Mar 6, 2018 - Design Elements: ⢠No sidewalk on west side of the street. ⢠Some motorists don't yield to people cros
NEWPORT/119th DESIGN BOARD A
TRAFFIC SAFETY IMPROVEMENT PROJECT
SE 56th St/119th Ave SE Intersection Enhancements: To improve safety for people walking and biking
N
Sidewalk
(see Design Board B)
Coal Creek Natural Area
New Crosswalks Planned Neighborhood Bikeway Route
48 ST
Future Planned Bike Lanes
SE
119 AVE
SE
SE 56th St Existing Intersection (Looking North)
SE 52 ST
E SE
E SE
118 AV
PL
117 AV
SE
54
Future Planned Bike Lanes Parking
11 9 t h A v e S E
Curb Extensions and Ramps on all Corners
Newport Heights Elementary School
Newport Hills Swim & Tennis Club
SE 56 ST
Example of Enhanced Crosswalks
Focus Area
Proposed Intersection Improvements
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
Community Concerns • Drivers roll through the stop signs • Safety of pedestrians in crosswalk
Proposed Concept • Narrow the roadway with curb extensions to slow traffic and reinforce desired travel speeds • Shorter street crossings with improved crosswalk striping for people walking • Striping for future planned bike lanes and Neighborhood Bikeway route on SE 56th/117th Ave SE
Design Elements: • Curb, sidewalk, and curb ramps • New marked crosswalks with opportunity for creative/artistic crosswalks for increased visibility • Striping for bike facilities • Landscape plantings where feasible • Opportunity for raised intersection
Construction Cost: $75,000 - $250,000 Curb extensions
Full Intersection Reconstruction
3.06.2018
NEWPORT/119th
119th Ave SE sidewalk:
To improve safety for pedestrians between Newport Heights Elementary School and SE 56th St
N
SE 54th
Pl
DESIGN BOARD B
TRAFFIC SAFETY IMPROVEMENT PROJECT
Bus Stop
Curb Extensions and Ramps
Designated Walkway (see Design Board C)
Mailbox Cluster
Driveway Approach
Sidewalk
Existing corridor (Looking North)
E S e v A h t 9 1 1
Existing Road Striping to Remain
Coal Creek Natural Area
SE 56th St Intersection
SE 52 ST Newport Heights Elementary School
118 AV E SE
E SE
• Curb, sidewalk, and curb ramps • Restoration along private property for sidewalk installation
SE
PL
• Provide new sidewalk for improved access along 119th Ave SE to school • Curb extensions at SE 54th Pl for traffic calming and provide a connection to designated walkway on SE 54th Pl
Design Elements:
54
• No sidewalk on west side of the street • Some motorists don’t yield to people crossing at the mid-block crosswalk at school
Proposed Concept
117 AV
Community Concerns
119 AVE
SE
48
SE
ST
(see Design Board A)
Newport Hills Swim & Tennis Club
SE 56 ST
Construction Cost: $425,000-$475,000 Focus Area
Proposed Improvements Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
3.06.2018
NEWPORT/119th DESIGN BOARD C
TRAFFIC SAFETY IMPROVEMENT PROJECT
Designated Walkway:
To improve walkability near school parking lot exit Community Concerns
N
School Parking Lot exit
• People feel vulnerable walking without sidewalks • Irregular parking patterns reduce visibility and safety during school pick-up/drop-off
Sidewalk along School Property (parking on both sides of street)
Designated Walkway
SE
(no parking on this side of the street)
Pl th 54
Designated Walkway
Example of designated walkway
Coal Creek Natural Area
Ave SE
(no parking on this side of the street)
E S e v A 119th
Proposed Concept • Provide designated walkways along SE 54th Pl (north side) and 118th Ave SE (west side) to improve safety for people walking • Remove parking on walkway side of the street • Connect walkways to existing and/or planned sidewalks
48
SE
• Concrete sidewalk at back of existing curb along school property • Creative/artistic pavement markings combined with walkway delineator along SE 54th Pl and 118th Ave SE • Ramps to connect to existing sidewalks
ST
118th
Design Elements:
SE
119th Ave SE Sidewalk
(see Design Board B)
119 AVE
See Street Cross Section
SE 52 ST
PL
118 AV
SE
54
117 AV
Newport Heights Elementary School
E SE
5 4t h P l E SE
SE
Newport Hills Swim & Tennis Club
SE 56 ST
Street Cross Section
Focus Area Proposed Improvements
Construction Cost: Designated Walkways: (900’ length) $65,000 - $80,000 Concrete Sidewalk Along School: (160’ length, behind existing curb) $35,000 - $40,0000
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
3.06.2018
NEWPORT/119th DESIGN BOARD D
TRAFFIC SAFETY IMPROVEMENT PROJECT
Enhanced crosswalk at SE 52nd St and 119th Ave SE: Improve crosswalk for students going to/from school
N New Enhanced Crosswalk
New Sidewalk
Existing Mid-block Crosswalk
E S ve A th
Example of Enhanced Crosswalks
9 1 1
(see Design Board B)
Example modified raised crosswalk on SE 22nd St, east of 148th Ave SE
Community Concerns • Poor compliance with crosswalks near school on 119th Ave SE (drivers don’t consistently stop for students)
Proposed Concept • Enhance crosswalk at SE 52nd to improve safety and compliance of drivers stopping for pedestrians • Coordinate with school for preferred crossing guard locations with new enhanced crosswalk at SE 52nd St and new sidewalk on west side of 119th Ave SE
Potential Design Strategies: • Enhanced crosswalk with creative/artistic pavement markings for increased visibility • Modified raised crosswalk • Advance pavement markings (e.g. zigzag markings) for increased awareness
Construction Cost: $10,000 - $75,000
Example pavement marking on SR 9 in Arlington, WA
3.06.2018
123 PL SE
NEWPORT/119th
TRAFFIC SAFETY IMPROVEMENT PROJECT
Newport Heights Elementary school zone signs: DESIGN BOARD E Improve safety New location of school zone beacons combined with radar sign on same post
N
12 7
SE 5 E
1 ST
120 AVE S
SE 51 ST SE 52 ST
L
SE 118 AVE
54 P
117 AV E
SE
SE
Existing school zone flashing SE beacons 5
123 AVE SE
116 PL S
E
Newport Heights Elementary School
4
ST
School Zone Sign with Flashing Beacon
SE Community Concerns5 3 125 AVE SE
E S E V A 119TH
Existing radar sign to be relocated
SE
SE 52 ST
Existing school zone beacons to be relocated
PL
SE 50 ST
• Travel speeds near andSaround T school • Safety of pedestrians in the crosswalks SE(also see Design Board D 5for enhanced 4 crosswalk at SE 52nd S St)
Example school zone beacon/radar sign combination
Proposed Concept • Relocate southbound school zone flashing beacons and radar sign to the north for better visibility • Combine on same post
T
Design Elements: • Flashing beacons • Radar speed sign
SE 56 ST
Construction Cost: $15,000 - $20,000
3.06.2018
NEWPORT/119th DESIGN BOARD F
TRAFFIC SAFETY IMPROVEMENT PROJECT
Speed cushions:
To reduce excessive speeding along 119th Ave SE
N
Speed Cushion Extruded Curb Example speed cushion on NE 30th St near 164th Ave NE
E S e v A 119th
Advance Warning Sign
E SE
118 AV
Construction Cost: $25,000-$75,000
Newport Heights Elementary School
SE
PL
• Survey adjacent households to determine if support exists to install speed cushions as a pilot along 119th Ave SE • Speed cushion design will aim to reduce excessive speeding without impeding emergency access • Cannot be installed on grades over 8%
SE 52 ST
54
Proposed Concept
• City split speed cushion with associated signing and pavement markings • Precast concrete mountable curb • Additional radar sign for southbound traffic
E SE
• Excessive speeding observed along corridor and documented in speed studies (50% of motorists recorded driving over 29mph)
Design Elements:
117 AV
Community Concerns
119 AVE
SE
48
SE
ST
Coal Creek Natural Area
Newport Hills Swim & Tennis Club
SE 56 ST
Potential Area for Speed Cushions When Feasible
Focus Area Potential Area for Southbound Radar Sign
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
3.06.2018
NEWPORT/119th
TRAFFIC SAFETY IMPROVEMENT PROJECT
SE 48th St/119th Ave SE Intersection:
DESIGN BOARD G
Potential future bike improvements
N Coal Creek Natural Area
Worn Crosswalks 48 ST
E S e v A h t 9 11
Safety Enhancements
No curb on west side of road Existing intersection (looking north)
119 AVE
Se 48th St intersection
SE
SE
E SE
117 AV
118 AV
t hS
SE
PL
48t
Newport Heights Elementary School
54 Newport Hills Swim & Tennis Club
SE 56 ST
SE
Planned Neighborhood Bikeway route
E SE
SE 52 ST
Example raised intersection
Focus Area Proposed Intersection Improvements Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
Community Concerns • Drivers roll through the stop signs • Stop sign visibility • Safety of pedestrians in the crosswalk
Proposed Concept • Enhance the intersection to improve safety and compliance with stop signs • Possible improvements include a raised intersection or traffic circle
Potential Design Strategies: • Reconstruct with landscaped traffic circle or as enhanced intersection to reduce speeds and improve accessibility • Construct curb on west side of street to narrow road and reinforce desired travel speeds • Raise pedestrian awareness with creative/ artistic crosswalks
Construction Cost: TBD
(based on preferred design strategy)
Example traffic circle 3.06.2018