.8
5.9
34
544
407
600
Kusko West
PSY-48
MP265.5
258.8
265.5
6.7
39
624
462
600
Donlin Mine
PSY-49
MP 270.1
265.5
270.1
4.6
27
432
317
500
Donlin Mine
PSY-50
MP 276.4
270.1
274.6
4.5
26
416
311
500
Donlin Mine
Donlin Gold
8-24
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Table 8-4 (Continued): Pipe Storage Yards TAG
NAME
Starting MP
Ending MP
Number of Miles
Number of Bundles
Number of Joints
Calc Length
Act Length
Planned Pipe Source
PSY-51
MP279.4
274.6
279.4
4.8
28
448
331
500
Donlin Mine
PSY-52
MP282.4
279.4
282.4
3.0
18
288
207
400
Donlin Mine
PSY-53
MP287.0
282.4
287.0
4.6
27
432
317
500
Donlin Mine
PSY-54
MP293.4
287.0
293.4
6.4
37
592
442
600
Donlin Mine
PSY-55
MP300.5
293.4
300.5
7.1
41
656
490
600
Donlin Mine
PSY-56
MP306.0
300.5
306.0
5.5
32
512
380
500
Donlin Mine
Donlin
306.0
314.3
8.3
48
768
573
N/A
Donlin Mine
1834
29344
Notes: This yard is not laid out; it is assumed there is adequate room at Beluga. Start pipe haul from Beluga All PSY = 100 wide minimum
Donlin Gold
8-25
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Material sites (gravel pits) Material sites would be needed to provide granular fill material for access and shoofly roads, airfields, camp pads, PSYs, the compressor station and meter pads, and granular workpads (if they are used). Material sites would also be the source and location for processing plants for crushed and/or screened material for select backfill, bedding, padding, surface courses, cobbles, rock riprap, and other types of granular material. All material used would be analyzed to be sure that it was appropriate to be used in contact with the pipe. Approximately 63 potential material sites (shown in Table 8-5) to supply granular materials have been identified along the proposed ROW, based on terrain type and geology. These sites would be developed as required to supply the needed granular materials for this project. Tables 8-6 and 8-7 show pipeline shoofly and access roads and airfields estimated material needs. The location and number of material sites that also may require a processing plant/crusher would be determined during final design. Material sites are located to accommodate construction material needs, where appropriate materials can be found, and to minimize haul distances. The frequency and size of material sites would be determined by the need for particular amounts of material along the pipeline route. Variables that would determine the need for a material site include ROW mode, construction season, distance to water for ice pad in winter, location of camps, PSYs, haul distances, suitability of mined material, environmental issues, and availability of candidate sites. Material sites would be located and sized to avoid sensitive areas such as wetlands, cultural sites, sensitive species habitat, or other environmentally sensitive areas. All activities at material sites would be conducted in accordance with required permits and authorizations and associated stipulations for protection of resources such as air and water quality. -
Current estimates call for more than 55,000 cubic yards (42,050 m3) of select backfill (bedding and padding) to be produced, hauled from material sites to the ROW, and placed under (bedding) and around (padding) the pipeline in the trench in ice-rich soils. The trench spoil would be mounded over the select backfill to provide for settlement after thawing. A total of 300 miles (483 km) of pipe would be padded with material screened from the trench spoil, with trencher cuttings where appropriate or with native trench spoil, i.e., no imported gravel needed. There would be sixteen 14inch (356 mm) MLVs to install, 8-inch (203 cm) valves at the inlet meter and outlet meter modules, and ancillary piping for suction/discharge branches for the single compressor station at MP 5. There would be three launchers and three receivers. Of the sixteen inline MLVs, all are assumed to be installed as direct-bury in native soils with no foundations or special backfill requirements unless they are located in icerich areas requiring select backfill for the pipeline.
The civil work would include an estimated 811,000 yd3 (620,054 m3) of gravel that would be mined, hauled, and placed as site pads for the compressor station, PSYs, MLVs, construction campsites, and airstrips. In addition, an estimated 757,000 yd3 (587,768 m3) of gravel would be placed for access roads. These values are estimates that would be reevaluated and refined to determine more accurately the material quantities required as the project progresses.
Donlin Gold
8-26
July 25, 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Table 8-5: Potential Material Sites Material Site
Road Sta. (ft)
Mile Post
Area (ha)
Material Type
Designation
Terrain
West of Beluga River
Distance from Alignment
Notes from 3/23 RECON
Centroid (UTM Z5) Volume
Photo Northing
4.0 mi SW
Easting
MS-00
000+00
0.0
5.3763
Gravel
6791112
608664
MS-01
269+28
5.1
1.4386
Gravel
1743
6802893
609678
MS-02
443+52
8.4
2.5000
Bedrock
1734
6807928
611018
MS-03
786+72
14.9
2.2500
Bedrock
6817770
612807
MS-04
971+52
18.4
1.9143
Bedrock
1746
6823243
613548
MS-05
1283+04
24.3
7.2800
Gravel
1747
6831919
609728
MS-06
1620+96
30.7
1.9200
Gravel
6840933
604844
MS-07
1821+60
34.5
1.5121
Gravel
1748
6845247
600853
MS-08
2127+84
40.3
8.7055
Gravel
1609-1613, 1754-1755
6851359
594091
MS-09
2280+96
43.2
7.0000
Gravel
1757
6854816
591319
MS-10
2571+36
48.7
4.2277
Gravel
1615-1619, 1760
6861720
586668
MS-11
2851+20
54.0
14.6738
1765-1766
6862970
578162
Upper Sucker Creek cUS1)
Skwentna River
Gravel (alluvial)
2500 ft S
MS-12
3511+20
66.5
1.4400
Gravel
6872901
561724
MS-13
4408+80
83.5
6.0000
Gravel (alluvial)
Happy River
6872269
535497
MS-14
4551+36
86.2
2.1000
Gravel (alluvial)
Helicopter Lake
6874107
531651
MS-15
5248+32
99.4
15.9998
Gravel (esker)
Puntilla (airstrip & laydown)
6883375
515324
MS-16
5338+08
101.1
3.7019
Gravel (alluvial)
Indian Creek
6885610
513940
MS-17
5728+80
108.5
9.0000
Bedrock (ridge)
Airfield quarry
6891648
505622
MS-18
6045+60
114.5
3.7960
Gravel (alluvial)
6892989
496469
MS-19
6251+52
118.4
1.0026
Gravel (alluvial)
Top Pass
6898777
495526
MS-20
6526+08
123.6
11.6880
Gravel (alluvial)
Dalzell Creek (camp/laydown airstrip)
6901178
488944
Donlin Gold
3000 ft S
1807
8-27
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Table 8-5 (Continued): Potential Material Sites Material Site
Road Sta. (ft)
Mile Post
Area (ha)
Material Type
Designation
Terrain
Distance from Alignment
Notes from 3/23 RECON
Volume
Photo
Centroid (UTM Z5)
MS-21A
6763+68
128.1
2.6219
Gravel (alluvial)
Tatina River
6907844
486120
MS-21B
6779+52
128.4
1.9200
Gravel (alluvial)
Tatina River
6907599
485591
MS-22
6953+76
131.7
4.6493
Gravel (alluvial)
Tatina River
6908113
480304
MS-23
7333+92
138.9
5.7982
Gravel (alluvial)
Post River
6917710
474846
MS-24
7492+32
141.9
4.5727
Gravel (alluvial)
South Fork tributary (kSFT4)
6922057
473099
MS-25
7840+80
148.5
6.0000
Gravel (alluvial)
1912
6927496
465328
MS-26
7946+40
150.5
1.3500
Gravel (alluvial)
(fault zone)
1913
6928971
462824
MS-27
8125+92
153.9
4.4321
Gravel
Sheep Creek
1914-1915
6927492
457577
MS-28
8342+40
158.0
3.0000
Gravel
Sheep Creek tributary (kSHT2)
6925391
451295
MS-29
8527+20
161.5
3.0000
Gravel
Sheep Creek tributary (kSHT5)
6923002
446170
1200 ft S
MS-30
8743+68
165.6
5.6513
Gravel
Windy Fork (kWI1)
6921228
440129
MS-31
8880+96
168.2
3.0400
Gravel
Khuchaynik (kKH1)
6920530
435992
MS-32
9060+48
171.6
4.5000
Gravel
Middle Fork tributary (kMFT2)
6918525
430892
MS-33
9192+48
174.1
2.4194
Gravel
Middle Fork tributary (kMFT3)
6917092
427101
MS-34
9308+64
176.3
2.0287
Gravel
Middle Fork tributary (kMFT5)
6915000
424216
MS-35
9519+84
180.3
5.4413
Gravel
Middle Fork Kuskokwim (kMF1)
6911092
419125
MS-36
9620+16
182.2
2.8084
Gravel
Middle Fork tributary (kMFT8)
6909464
416496
MS-37
9926+40
188.0
9.0000
Gravel
Big River airstrip
6909824
404297
MS-38
9942+24
188.3
2.1130
Gravel
Big River (East)
6905106
407950
MS-39
9989+76
189.2
3.0000
Gravel
Big River (West)
6904496
406757
Donlin Gold
3.5 mi NW
8-28
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Table 8-5 (Continued): Potential Material Sites Material Site
Road Sta. (ft)
Mile Post
Area (ha)
Material Type
Designation
Terrain
Distance from Alignment
MS-40
10317+12
195.4
5.6782
Gravel
edge moraine
MS-41
10676+16
202.2
1.5000
Gravel
Tatlawiksuk Tributary (kTLT2)
500 ft S 1300 ft S
MS-42
11119+68
210.6
16.0000
Bedrock
Ridge quarry
MS-43
11309+76
214.2
3.1725
Bedrock
Tatlawiksuk River (kTL1)
MS-44
11616+00
220.0
17.6000
Bedrock
Quarry
MS-45
11790+24
223.3
8.7642
Bedrock
MS-46
12001+44
227.3
7.9412
Bedrock
MS-47
12107+04
229.3
7.5000
Bedrock
Quarry
MS-48
12265+44
232.3
25.0000
Bedrock
Quarry & pipe/laydown
MS-49
12276+00
232.5
6.0000
Bedrock
Airstrip quarry
MS-50
12513+60
237.0
7.5000
Bedrock
Kuskokwim-1 Quarry
MS-51
12540+00
237.5
5.4000
Gravel
Kuskokwim Barge Landing
MS-52
12587+52
238.4
19.6519
Bedrock & Gravel
Kuskokwim Quarry & Camp
MS-53
12708+96
240.7
7.0000
Bedrock
Quarry on Camp Road
MS-54
12909+60
244.5
13.3000
Bedrock
Camp & Material Site
Notes from 3/23 RECON
Volume
Photo
Centroid (UTM Z5)
6902798
397576
6898306
387844
6892790
375595
6892299
369846
6892031
360627
Quarry
6892959
355468
Quarry
6892119
349068
6892269
345911
6891804
341109
2400 ft S
1978
1973
5000 ft S
4000 ft S
2800 ft S
6890147
340257
1967
6891160
333824
1968
6890062
333162
1970
6890566
331428
6888665
328199
6888480
322586
MS-55
13310+88
252.1
1.5000
Bedrock
Quarry on ridge
6887912
312118
MS-56
13421+76
254.2
1.3200
Bedrock
Quarry on ridge
6886689
309202
MS-57
13812+48
261.6
1.5000
Bedrock
Quarry on ridge
6885814
298231
MS-58
14081+76
266.7
1.5000
Bedrock
Quarry on ridge
6884006
291251
MS-59
14731+20
279.0
4.2750
Bedrock
Quarry on ridge east of East Fork George River
6887968
275926
MS-60
14889+60
282.0
4.8000
Bedrock
Quarry on ridge west of East Fork George River
6889728
271398
MS-61
15195+84
287.8
3.0827
Bedrock
East side George River
6893304
263309
MS-62
15375+36
291.2
6.7500
Bedrock
Ridge west of George River
6893989
257939
Donlin Gold
8-29
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Table 8-5 (Continued): Potential Material Sites Material Site MS-63
Road Sta. (ft) 15644+64
Donlin Gold
Mile Post 296.3
Area (ha)
4.0500
Material Type Bedrock
Designation
Terrain
Ridge west of West Fork George River
Distance from Alignment
Notes from 3/23 RECON
Volume
Photo
Centroid (UTM Z5)
6892292
8-30
250525
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Table 8-6: Pipeline Shoofly and Access Roads Material Needs All Season Access Roads Earthwork Summary Approximate Mile Post (MP)
Description
Cut (yd3)
Cut (m3)
Fill (yd3)
Fill (m3)
Select Material (yd3)
Select Material (m3)
49.26
Main Camp Access
4,559
3,486
538
411
3,208
2,453
83.80
Happy Alt. 1 Shoofly
333,776
255,190
294,916
225,480
20,340
15,551
128.03
Tatina Camp Access
34,485
26,641
2,495
1,908
3,257
2,490
154.12
Farewell Upgrade
25,505
19,500
1,870
1,430
16,247
12,422
188.27
Big River Strip Access
33,227
25,404
25,859
19,771
15,185
11,610
238.5
Kusko West Camp and Strip Access
885,203
676,807
297,981
227,823
47,817
36,559
Table 8-7: Pipeline Airfields Material Needs
Airfields Earthwork Summary Approximate Mile Post (MP)
Description
Cut (yd3)
Cut (m3)
Fill (yd3)
Fill (m3)
Select Material (yd3)
Select Material (m3)
52.00
Airfield
293
224
203,711
155,748
34,229
26,170
106.00
Airfield
263
201
322,590
246,638
35,390
27,058
132.00
Airfield
12,557
9,601
60,405
46,183
38,760
29,634
189.00
Airfield
21,584
16,502
96,927
74,106
41,230
31,576
232.00
Airfield
1,491,520
1,140,349
3,058
2,338
37,644
28,781
244.00
Airfield
138,275
105,719
27,195
20,792
34,183
26,135
Material site boundaries would be shaped in a manner as to blend with surrounding natural land patterns. Regardless of the layout of material sites, primary emphasis would be placed on prevention of soil erosion and damage to any vegetation. All material sites would be reclaimed consistent with approved reclamation plans for each site. Final volumes of these granular materials and specific location of material sites and development plans for these sites would be part of the final pipeline design. Material sale applications would be separate from the ROW applications. Construction Camps Of the eight construction campsite locations, four main construction campsite locations in addition to the existing campsite at the mine are planned to be in use at any one time along the proposed ROW to support project construction. These camps will be located at various locations along the ROW and would be supplemented by fly-in camp sites along the ROW to reduce travel time for construction crews to commute to their work locations as the project progresses. The main campsites would be cleared gravel pads ranging from approximately 4 to 10 acres (1.6 to 4 ha) in area (not including the airstrip or additional contractor laydown space), with self-contained, soft- or hard-sided structures with full subsistence capability for Donlin Gold
8-31
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
the work crews. These camps would be erected and operated by independent camp suppliers. The following facilities would be included in the 300-person construction camps: • • • • • • • • • •
• • • • • • • •
Dormitory units Arctic corridor First Aid Unit Recreation Center Office Modules Kitchen-diner Laundry facility Warehouse/storage (augmented by pipeline contractor as needed) Contractor shops (augmented by pipeline contractor as needed) Fuel storage and distribution system - Diesel/fuel oil storage tanks (for camp consumption) - Diesel storage tanks (by pipeline contractor for construction equipment) - Gasoline storage tanks (by pipeline contractor for construction equipment) - Propane storage tanks (for camp kitchen cooking stoves and ovens) - Propane storage tanks (by pipeline contractor for preheat) - Fencing (if needed) Water storage Water treatment Sewage treatment Lift stations Generators Parking for equipment and vehicles Communications tower (by Donlin Gold or others) Water well.
The 30-person camp would have the same types of facilities, but everything would be sized for a maximum of 15-two-person sleeper units, or a total of 30 workers, plus eight beds for maintenance, catering, and housekeeping. Each 300-person camp would be capable of supporting a workforce of 250, plus maintenance, catering and housekeeping personnel. In addition to serving the subsistence needs of the workforce, the camps would provide administrative space and communication facilities for the construction management and inspection teams to conduct their activities. Each main camp would house an emergency medical technician who would be onsite 24 hours a day, 7 days a week, because there would be no emergency medical facilities along the pipeline route except at Beluga and the mine site. The sites would be completely fenced for security, and a security guard would be on shift 24 hours a day, 7 days a week, to monitor labor traffic in and out of the campsite to ensure that no worker is unaccounted for following the workday. -
Donlin Gold
Eight 300-person pipeline construction campsites would be used, four of which would have an active camp at any given time; camps would be moved with the progression of pipeline work. Four 30-person camps would be used to support HDD drill crews and for use as fly camps to set up the mainline camps, plus one 60- person camp for compressor station construction. As pipeline construction nears completion, the pipeline construction camps would be demobilized with the pipeline equipment. 8-32
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
-
Spread 1 would have five mainline campsites (two of which would be used at any given time), plus sites for HDD camps, barge landing camps, and fly camps for advance setup of mainline camps. The existing Farewell airstrip would be used for logistics during W2 (winter year 2) Section 4 construction and may have its own fly camp for the duration of work in that area. The spacing of sites would average 60 miles (96.6 km), and the average maximum travel distance from camp to work would be about 30 miles (48 km). The longest travel distance would be 35 miles (56 km) between the mine site or Kusko West and the East Fork of the George River. Spread 1 campsites would include besides use of the Donlin Gold mine site, Farewell.
-
Spread 2 would have three campsites (two of which would be used at any given time). The spacing of sites would average 62 miles (99.8 km), and the average maximum travel distance would be about 31 miles (49.9 km). The longest travel distance would be the distance between Skwentna and Happy River No. 136 miles (57.9 km), and Puntilla or Happy River No. 1.
Camp water would generally be supplied from nearby wells or clean water sources. The water would be either piped or trucked to the water treatment facility. The facility would treat the raw water to State of Alaska standards for potable water. The camp would have storage capacity for several days water requirement. There would also be firewater storage for each camp. Projected camp size and the applicable fire code would determine the volume of firewater. Camp water would be returned to the same watershed after treatment. There would not be a significant net loss of water. Sewage and gray water generated by each camp would be treated as required and disposed of in accordance with regulations and requirements. All waste would be handled according to applicable regulations. Hazardous waste would be hauled to disposal sites approved for hazardous waste disposal. Waste oil from equipment maintenance would be burned in purpose-built waste oil unit heaters. In general, the importation of grease, solvents, oils, coolants, hydraulic fluids, and other liquids or chemicals would be controlled to limit the types and amounts of waste generated. Medical hazardous waste would be handled by the appropriate medical personnel and disposed of in approved sites. The fuel storage facility for pipeline equipment at each camp would be provided by and installed by the pipeline contractor. Depending on the individual contractor’s equipment fleet, the fuel storage facility would hold all diesel or diesel and gasoline. The fuel storage facility would consist of a bermed and lined (primary and secondary containment) area with a capacity exceeding the tankage within the berm, as required by regulations. As an alternative, the tankage can also be double-walled, and just the piping can be in the bermed and lined area. The fuel storage within the berm would be either modular, double-walled tanks or fuel bladders. Primary fuel storage would be at each camp airstrip because the fuel would be mostly flown in. Fuel would be dispensed to the contractor’s fuel trucks for fueling of construction equipment on the ROW or at camp. Pumps at the fuel storage facility can fuel light vehicles and/or onhighway trucks. There would also be a propane storage facility so that contractors can refuel their preheat equipment. Appropriate spill containment kits and procedures would be in place to address fueling and spills while fueling. The pipeline contractor would use the equipment shop and warehouse buildings. Because of the remoteness of the project location, the large amount of equipment, and the winter construction seasons, the contractor would require the weather protection afforded by buildings to perform equipment and vehicle maintenance and overhauls. The size and number of buildings required would vary, depending on season of work and size of the spread. Donlin Gold
8-33
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Camp Installation Construction and installation of the four mainline camps must begin during S0.5 (see explanation of winter [W] or summer [S] designation in Table 8-1) in Spread 1, Section 6, at the mine site; in Spread 2, Section 1, at Beluga; and during W0 at Kusko West and at Skwentna. The civil work at campsites, water wells, and underground utilities must be installed early during S0.5 to allow camp module installation to be well underway and be ahead of winter. The selection of the civil, well drilling, and other contractors must also begin well in advance of S0.5. During W0 and early S0.5, preparation of four more campsites must be started. See Figure 8-3 for general camp configuration. Campsite preparation would include clearing, gravel fill, installation of berms and liners for fuel storage, and, possibly, placement of suitable flooring for shop and warehouse buildings. Water wells would have to be drilled and proven for each campsite. Camp Moves Camps would be relocated at the end of a construction season and moved ahead in preparation for future construction. All such camp moves would occur within each spread. There would be no camp moves from one spread to another. Other than normal movement of sleeper units, the four planned camp core moves are: •
From the mine site to Kusko East during mid-W1, approximately January 1, as the work moves from Section 6 to Section 5 in Spread 1
•
From Kusko West to Big River during W1 in mid-February
•
From Kusko East to Tatina during late W1 or early S1.5
•
From Beluga to Pass Creek during late W1, when the spread moves from Skwentna to Puntilla.
Camp moves are summarized in Appendix F and Figure 8-4.
Donlin Gold
8-34
July 2012
SCALE:
NA
GENERAL CONSTRUCTION CAMP CONFIGURATION
FIGURE:
8-3
DONLIN GOLD PROJECT DG: PER-317.mxd, 07/12/12, R00
Plan of Development Donlin Gold Project
Construction of Facilities
Camp Medical and Fire Protection There would be 24-hour coverage for medical and fire emergencies. The pipeline contractor and each subcontractor would have a project-specific HSE plan. Each plan would be submitted for approval by construction management before the start of fieldwork. A camp fire response & prevention plan would be determined concurrent with final design and procurement. Compressor Station Camp The compressor station camp would be set up and used on the compressor station site only for the onsite compressor station construction. Workers constructing the power transmission line to the compressor station may be housed at the Beluga mainline camp or at another commercial camp in the Beluga area. Delivery of Pipe to Support Construction The following facilities would be used for delivery of pipe from which distribution would be made to the PSYs along ROW. These include the following major pipe staging areas and access roads. Barge Landing at Jungjuk Port A barge landing at Jungjuk Port near Crooked Creek on the Kuskokwim River would be developed to support MP 273 to 313. (Note: There would be no road built to the Birch Creek Crossing to the mine site.) Barge Landing at Beluga Some improvements to the existing barge landing at Beluga would be required, along with associated construction of laydown yards and a campsite. The Beluga Barge Landing would support MP 0-48. Port of Bethel Improvements to the Port of Bethel are needed to expand laydown yards for staging pipe and contractor equipment for barging up the Kuskokwim River. Barge landing on east side of Kuskokwim River A barge landing would be constructed at pipeline crossing and would be used for unloading and staging pipe and contractor equipment for construction work on Sections 5, 4, and 3c in Spread 1 (MP 232-128). Barge landing on west side of Kuskokwim River A barge landing would be constructed at pipeline crossing and would be used for unloading and staging pipe and contractor equipment for construction work on Section 6 of Spread 1 (MP 232-273).
Donlin Gold
8-37
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Oilwell Road In addition to the staging facilities a 45 mile (72 km) winter access road for logistical support would be constructed from Oilwell Road to Skwentna for contractor use and pipe movement to Sections 2, 3a and 3b (approximately MP 48-128) in Spread 2. Roads Graded or granular fill access roads would be needed for all-season use; ice access roads would be for winter use only. Ice access roads would be used primarily to reach water sources that cannot be reached from the ROW and for access to the ROW for ice or snow workpad construction. In general, the use of ice access roads is being minimized in favor of granular access roads because access roads connecting campsites and airstrips would be used during summer for the pressure test and reclamation program. Table 8-8: Access Road Identifications Mile Post
Length (miles)
Width (feet)
0.00
10.2
Existing
Existing access from Beluga airstrip to MP 0
7.39
0.13
24
Shoofly
9.73
0.64
24
Shoofly
12.38
0.85
24
Shoofly
42.21
0.33
24
Shoofly
47.97
0.01
24
HDD fly camp access
49.26
0.54
24
Main camp access
49.59
8.1
24
49.90
0.51
24
Main camp access
52.19
0.22
24
Airstrip Access
53.20
0.06
24
Airstrip Access
61.03
0.14
24
Alternative 1 Shoofly
61.06
0.1
24
Alternative 2 Shoofly
65.52
0.14
24
Shoofly
66.18
0.14
24
Alternative 1 Shoofly, part 1
66.20
0.33
24
Alternative 2 Shoofly
66.32
0.09
24
Alternative 1 Shoofly, part 2
68.63
0.19
24
Shoofly
76.84
0.42
24
Shoofly
83.80
3.38
24
Alternative 1 Shoofly
83.80
1.33
24
Alternative 2 Shoofly
86.34
0.26
24
Shoofly
99.33
0.1
24
PSY access
Donlin Gold
Status
Description
Skwentna winter access
8-38
(may need upgrading for pipeline use)
(Deleted based on southern access to Skwentna from Oil Well Road)
(preferred)
(preferred)
(preferred)
(most probable)
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Table 8-8 (Continued): Access Road Identifications Mile Post
Length (miles)
Width (feet)
Description
99.58
0.03
24
PSY access
100.68
0.25
24
Shoofly
100.99
0.08
24
Shoofly
101.06
0.23
24
Shoofly
107.25
0.53
24
Pass Creek Camp & Strip access
128.03
0.03
24
128.31
0.28
24
Tatina Camp to Tatina River
131.90
0.15
24
Rohn Camp & Strip access
147.37
0.12
24
Shoofly
154.12
2.97
24
Upgrade existing trail to Farewell Strip
154.22
0.02
24
Farewell Camp access
188.27
1.76
24
Big River Strip access
188.35
0.03
24
Big River Camp access
232.52
1.12
24
Kusko East Camp & Strip access
237.00
1.47
24
Kusko East Barge site & Laydown Yard access
238.40
0.13
24
Kusko West Barge site & Laydown Yard access
238.50
6
24
Kusko West Camp & Strip access shoofly from Kusko
243.94
0.05
24
Kusko West Strip access
244.20
0.03
24
Kusko West Camp access
246.29
1.50
24
Shoofly
247.75
0.16
24
Shoofly
248.22
0.25
24
Shoofly
248.65
0.44
24
Shoofly
249.13
0.42
24
Shoofly
256.50
2.92
24
Shoofly
260.59
2.27
24
Shoofly
266.82
0.54
24
Shoofly
270.49
0.76
24
Shoofly
271.88
0.73
24
Shoofly
279.22
1.1
24
Shoofly
282.85
0.47
24
Shoofly
Donlin Gold
Tatina Camp access
8-39
Status
(needs realignment based on new HDD entry point)
(approximate mileage)-needs design
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Table 8-8 (Continued): Access Road Identifications Mile Post
Length (miles)
Width (feet)
Description
283.83
3.16
24
Shoofly
305.26
0.47
24
Shoofly
307.92
0.5
24
Shoofly
310.58
1.9
24
Shoofly - ANACONDA
Status
Water Use and Potential Sources Water would be required during construction for camp use which would be supplied from wells or clean water sources and would be piped or trucked to a water treatment facility. There would also be firewater storage at each camp. Water would also be needed for other potential uses including ice road construction, dust control, reclamation and hydrostatic testing. Water withdrawal from lakes and streams would be planned and executed in accordance with the requirements of the appropriate permits and authorizations. It is understood that water removal from fish overwintering areas during winter months may not be permittable. Temporary water use authorizations would be applied for by either the appropriate contractor or Donlin Gold. Table 8-9 identifies potential water sources and use during construction.
Donlin Gold
8-40
July 2012
Plan of Development Donlin Gold Project
Construction of Facilities
Table 8-9: Potential Water Sources and Use Water Extraction Site
Road Sta. (ft)
Mile Post
Stream Crossing Label
Waterbody Type
Ponds Only Flow
Designation Area (ac)
Volume
Terrain
Distance from Alignment
Open Water in Winter?
At road bridge - good water
WES-001
000+00
0.0
River
Theodore River bridge
WES-002
179+52
3.4
River
Theodore River
1600 ft W
WES-003
422+40
8.0
Pond (x2)
Two ponds
500 ft W
WES-004
564+96
10.7
cLET1
Tributary
Lewis River trib 1
WES-005
665+28
12.6
cLET2
Tributary