May 30, 2017 - Preliminary data gathering (GIS, other) ... Columbus, Ohio 43215. Phone: 614.228. ... Transportation Syst
Progress Update 2018 Rickenbacker Area Study
Community Advisory Committee May 30, 2017
Transportation Advisory Committee May 31, 2017
UPDATE OVERVIEW
• Working Group Updates Housing Transportation
Water/Energy/Broadband Economic Development • Upcoming Tasks
• Project Administration
HOUSING WORKING GROUP UPDATE Meetings held on Nov. 28th, Feb. 9th & May 9th Current Group Tasks: • Input into Draft Existing Conditions Document • Housing & Transportation Affordability Index • School Districts Analysis
TRANSPORTATION WORKING GROUP UPDATE Meetings held on Dec. 2th, Feb. 7th & May 15th Current Group Tasks: • Review of forecast volumes • Begin transportation projects identification
• Develop project evaluation criteria
WATER/ENERGY/BROADBAND WORKING GROUP UPDATE Meetings held on Nov. 29th & Feb. 16th Current Group Tasks: • Preliminary data gathering (GIS, other) • Developing existing conditions
• Water & sewer agreements inventory
ECONOMIC DEVELOPMENT WORKING GROUP UPDATE Meetings held on Dec. 2th & May 15th Current Group Tasks: • Information gathering - incentives - case studies - stakeholder interviews • Infrastructure connection - broadband needs - water & sewer needs • Future visioning
UPCOMING TASKS
•
Energy/Broadband/Utilities Working Group Meetings
•
Economic Development Working Group Stakeholder Interviews
•
Study area population trends
•
Developer Interviews
•
GREAT Riders Survey
•
Placemaking Element
PROJECT ADMINISTRATION
•
Communications Strategy
•
Area Study Funders meetings
•
Future Meetings – Scheduling
STUDY TIMELINE 2016 2017 2018 A M J J A S O N D J F M A M J J A S O N D J F M A M J LCK-MP Task I - Advisory Committee Meetings Task II - Land Use Task III (Chapters) Chapter 1 - Transportation Chapter 2 - Housing Chapter 3 - Water Chapter 4 - Data Chapter 5 - Energy Chapter 6 - Economic Development Chapter 7 - Placemaking Task V - Implementation Plan Task VI - Final Report
We are here
Dina Lopez Principal Planner Transportation Systems & Funding
[email protected]
Maria Schaper Senior Planner Transportation Systems & Funding
[email protected] Mid-Ohio Regional Planning Commission 111 Liberty Street, Suite 100 Columbus, Ohio 43215