Institutions, interactions and insulation: The Home Insulation Program Australia 2009-2010

Garth Britton Paper submitted to the panel “Balancing entrepreneurship and risk management in decision making on policy initiatives: dealing with uncertainties” at 16th Annual Conference of the International Research Society for Public Management IRSPM XVI, 11-13 April 2012 Rome, Italy                   Please address correspondence to:  Dr. Garth Britton  P.O. Box 3495  Manuka, ACT, 2603  Australia  Phone: +61 2 6161 0556  E‐mail: [email protected]     

Introduction This paper is the third in a series looking at how large public programs fail, particularly where, in  retrospect, it seems obvious that failure could have been avoided. The first paper in the series  (Britton, 2010) suggested that risks that should have been clearly visible to all the major actors had  been ‘externalised’ and gone unmanaged because of the way the various institutions related, or  failed to relate, and allocated roles between themselves. The second paper (Britton, 2011) suggested  that one of the mechanisms by which public service organisations might mitigate risk could be to  engage in their own right in activity that is in some respects creative or entrepreneurial, rather than  acting solely or reactively at the bidding of their elected political masters. This paper aims to extend  and refine the ideas presented in the two previous papers by comparing and contrasting the earlier  work with another case of what is perceived as a major failure in government policy.  The Home Insulation Program (HIP) was announced on 3 February 2009, as a major element of the  AUD 3.9 billion Energy Efficient Homes Package (EEHP), which itself formed part of the AUD 42  billion Nation Building and Jobs Plan, a sweeping array of initiatives designed to stimulate the  economy in the aftermath of the financial crisis of late 2008 (Auditor‐General, 2010, pp. 19‐20).  Originally budgeted at AUD 2.87 billion, later reduced to AUD 2.45 billion (p. 93), the program was to  insulate 2.2 million homes1 (Hawke, 2010, p. vii). over 2 ½ years (Auditor‐General, 2010, p. 20). As  well as creating jobs and encouraging small business activity, the HIP was intended to improve the  energy efficiency of homes, so reducing greenhouse gas emissions and the need for energy  investment. Only a few weeks after the main phase of its implementation began in July 2009,  significant concerns began to emerge about fraud and then safety in the delivery of the program. By  the time the HIP was closed down on 19 February 20102, it had been linked with 4 fatalities and 87  house fires (Australian Financial Review 23/2/10), a number which was to continue to grow in  following months. At the date of termination, AUD 1.55 billion3 had been spent to insulate 1.2  million homes (Auditor‐General, 2010, pp. 45‐46); however, the costs of remediation programs and  industry support for companies affected by the closure of the program, estimated at AUD 784  million (p. 93) were expected to consume almost all available remaining funds, even though no more  insulation was to be installed under the program. The failure of the program led directly to the  demotion of the responsible Minister and contributed to a disastrous decline in credibility and  popularity of the then Prime Minister in the first half of an election year (Macintosh, Wilkinson, &  Denniss, 2010, p. 211). It may be, in this context, that, along with several other policy reversals and  perceived mishandled responses, that it also contributed to the Prime Minister Rudd’s spectacular  sacking by his own party just prior to the election and his replacement by the current Prime  Minister, Julia Gillard. 

                                                            

1

 There was also a companion program, the Low Emissions Plan for Renters, intended to encourage the  installation of insulation in 500,000 rental homes. This plan was dropped in August 2009, due to low uptake.  2  The HIP was terminated on 19 February 2010, but was to have been replaced from 1 July 2010 by the  Renewable Energy Bonus Scheme (REBS). Following the Review of the Administration of the Home Insulation  Program by Dr Allan Hawke, received in April 2010, the government decided not to proceed with REBS.  3  AUD 103 million in the first Phase, which ran to 30 June 2009, and AUD 1.45 billion in Phase 2, which ran until  termination.  

1   

The data on which this paper is based encompasses all press articles retrieved from the Factiva  database mentioning the program4 that were published between the announcement of HIP in  February 2009 and June 2010, 4 ½ months after its closure (some 3000 pages of articles5), as well as  the Review of the Administration of the Home Insulation Program commissioned by the government  from Dr. Allan Hawke and delivered on 2 April 2010 (Hawke, 2010) and the Audit Report No 12 2010‐ 11 on the program submitted to Parliament by the Australian National Audit Office (ANAO) on 15  October (Auditor‐General, 2010)6. It does not cover the progress of the remediation programs which  followed the HIP. Data was analysed using a grounded theory methodology with the assistance of  the qualitative data analysis package Atlas.ti 6.2.  

The Home Insulation Program The HIP was launched with high ambition and a measure of confidence in difficult times. In the  words of the responsible Minister, rock‐star turned politician Peter Garrett in February 2009, ‘This is  the most exciting, ambitious energy efficiency program that we will ever see and it’s open for  business (Lateline 23/3/11).’ Australia had hitherto had one of the lowest rates of household  insulation in the developed world ‐ 40% of households either did not have or didn’t know if they had  insulation (Hawke, 2010, p. 23). With immediate effect, the HIP offered rebates of up to AUD 1600  per home to homeowner‐occupiers who installed insulation in homes built prior to 2003 and which  did not have insulation above negligible effectiveness (Auditor‐General, 2010, p. 45)7. The level of  the rebate had been set to completely cover the cost of ceiling insulation in most homes (Hawke,  2010, p. xi). Hence, the HIP effectively offered insulation ‘free’ for homeowners.  Such a possibility had been mooted for some time. On the one hand, there were significant  environmental attractions to increasing household energy efficiency, at a time when concerns about  the effects of greenhouse gas emissions on climate were at their peak. Although then Prime Minister  Kevin Rudd’s rather florid description of climate change as ‘the greatest moral challenge of our time’  had been the subject of some ridicule, very few on either side of politics were willing to deny its  importance either as a political issue as a policy challenge. There were also economic attractions –  rising energy consumption and a pressing need for investment in energy production and distribution  was putting pressure on energy prices and affecting both household and government budgets. The  concept of a subsidy on insulation had been discussed in the last year of the government of previous  Prime Minister John Howard, at the instigation of the then Environment Minister, Malcolm Turnbull  (Sydney Morning Herald 23/5/09). Although it had not been pursued, reportedly having been rather  contemptuously dismissed as too expensive by then Treasurer Peter Costello, the ascension of                                                               4

 As represented by the results of a search using the term “‘home insulation’ OR ‘energy efficient home*’”   It is to be noted that not all these articles were specifically about the HIP – particularly towards the end they  were chiefly references to the program in other contexts, always as an example of failure or incompetence.  The coverage of the program continued for some months along these lines, as well as reporting on the  progress of the remediation programs, but added little new information.  6  There was also a Senate Inquiry held into the EEHP tabled on 15 July 2010. However, this has not been used  since it was widely reported in the press and appears to contain mainly repetitions of points which were  already being made by others. Furthermore, its recommendations were more to do with remediation activities  rather than addressing the aim of this paper, to develop a deeper understanding of what occurred in the  program itself.  7  Homes built after this date were not eligible, since building code modifications in 2003 meant that they no  longer met the negligible effectiveness requirement (Canberra Times 14/2/10).  5

2   

Turnbull to leadership of the Liberal Party after the defeat of the Howard government, and his  staunch support for action on climate change, meant that the principle of an insulation subsidy was  not politically much contested. In fact, in a speech on 24 January 2009, only a few days before the  HIP was announced, Turnbull had described insulation as ‘probably the single biggest opportunity for  straightforward, easy gains in energy efficiency (Sydney Morning Herald, 23/5/09).’  The concept of subsidising the installation of insulation in the existing housing stock had been  examined by the Department of the Environment, Water, Heritage and the Arts (DEWHA) in the  months following the election of the Rudd government in late 2007 and proposed for budget  consideration in 2008, but rejected as being too expensive (Sydney Morning Herald, 23/5/2009).  Nevertheless, the idea suddenly gained in attractiveness when two powerful central agencies, the  Department of Prime Minister and Cabinet (PM&C) and Treasury8 were searching for ways to quickly  stimulate the economy following the financial crisis in late 2008. It was especially attractive as a  stimulus measure because there was significant latent demand for insulation, particularly in lower  income households that were most likely to be hit by the economic downturn, and also because low‐ skilled workers were particularly at risk from the crisis and could quickly be employed at installing  insulation (Hawke, 2010, pp. vi‐vii). What, when DEWHA proposed it, had probably been seen as a  good little idea for a slow budget year, suddenly became part of a major effort to save the nation  from economic disaster.  DEWHA was a relatively small department, mainly involved in policy development and with little  experience of large‐scale service delivery (Hawke, 2010, p. 33). The EEHP, including the HIP, as well  as a large Green Loans program and other energy efficiency programs, were initially managed by a  single branch of the Renewables and Energy Efficiency Division (REED) within DEWHA (p. 12). REED  reported to a Deputy Secretary who also had responsibility for the Antarctic Division, the Marine  Division, Australian Government Land and Coasts Division and Parks Australia, and was involved in  three major strategic policy reviews related to a proposed carbon pollution reduction scheme (p.  59). In the words of the ANAO, ‘The demands placed on those at the branch and division head levels  to deal with a wide range of issues under tight timeframes were unreasonable (Auditor‐General,  2010, p. 97).’ There are a number of indications that DEWHA had expressed concerns about their  capacity to deliver the HIP (and the EEHP more broadly). Prior to the announcement of the program,  they had favoured a roll out over 5 years rather than 2 ½ (p. 32). However, this was found to be  inconsistent with the priority stimulus objectives and DEWHA were over‐ridden9. There were also  well‐established concerns ‘related to IT system capability, accommodation, recruitment/training and  challenges and serious backlogs with existing programs. …the picture was one of a division already  seriously stretched in terms of its capacity to deliver (p. 69).’                                                              

8

 PM&C and Treasury are two of the three ‘central agencies’ of the Commonwealth government (the other  being the Department of Finance and Deregulation). Both are senior agencies with cross‐government  responsibilities, with the Secretary of PM&C having important leadership roles across the Australian Public  Service. PM&C’s role in particular has been evolving over recent years ‘…assuming a stronger role in driving  policy development and ensuring delivery of high‐priority government initiatives (Auditor‐General, p. 86). ’  9  It is not possible to identify from the public data used for this paper precisely where the decision not to  accept a five‐year rollout was taken. However, it seems quite clear that, in addition to the omnipresent  statements of the Prime Minister at the time about the urgency and importance of the stimulus programs, a  specific mechanism for enforcing the stimulus goals had been established, in the form of the Office of the  Coordinator General (OCG ‐ see below) . Whether it explicitly took this decision cannot be known. 

3   

In the first phase of the HIP, which began when the program was announced, homeowners arranged  the installation of insulation with an installer of their choice, after obtaining two quotes, then  claimed the rebate back from DEWHA. It is not known how much warning DEWHA received of the  announcement of the EEHP, but they do not appear to have had time to develop any specific  systems to handle rebate claims that began to arrive under the HIP from 1 March, 2009. It was not  until 26 February, 2009 (Auditor‐General, 2010, p. 198) that they published the first program  guidelines and they did not begin processing rebates for payment under the scheme until late March  2009, using a hastily established manual process based on spread sheets. By this stage, there was  already a backlog of 2000 claims. By the end of May, the backlog had ballooned to 16000 claims and  Departmental staff engaged in this task had grown from 22 to 45 (pp. 59‐60).   The insulation industry was largely unregulated at the time the HIP was being developed (Auditor‐ General, 2010, p. 33). What regulation did exist was the responsibility of State and Territory  governments. In only one state (South Australia) was it necessary to have a license to install  insulation, and no specific training was required (Hawke, 2010, p. 35). The insulation manufacturing  industry was also highly fragmented with ‘at least four rival insulation manufacturing associations –  with a history of mutual distrust ‐ … each pushing competing product (Australian Financial Review  26/3/10)’. The main form of insulation used in Australia was the fibreglass batt, which was locally  produced by two companies (New Zealand company Fletcher and CSR‐owned Bradford Insulation).  These two companies held a market share of some 75% nationally, and had established the  Insulation Council of Australia and New Zealand (ICANZ), which had been strongly involved in  lobbying for the establishment of subsidised insulation schemes (Australian, 11/3/10). Other forms  of insulation did, however, exist, each with their own industry association; aluminium foil insulation  was particularly strong in Queensland. Disputes, which had occurred between the different  manufacturing groups in the past, had chiefly been around relative safety claims and what were  seen as attempts by ICANZ to skew government standards and programs in favour of fibreglass batts  (Australian Financial Review 26/3/10).  Prior to the inception of the HIP, an estimated 65 to 75,000 installations of insulation were being  performed each year by about 200 businesses around Australia. Demand was expected to increase  to 90,000 installations a month under the HIP (Auditor‐General, 2010, pp. 65‐66), a level which all  parties recognised would cause major changes in the industry (p. 28). DEWHA, being largely  unfamiliar with the industry, had commenced consultations with insulation industry bodies and  training organisations soon after the HIP was announced. State and Territory agencies were also  consulted. DEWHA had been informed that the manufacturing industry could expand by some 40  per cent but this was still well short of the level required and it was already clear to senior ministers  in early 2009 that imports would be used to address the increased requirements (p. 66). It was also  specifically pointed out by State and Territory authorities that the increased demand would increase  the risk of poor installation by unskilled labour (p. 88)and that this might lead to electrical and fire  safety issues. As one of the responses to these concerns, DEWHA initiated the development of an  insulation specific unit of competency within the national training framework(p. 110). This was in  place by the launch of Phase 2 on 1 July 2009.  Unfortunately, however, involvement of the electrical industry in this process was limited. Neither  had the electrical trades bodies been engaged in stakeholder consultations (Auditor‐General, 2010,  p. 111), because they were not considered part of the insulation industry (p. 108). Some unsolicited  4   

warnings had nevertheless been made by these bodies – in particular, the National Electrical and  Communications Association had written to the Minister in March 2009 warning that laying  insulation over existing electrical installations, posed significant risks (Australian Financial Review  11/2/10).  In parallel to the challenges of implementing Phase 1 of the HIP, DEWHA had the task of designing  the much more demanding second phase of the programme, due to start 4 months after its  announcement. DEWHA’s own assessment at the time was that it would take 6 months to be ready  (Auditor‐General, 2010, p. 68). In Phase 2, payments were to go directly to the installer, a change  which, it was hoped, would increase uptake of the program and ensure quicker transfer of stimulus  funds into the market. Initially, it had been intended that DEWHA contract with large national and  regional insulation suppliers around the country, who would deal direct with householders and  invoice DEWHA on completion of installations (p. 69). However, there were fears that DEWHA might  not be able to arrange the necessary procurement in the time available and that this model might  engage the legal responsibility of the Commonwealth for any accidents (pp. 73‐74). Because of these  concerns, the decision was taken in April 2009 to design the program around householders  contracting direct with installers, who would claim the rebate direct from the government. It was  also felt that this approach would maximise the job creation effect of the programme, since it was  expected that many new installation businesses would be established to take advantage of the  program (Hawke, 2010, p. xiv). Under the new business model, installers would simply have to  register with the government to start to offer work under the scheme, then be able to claim their  rebates direct from DEWHA on completion. Medicare Australia, the service deliverer for the national  health insurance system, was retained to provide the necessary high volume transaction systems  and controls and enable both registration and claims to be done on‐line (Auditor‐General, 2010, p.  28).  In order to manage the project a Project Control Group (PCG) was set up in April (Hawke, 2010, p. 3).  It was chaired by a Deputy Secretary from DEWHA, with members from DEWHA; the Office of the  Coordinator General (OCG – part of PM&C); Medicare Australia and other agencies as appropriate  from time to time (Auditor‐General, 2010, p. 81). Membership of the OCG was significant, since it  had been given the role of ensuring the timely delivery and overall coordination of the full range of  stimulus initiatives across government. The OCG also centralised communication to the Prime  Minister and Cabinet for this and other stimulus programs; all formal correspondence, even from the  responsible Minister, was to be passed through the OCG (p. 87).  Although the biggest concern during the design phase appeared to be that the program would not  generate sufficient interest (Auditor‐General, 2010, p. 91), early in its development DEWHA  commissioned a risk assessment by an external consultant. The resulting advice was that proposed  management plans ‘would appropriately mitigate all but six risks to medium or low (Hawke, 2010, p.  32)’. The six unmitigated risks were that:  • • • •

procurement would not be completed by 1 July 2009;  the program could not be developed or delivered in a controlled way;  inadequate controls would allow fraudulent or inappropriate behaviours  the internal capacity did not exist to develop, staff, control and deliver the program on time; 

5   

• •

there was potential political fallout from failures in process, system and project deliverables;  and that  the regulatory framework would not adequately support the programs goals. 

It is also particularly important to note that this external risk assessment was based on the  superseded regional outsourced delivery model, not the final ‘direct to installer’ business model  (Auditor‐General, 2010, p. 71). Although the change of business model addressed the first two of the  remaining unmanaged risks, it arguably exacerbated several of the others (Hawke, 2010, p. 32).  Nevertheless, DEWHA advised the Minister on 9 April 2009 that  ‘…Development and selection of the business model is being informed by a comprehensive  risk assessment, to identify and manage the full range of risks. The emerging preferred  model will adequately address these; however residual risk around: fraud, complaints and  installer and household safety will remain. Our strategies for managing these will be built  into the business model wherever possible, or dealt with on an ongoing basis after the  business model is put in place (Auditor‐General, 2010, p. 73).’  This advice was described by the Auditor General as ‘overly optimistic’. Moreover, despite the risk  register being ‘regularly updated to reflect the changes in risk profile’ and risk management being  reported on and discussed at each PCG meeting (Hawke, 2010, p. 31),  ‘A full risk assessment, explaining the breadth and scale of the risks and the reliance on  successful implementation of a range of mitigation strategies was never provided to  Ministers, either from DEWHA to its then Minister or through the OCG to the then Prime  Minister (Auditor‐General, 2010, p. 73).’  The level of activity in preparing Phase 2 must have been intense. The first project plan, still based  on the contracted service delivery model, became available only in April 2009 (Auditor‐General,  2010, p. 70). Over the next months, it was adjusted several times and it was only in the 5th and final  version of the plan, completed after launch of program in July, that Medicare involvement was  recognised. The plan was never finalised. In July 2009, a DEWHA review of Phase 1 also identified  that there had been significant issues in getting sufficient numbers of staff with the right skills,  particularly in the areas of compliance and audit and IT support. However, ‘These lessons were not  transferred into Phase 2 (p. 98).’ By the end of June 2009, 68,496 claims had been received under  Phase 1 (p. 59). Phase 1 claims were still being processed in February 2010 (p. 63) when Phase 2 was  terminated.  In order to facilitate registration and access for new entrants to the industry, the on‐line registration  process that had been introduced for installer did not require verification of any documents  (Auditor‐General, 2010, pp. 104‐105). Furthermore, in order to speed up payments, the system  allowed claims for rebates to be made without any proof that the work had been carried out (p.  115). Householders merely had to get one quote (rather than two as in the first phase) and  countersign an installer work order to enable a claim to be made. Hence, when Phase 2 was  launched on 1 July 2009, it became both easier to get involved in the scheme and easier to claim  rebates. What’s more, significant elements of the program were still not in place, perhaps most  importantly given the relaxation of checks, the compliance and audit system (p. 130). 

6   

Media references to the HIP prior to the roll out of Phase 2 had mainly been in the context of  criticism of the scale and lack of targeting of the overall stimulus program. Sub‐editors and  commentators could effortlessly generate catchy headlines by playing word‐games with the main  brand of insulation, Pink Batts, but despite sneering references to the ‘Pink‐Batt led recovery’ and  endless puns on ‘Battman’, the press by and large did not pay much attention the program until  August 2009, when stories started to appear about ‘dodgy practices’ related to the scheme. These  included reports of suppliers always quoting the maximum amount of the rebate, regardless of the  size of the installation; of rebates being paid without any installation actually occurring; and of  quotes being based on Google Earth surveys rather than any physical attendance at the home  concerned. Imports of insulation also increased, as expected and despite heavy investment in new  local production capacity, leading to stories that stimulus money was being used to support overseas  (particularly Chinese and American) jobs rather than Australian workers.  The government appeared confident that these issues could be managed by pointing to the success  of the HIP in generating jobs, as had been its primary intention. However, they did take action on  some of the developing issues with regard to potential fraud and abuse. On September 1, new  program guidelines were released, which specified that new installers had to provide proof of  insurance and minimum competency standards prior to registration; that written quotes had to be  based on physical inspections; and that prices quoted could not exceed a new Pricing Table without  explanation (Auditor‐General, 2010, p. 198). Despite these measures, stories of rorting of the  program and increasingly extreme claims of waste, continued to grow.  On 21 September 2009, the NSW Fire Brigade issued a warning concerning the dangers of locating  insulation too close to down lights and on 29 September, DEWHA reminded installers of existing  building standards concerning down light clearances (Hawke, 2010, p. 6). However, when a young  installer was electrocuted in mid‐October, attention turned to the risks of electrocution, particularly  when using foil insulation. The electrical trades groups who had been left out of earlier consultations  were quick to note that they had warned the government of just this risk; and the industry  associations for non‐foil insulation were also keen to establish that foil was particularly dangerous.  On 26 October, DEWHA reminded all registered installers of their responsibilities under Occupational  Health and Safety legislation, and convened a meeting of training organisations on the following day  to review the training packages with specific regard to potential fire hazards and foil insulation.  Nevertheless, despite deficiencies in the training packages, unprecedented numbers of people (more  than 3700) were being trained in insulation installation (Auditor‐General, 2010, p. 109).  Also in early October, the first de‐registrations of installers occurred under the scheme. Although  this was generally presented in the press as a belated response to unscrupulous practices, in fact all  the first batch of deregistrations were for failing to provide insurance documents required under the  1 September guidelines, and most of those affected would be readmitted to the register when they  did produce evidence (Hawke, 2010, p. 51). Nevertheless, the press and opposition made great  capital over the government’s unwillingness to reveal the names of the deregistered installers and  pressure grew for a so‐called ‘name and shame’ register to be established. The issue of  deregistration would continue to dog the program. It was the key sanction DEWHA had against  installers who did not comply with program guidelines, but the fact that it was an administrative  sanction, which was not supported by any specific legislative power, meant that the Department had  to provide for natural justice and precede any action by asking the wayward installer to show cause  7   

why they should not be struck off (Hawke, 2010, p. 50). Initially, the length of these show cause  periods was set at 56 days: it was only very late in the program, when safety issues became a real  concern and stories started to appear that installers who had already been found in breach of the  guidelines were still operating, that the show cause periods were reduced to 24 hours for safety  breaches (p. 52).  On 1 November, without warning, the rebate was cut from AUD 1600 to AUD 1200. Although the  media tried to link this reduction to the stories of fraud, the real concern was the much higher than  expected uptake of the programme (Hawke, 2010, p. 28). Instead of the forecast demand of 90,000  claims per month, by end October more than 40,000 claims were being received each week, and the  trend was steadily upward (Auditor‐General, 2010, p. 117). AUD 696 million had to be brought  forward from future budget allocations in November and further funds were to be brought forward  early in 2010 (p. 91). This was presented by the opposition as cost blowout, which was not the case,  since the overall program was capped. It was also presented as ‘evidence’ that the previous level of  subsidy was too high and had been absorbed into wasteful overpricing.  The sudden change caused distress in the industry, since many manufacturers and distributors had  invested heavily to handle the higher demand. Moreover, there was a relatively complex exception  to the reduced rebate level, allowing homeowners who had already received quotes and who  completed installation before 16 November 2009 to still apply at the higher level, with the  difference being processed as a top up payment through a manual system. This placed extra strain  on the DEWHA manual processing system, which was still processing Phase 1 payments.  The program guideline revisions of 1 November 2009 also introduced new safety measures; a ban on  the use of metal fasteners; making mandatory the installation down light covers; and the start of a  targeted electrical inspection program in Queensland, where foil insulation was mainly used and  where the first fatality had occurred (Auditor‐General, 2010, p. 198). Despite these measures, stories  of safety issues continued to increase. In early November, papers started to keep records of the  numbers of house fires attributed to insulation issues (43 in the year to 10 November). Despite the  frequent vagueness as to whether these fires were related to the HIP or earlier installations, the  relatively large numbers made it appear that safety problems were indeed very widespread. To add  to the impression of major problems, 2 further fatalities occurred on 18 and 21 November, one from  electrocution while installing foil insulation and the other from heat exhaustion. On 30 November,  new training materials were released, but calls had already commenced for massive inspection  programs to be put in place to ensure safety. Speculation was rising that the cost of such a program  would actually exceed the amount of money available for the HIP itself. Meanwhile, bit by bit behind  the scenes, resources were being martialled within DEWHA to deal with what had become a very  troubled program. Most importantly, during November, an Energy Efficiency Taskforce was formed  to take responsibility for all energy efficiency programs, and a separate compliance branch was  established (Hawke, 2010, p. 60).  December saw the fifth version of program outlines issued (Auditor‐General, 2010, p. 198). This re‐ established the requirement for homeowners to get two independent quotes; introduced a  requirement that workers (not just supervisors as had been the case up until now) had to prove  training in installation or demonstrate previous experience; required installers to complete a risk  assessment prior to every installation; and banned the use of metal or conductive tools. Installers  8   

were also required to accept terms that would see them placed on a public list if they were  deregistered. Later in the month, a new requirement was introduced that installers had to provide  evidence of minimum training by 12 February and lastly, on 23 December, a list of approved  insulation products was issued.  Over January the press continued to report on the growing numbers of house fires, examples of  sham installations and abuse of the rebate system. By this stage, the words ‘bungle’, ‘fiasco’,  ‘debacle’ or ‘scandal’ were seldom absent when the program was mentioned. Pressure on the  Minister to resign, or for the Prime Minister to sack him, was growing, and both newspapers and the  opposition were attempting to establish that both Ministers knew of the risks well in advance and  had failed to act on them. On 4 February 2010, a fourth fatality occurred, when another young  installer in Queensland fired a banned metal staple through foil insulation. Foil insulation was  al, 2010, prom the program on 9 February, and on 10 February the government announced a  program to inspect and either remove foil installation from or install electrical safety switches in  50,000 homes where it had been installed.  On 19 February, HIP was terminated. Not much more than half the funding originally allocated to the  program had been expended at this stage, but it was expected that all remaining funds after claims  in the pipeline were met would be used on remediation measures, including the inspection of  150,000 homes with non‐foil insulation later announced in addition to the foil insulation program, as  well as the implementation of assistance programs for businesses that were forced to fire workers or  close due to the program cancellation. Ironically, recruitment at DEWHA was finally catching up with  demand for staff, which meant that more staff would be allocated to the program after its closure  than during its period peak of demand (Auditor‐General, 2010, p. 35). 

Understanding the case The story of the HIP can be understood at several levels. Some commentators attempted to use it  (or parts of it) as a morality tale about the inappropriateness of governments intervening in markets.  The focus of the economic press, on the other hand, was chiefly on whether the program was likely  to succeed in its stated objective of stimulating the economy or as part of a broader discussion  about the appropriateness or level of stimulus being applied. The economic press was also much  pre‐occupied with the level of waste in this (and other) programs, a key theme for the broader  media, political commentators and the opposition. However, the latter groups were interested  mainly in what this waste said about the competence and credibility of the government and what its  implications were for individual political careers and, ultimately, re‐election prospects. The general  media also gave relatively much more emphasis to the spectacular safety issues arising from the  program, which allowed the opposition to claim that the government could be charged with  industrial manslaughter if it were a private company and to suggest that the government had been  ‘the greatest threat to the safety of many Australian families over the last 12 months’ (Sydney  Morning Herald 24/2/10). This was followed later in the period under review by an almost forensic  interest in ‘who‐knew‐what‐when’, something which was to continue for some months.  Little, if anything, can be productively added to any of these stories, with the possible exception of a  small footnote in an examination of the economic benefits, or otherwise, of the stimulus, which will  no doubt take some years to write. Likewise, the purpose of this paper is not to attempt any form of  9   

assessment of blame or responsibility, but rather to try to understand the mechanisms by which the  failure of this program came about and, using comparisons with the other cases examined in earlier  papers, to suggest some learnings that might assist in avoiding similar situations. Such questions  were left largely untouched in crushing weight of media coverage and commentary, virtually all of  which seemed to imply that any reasonable person with a bit of sense could have done a better job  than the combined minds of the Cabinet and the APS. This might be a tenable position if ‘bad’  decisions could be traced to a few people. However, an examination of the case suggests that the  construction of this mess involved many people, most of whom were almost certainly operating to  high standards and with great commitment. How is it that such a system can still fail catastrophically  and how could it be avoided in future?  A useful first step in coming to terms with what can be learnt from the HIP might be to examine in  what ways it can be seen as a failure. This series of papers has paid attention not only to ‘objective’  standards of success or failure, but also to the construction of success or failure within the broader  discourse of Australian society. From this point of view, it could probably be said the Strategic  Indigenous Housing and Infrastructure Program (SIHIP) was characterised by the way that all the  actors involved, at both Commonwealth and Territory levels and from either political or public  service sides of government, failed to engage with expectations of the program, particularly in terms  of timing, even though all the parameters which were eventually used to portray it as bungled were  known well in advance. The Australian Technical Colleges (ATC) program, on the other hand, can be  seen as a demonstration of how a government department can help to reconcile political objectives  with external realities in a very fluid environment, in a way that potentially avoids the worst  consequences of the conflict between the two. In this latter case, the discursive construction of  success and failure continued in some ways externally to the program and departmental actions, and  with different purposes.  In the case of the HIP, it is hard not to consider the program as a failure at almost any level. In terms  of its original objectives, the 1.1 million homes insulated represent only half what was intended; the  10,000 jobs that were probably created at the height of the program were no doubt significant  (there was no clear a priori statement of an employment objective), but against that has to be  placed the fact that many of these jobs were lost when the program was cancelled. Furthermore,  the cost of the insulation actually delivered and the jobs created, particularly when the cost of  remediation and industry adjustment programs is taken into account, was without question much  higher than intended, or than it need to have been, if the program had been better managed. Even  the argument that the waste was justified because of the overriding importance of the immediate  economic effect seems hard to sustain. Apart from the fact that there doesn’t appear to be any way  to assess the contribution of the HIP to the economic rescue and even allowing for the possibility  that the stimulus may have been timely when the program was running, the fact that almost half the  cost of the program was incurred after it ceased, in a context where government was increasingly  attempting to reduce the fiscal stimulus on the economy, suggests that it involved a great deal of  waste even as a macroeconomic measure. If the HIP made good economic sense during the second  half of 2009, it was bad during at least the latter half of 2010 and 2011, a period during which it  consumed almost as many resources as when it was still operational.  Moreover, looking beyond the achievement or otherwise of the program’s objectives, it must also be  seen as having fallen seriously short by any standards of good practice in policy design or delivery.  10   

Observing the media frenzy might suggest that the biggest failings of the program were those  around worker safety and household security. However, even given that there were alternatives  available that might have made it possible to better manage these events and that there may be  broader issues to be addressed with regard to construction industry training and regulation, it is far  from certain that the level of worker fatalities or insulation‐related house fires was higher than  might have been expected for the same number of installations prior to the program (Australian  Financial Review 27/2/10). For the purposes of this paper, it is also important not to underestimate  the very apparent failures of the program to control the disbursement of funds or to ensure that the  funds were spent as intended. Whereas the ATC program can be seen as having spent more than  was necessary for what had been delivered, many of these costs related to the achievement of  political goals that, whether one considers them worthwhile or not, were at least legitimate and  lawful. In the case of the HIP, these funds can only be considered to have flowed uncontrolled into  the pockets of private companies or individuals, in many cases in some measure through their  dishonesty. This cannot be considered an acceptable standard for the delivery of a major  government program.  Hence, the HIP differs from the other two cases examined in this series chiefly because of its  substantive failure. Although media coverage played a key role in bringing about its collapse, it  achieved this mainly by bringing to light the fact that fraud and safety breaches were occurring, and  reporting on the apparent ineffectiveness of the measures taken by the government to address  these issues. While there can be little doubt that some of the coverage was pursuing a partisan  political agenda, it seems unlikely that less ‘biased’ or more ‘balanced’ coverage would have brought  about a significantly different result. This is so even taking into account the fact that the intense  press coverage of the SIHIP, subject of the first paper in this series, which clearly did consist of  contestable assessments and struggles for meaning, was contemporaneous with Phase 2 of the HIP.  The only point that might be made is that the juxtaposition of these two media storms may have  significantly increased the effectiveness of the attack on the Rudd government as being  fundamentally incapable.  Was the program, in fact, so flawed in its conception that it should not have been considered under  any circumstances? This is the implication of those who wanted to present the HIP as typifying what  goes wrong when governments interfere in markets. If such were the case, however, it might be  expected that similar programs elsewhere in the world had had similar issues, which is not the case.  The Warm Front scheme ran in the UK from 2000, providing assistance for energy efficiency  measures, including insulation, with the overall goal of ensuring that people did not spend more  than 10% of their annual income on energy costs. Although audits identified that it was not reaching  the low socio‐economic households it targeted (Auditor‐General, 2010, p. 52), the issues identified  were neither of the type nor the severity of those that plagued the HIP. Warm Front continues to  operate.  Although the Warm Front scheme was a demand‐driven energy program, it was not a stimulus  measure. However, at the same time as the HIP was entering its second phase, the New Zealand  government implemented the Warm Up program, which had job creation objectives in addition to  health and energy efficiency aims. This program, instead of offering insulation effectively for free,  required significant co‐payment by householders, although it also offered access to subsidised  finance to disadvantaged homes for the co‐payment component. The Warm Front program  11   

experienced no significant difficulties, in spite of the fact that demand was much higher than  predicted, with the first year target for installations being surpassed in the first 6 months.10  Other important differences did exist, however, between both these programs and the HIP. In  particular, both required extensive checks on installers prior to registration and applied outsourced  delivery models using established companies. Both were also carried out over longer timeframes  and were on a much smaller scale.   Whether an insulation subsidy program was the best stimulus option available to the Australian  government under the circumstances is hard to evaluate. Clearly, the government wished to take  advantage of the widespread consensus that prevailed at the end of 2008 that something needed to  be done to reduce carbon emissions; it was perhaps unfortunate for them that this sentiment  appeared to erode during 2009. With the failure of the Copenhagen talks at the end of 2009, even  those who still supported action on climate change were probably more cynical about some of the  programs that drew on ‘green’ sentiment to justify themselves. It is perhaps ironic that the failure of  the HIP may have contributed to this increasing cynicism.  If it cannot be said that there was anything inherently wrong with selecting an insulation program as  part of the stimulus package, it does seem plausible to say that it was an error to attempt to make it  fill a role that it may have been inherently too small to fill. Treasury had a declared intention of  trying to channel stimulus through the construction industry, and had determined that the industry  as a whole had the capacity to bear such stimulus (Australian Financial Review, 6/2/09). However, no  specific evaluation of the capacity of insulation industry to fulfil this role in its own right appears to  have been done. To make this small sub‐segment of the overall construction industry the delivery  pipeline for a significant proportion of the stimulus plan seems with hindsight to have been  inherently risky.  The mismatch of industry size with the scale of the ambition goes well beyond program selection.  Although the desire to reap political gain is clearly evident in the extravagant language used to  launch the program (recalling the quote from the Minister responsible noted above), more  importantly, critical features of the design seem to have been deliberately selected to exacerbate  any mismatch between industry capacity and economic goals. The fact that no co‐payment was to  be required demonstrates the level of priority that was being given to maximising the attractiveness  of the scheme and ensuring the greatest possible accessibility to it. The decision to adopt a  decentralised business model was also, if only in part, driven by the desire to maximise the  formation of new businesses and employment creation effects of the program. Aspects of the  implementation of the HIP were also modified for the same reason, in particular the removal of  controls through on‐line registration and claiming of rebates in Phase 2. Moreover, there seems to  have been no consideration given to the possibility that the program might be too successful. Little  attempt seems to have been made to understand how demand would be generated or how large it  might become, and it appears to have been decided that if it all came at once that would only assist  in the achievement of that primary goal. Everything points to the conclusion that the intention was  to push as much money out as fast as possible through the HIP. Another indication of this ‘après moi                                                              

10

It is interesting to note that an earlier New Zealand program, which subsidised ‘do‐it‐yourself’ insulation was  stopped after 3 deaths occurred due to electrocution involving the use of foil insulation. Foil was not on the list  of approved products in the Warm Up program of 2009. 

12   

le deluge’ attitude is that at no stage does any exit plan appear to have been developed. Even had all  gone well, it would seem to have been sensible to foresee some adjustment mechanisms when the  subsidy ceased, either because there were no more roofs to insulate or because homeowners  suddenly had to pay full cost.  The crucial decision to adopt a decentralised business model is also linked to what appears to have  been an unshakeable determination to get the program out ‘on time’, as was the decision that it  must be rolled out over 2 ½ years rather than the five requested by DEWHA. In the light of this, the  consistent theme running through both the Hawke review and the ANAO report, that the extremely  limited time available for design, planning and development of capacity was either the direct cause  of or exacerbated other shortcomings, is particularly significant. It was this ‘urgency’ that meant the  risk assessments were constantly failing to reflect the current state of the business model; that  meant that no project plan was ever finalised; that meant that recruitment was running well‐behind  requirements throughout the life of the program (indeed it seems only to have caught up after its  closure!); and that led to the program being launched without an operating compliance and audit  system.  Over‐ambition, then, both in terms of the program objectives and in terms of the time allowed for  its design and planning, seems to underpin virtually all of the other failures that occurred. In  conjunction with the lack of capacity of DEWHA and its lack of experience in delivering large‐scale  programs, both of which were well‐known at the time of the program’s announcement, and what  appears to have been a governance system that was either incapable of or unwilling to admit the  problems that emerged, it seems fair to say that the die was cast for disaster well before the launch  of Phase 2, and that no crisis‐management after that stage, short of an even earlier termination, was  likely to have significantly improved outcomes. 

Underlying issues There are, no doubt, many factors that contributed to the establishment of such a fundamentally  flawed program. Even if it is likely that some of these can be laid at the door of executive decisions,  the way those executive decisions were enabled and could be seen as legitimate is of interest when  looking for lessons to draw from the case. The data suggests that some of these factors can be seen  as systemic and therefore prone to allow similar failure in the future.  Perhaps most striking in this respect is the way that the stimulus objectives of the program became  the unquestioned (and possibly unquestionable) dominant purpose of the program, to which all  other considerations were subject. It was the perceived need to release money into the market in  the shortest possible time that drove the timeline; it was the perceived scale of the economic  challenge and therefore the need to maximise the scale of the intervention that drove the design of  the program rebate levels and allowed the program to go ahead with only minimal controls on  either registration or rebate; and both of these considerations justified the choice of a business  model which magnified both control and safety risks.   Against this background, the fact that the HIP was largely conceived by two central agencies, the  Department of Prime Minister and Cabinet and Treasury, with little input from DEWHA (Auditor‐ General, 2010, p. 64) seems particularly significant. There seems to be little doubt that it was these  two powerful departments, focussing on their core concern to save the economy from recession,  13   

which drove both the design and the delivery timeframe of the HIP. While DEWHA may have been  happy to go along with this in order to get an energy efficiency program up and running, those  objectives seem never to have been allowed to interfere with the main purpose of the program. It is  far from certain (indeed with the benefit of hindsight it might be said to have been convincingly  refuted) that the model adopted represented the most efficient or effective way of ensuring that  Australian homes were insulated, but that seems not to have been a relevant consideration.  Not only were the two central agencies firmly behind the establishment of the key design  parameters of the program, at least one of them, PM&C, through the OCG, seems to have continued  to reinforce the timeline throughout the development of the program and specifically to have  contributed to the decision on the business model (Auditor‐General, 2010, p. 69). They also played a  key role in facilitating the connection with Medicare, which enabled the Phase 2 business model.  There can be no doubt where the priorities of the OCG lay:  ‘The design of Phase 2 was strongly influenced by the clear riding instruction from the  Commonwealth Coordinator‐General to reduce red tape and commence work on projects as  soon as possible, in keeping with the stimulus objective of the program (Auditor‐General,  2010, p. 78).’  This focus on the stimulus component of the program is also visible in the fact that data was kept on  the number of installations, based on claims and payments made, which allowed DEWHA to report  to the OCG on progress against the stimulus objectives, but none was kept on jobs or greenhouse  benefits (Auditor‐General, 2010, p. 99).  Moreover,   ‘Although the economic stimulus component was supposed to be equally important as the  energy efficiency objective, the imperative of responding to the global financial crisis  subordinated the energy efficiency requirement such that the usual processes associated  with putting a scheme such as the HIP in place were constrained. (Hawke, 2010, p. xiii)’  It seems to be quite clear then, that the influence of the central agencies, exerted through the OCG,  was sufficiently powerful to ensure that any consideration other than adhering to timelines and  expenditure objectives was likely to be given little consideration. A purported whistle‐blower  interview with current affairs program 4 Corners illustrates the way things may have been:  ‘Job creation was the most important thing. That was mentioned on many occasions, we  were told many times by senior management that the technical and safety issues were of less  importance than getting this programme up and running and creating jobs (Four Corners,  26/4/10).’  Under the circumstances, one could be forgiven for wondering whether, rather than following  Hawke’s recommendation to ensure more senior management oversight (Hawke, 2010, p. x), the  opposite might not have been more productive.  In addition to the insight that this quote gives to the way hierarchical and bureaucratic force was  exerted to ensure the predominance of one program objective, it suggests that there was a  distinction being drawn between issues related to delivery and those which were considered ‘higher  14   

level’. Several Ministerial and Prime Ministerial statements at the time assert that the policy  departments involved in developing this program could not be held responsible for its outcomes  because implementation was the responsibility of DEWHA. This distinction was explicitly expressed  when the then Commonwealth Coordinator General  ‘…told a Senate committee that federal government line agencies had primary oversight of  individual stimulus programs. Her responsibility was to ensure the money got out the door  according to the agreed milestones. "It was very clear in the budget papers that the program  delivery and compliance responsibilities rested with the line agencies. (Australian Financial  Review 2/6/10).”’  That the problems which arose were considered to be ‘lower level’ implementation points, which  could have been dealt with if only more controls had been in place, is also evident in the way the  Prime Minister, when he finally decided to try to take political responsibility for the program (whilst  at the same time using that as an argument against taking action against himself or his Minister) laid  the failure at the doorstep of his ‘failure to ask more questions.’ This seems to significantly  misrepresent the drivers for what occurred, which cannot be characterised as lower level staff  working without sufficient supervision. There can be no doubt that, in addition to their engagement  in making decisions on design features that exacerbated the fraud and safety outcomes of the  program, the timeline and scale of the HIP were directly inherited from and strongly enforced by the  central departments concerned. Although the auditor is no doubt formally correct when he finds  that DEWHA failed to inform their Minister that there were resource and capacity restraints that put  the delivery of the program at risk (Auditor‐General, 2010, p. 73), it is hard to believe that these  concerns were not raised, at least at PCG meetings. If they were not, it provides dramatic  demonstration of how limited the scope of the governance body was seen to be; if they were,  remembering the role of the OCG in centralising communication with the Prime Minister and  Cabinet, it seems the same conclusion must be reached, as a decision must have been taken either  not to refer the concerns to the Prime Minister, or that they were taken back to the Prime Minister  and ignored. In short, the alignment of hierarchical power with an overriding objective, coupled with  a belief that the origination of a policy and control of its key components can be quarantined from  its implementation and responsibility for its outcomes, appears to have left all the risk inherent in  this very ambitious project effectively unmanaged – transferred from the strategic level at which it  was developed to a delivery department known to have little experience in delivery, known to be  under resourced and concerned about its ability to deliver, but without a voice at levels at which  resources and authority might exist to mitigate the risks.  Mention has been made of the fact that a narrow definition of the insulation industry led DEWHA to  exclude electrical trade groups from its consultations. Whether their inclusion would have made  much of a difference to the program design is not clear, given that some of the groups involved did  give unsolicited warnings of safety risks to the government anyway. However, the fact that they had  apparently not been listened to became a problem for the government later on, when they began to  make critical statements to the press. Another key problem for the government in managing the  media were the competing statements of the various manufacturing industry groups, which  provided a steady stream of ‘information’ to the papers about ‘problems’ with different types of  insulation, in particular foil. Lastly, although the States and Territories were consulted to some  extent,   15   

‘(t)he final business model did not directly involve state or territory authorities. Their role was  limited to secondary contact through householder complaints to consumer affairs or fair  trading authorities, occupational health and safety authorities and emergency services  authorities. The Commonwealth placed a high reliance on state and territory regulatory  authorities to carry out their responsibilities in these areas effectively.  But, there was always  a risk that the existing regulatory framework might not adequately support the HIP’s goals –  and this was indeed the case (Hawke, 2010, p. 15).’  Precisely why this connection was not better made is a matter for speculation, but it seems likely  that if it had been, the government would have benefited from the States’ much greater familiarity  with the industry and with key players, and also potentially been able to mobilise significant pre‐ existing resources to better enable delivery. Was it again due to the imperative of the timeline? A  belief that in order to maintain control, particularly given the schedule, the number of players had to  be restricted? Was it due to confusion as to the role of the OCG, who was holding its own weekly  meetings with counterpart bodies in the States and Territories to oversee the stimulus rollout? Or  perhaps a desire that the Commonwealth should get most of the credit for the program (a pyrrhic  victory if ever there was one)?  Whatever the reasons, it is interesting to compare the HIP case to the ATC program. In the latter  case, one of the key means by which DEST seems to have been able to negotiate acceptable  outcomes for both the roll‐out and eventual close‐down of the program appears to have been pre‐ existing connections with their State and Territory counterparts. Even in the case of the SIHIP, the  eventual resolution of the immediate problem created by the program involved FaHCSIA  ‘shadowing’ key posts in the Territory public service. Both of these Departments are significantly  larger and much more experienced with delivery than DEWHA was – and perhaps much more  familiar with how to deal with the States. It seems likely, then, that the failure to recognise or act  upon the known limitations of the delivery Department for the HIP in turn led to a failure to engage  resources that might have assisted in mitigating some of the issues that arose. 

Implications A significant proportion of the press coverage of the HIP related to the attribution of blame for its  failure. By far the dominant position was that the government had to take primary responsibility for  the deaths, fires, fraud and waste. However, the debate on this point was far from one‐sided – a  significant stream maintained that at least some proportion of the blame for both safety failures and  fraudulent behaviour should be laid at the door of the installers concerned (a view that seems  incontestable, but does not negate the possibility that the government also had a responsibility to  develop and deliver well‐designed policies). However, the program was not established as failure as  a result of this negotiation of meaning – indeed, there can be no doubt that, had the program been  successful, the government would have happily accepted credit for it. This case, at least, is  susceptible to understanding mainly in terms of the interactions, relative power and the capabilities  of the political and bureaucratic institutions of government and the ways these elements combined  once again to allow well‐identified risks to go unmanaged. At the heart of this phenomenon, looking  across the three cases in this series, it seems possible to discern a central issue: the relationship  between control and initiative, particularly between institutions and relative to their accepted  powers.  16   

In the HIP, a technology of control was established, consisting of an institutional structure  particularly represented by the OCG, and a set of processes involving schedules, milestones and  reports. Because of the power imbalance between the OCG and central departments on the one  hand and DEWHA on the other, the program goals enforced on the HIP were those related to the  stimulus, to the exclusion of the ‘green’ goals that were also purportedly attached to the program.  Furthermore, the power of the control system was such that, intentionally or unintentionally, it may  have quashed any dissenting voices or evidence that stood in the way of the imposed goal– including  those that were actually vitally important for the good of the government from which that power  was drawn.  This is not completely dissimilar to what occurred in the attempt to adjust the SIHIP after massive  criticism, so that it conformed more closely to the public models of what a successful housing  program might look like. Again, almost all latitude for local adaptation was removed from the system  and a bureaucratic mechanism of shadowing and reporting put in place that allowed the  government to demonstrate that it was achieving a particular set of outcomes in a predictable  fashion, despite the fact that these were arguably sub‐optimal in terms of either value for money or  benefit to the intended communities. More importantly, the SIHIP case also raised the possibility  that the rigidity of the roles of the various institutional actors in the early stages of the development  of the program were at the heart of their apparent inability anticipate a predictable disaster or take  any initiative in mitigation.  Both cases contrast in some sense with the ATC program, where, although a political battle to  declare the program successful or failed raged on in parallel, the actual results were to at least some  sense optimised because the bureaucratic players were able to negotiate solutions that were not  mandated but which were at least acceptable to most stakeholders. Although the same technologies  of control existed, through either good luck or good management between the political and  bureaucratic actors concerned, they were not used to close down options but rather to establish  parameters within which sufficient freedom was preserved to construct a solution that was far from  pre‐determined.  Further implications of this point can be elaborated across three different domains: the relationship  between political leadership and civil service; the unreconciled tension with regard to the roles and  relationships between and among Australian federal and state governments; and, the way in which  policy and delivery agencies are typically seen to relate.  Firstly, the suggestion is that some attention should be paid to the assumptions we hold with regard  to the relationship between political leadership and civil service. The past two decades have seen  significant changes in the way this relationship is understood and enacted. It has been claimed that  one of the most crucial changes to the definition of the role of the bureaucracy was the insertion, in  1984, of the phrase ‘under the minister’ into the definition of the responsibilities of Departmental  Secretaries under the Public Service Act, so clarifying their subservience to the Minister (Australian  Financial Review, 30/4/10). The arrival of New Public Management can also be seen as presupposing  that a public service organisation is the same as a private sector one, with the Minister in the role of  CEO (or perhaps Chairman). Of particular note in this respect is the prominence given to the notion  of ‘responsiveness to the elected government’ in an introduction by the Secretary of PM&C to PM&C  and its role (Moran, 2011). The work undertaken in this series of papers, however, indicates that  17   

further consideration might be given to the bureaucracy having some set of obligations that are  longer lasting than the specific direction of a Minister and, at least in the short term, are not easily  over‐ridden by political actors. This would be intended not so much to protect against incompetent  or corrupt political actors, but to embody some form of reconciliation between short and long‐term  horizons in the creation of public good.   The second domain where the balance of control and initiative may be susceptible to  reconsideration is the unreconciled tension visible in all three of the cases examined in this series  with regard to the roles and relationships of Australian federal and state governments. It is quite  possible to read the SIHIP case as demonstrating assumptions about the ‘seniority’ of federal  bureaucracy over the Territory public service – and federal government over Territory government ‐  in a relatively simplistic hierarchical relationship. In the HIP case, the same tension is visible in the  mismatch between the policy setting at federal level and the location of regulatory powers at state  level. This is not just a question of constitutional issues around the domains of sovereignty of the  various jurisdictions. It also seems that achieving positive results in program design or delivery  across the jurisdictions might depend to at least some extent on preserving a measure of initiative  for the ‘junior’ partners to act as true collaborators. Such a relationship is reflected in the relatively  ‘open’ way in which the jurisdictions seem to have negotiated a resolution for the ATC program.   Finally, these three cases draw into question the way in which policy and delivery agencies are seen  to relate. Obviously the distinction has significant value in its own right – the activities of developing  policy are quite different from those involved in delivering programs. However, to see the policy  agency as in some way ‘higher’ than the agency responsible for implementation, particularly if it is  able to alienate responsibility for issues that might arise in delivery, seems to magnify the risk of the  policy agency imposing an unworkable policy on a delivery agency because it has greater access to  power. This work suggests that delivery agencies should have a well‐established voice in the design  of policy, and that policy agencies should be intimately aware of the conditions that apply in the  delivery field in which their policy will be implemented.  Although all these suggestions must still be treated as highly provisional and in need of much greater  specification, nevertheless a number of practical implications seem to emerge.  In the HIP case, the concept of better balancing control and initiative might have played out in a  more balanced consideration of the competing implications of the program’s goals and by  recognising some overriding requirement that public sector managers take into account basic  standards with regard to the handling of risks, whatever the declared political priorities. This  probably needs more than exhortations to higher standards of individual integrity or courage; some  form of protection or recognised standard upon which the managers could stand would be the only  secure base to enable such behaviour. In addition to potentially re‐evaluating the use of instruments  such as public service codes, this might also lead to a careful consideration of how central agencies  in general, and coordination units in particular, are established. The suggestion would be that, rather  than focussing on their ‘disciplinary’ or control role (though this does not mean such roles should  not exist), it may be fruitful to enhance their role as facilitators and enablers, who also ensure the  maintenance of key standards in both policy design and development.  Some of this role is already visible in the declared approach of the Cabinet Implementation Unit  within the Department of Prime Minister and Cabinet (CIU, 2006), which should have been in force  18   

during the lifetime of both the SIHIP and the HIP. The question of how, and with what purpose, this  Unit played so little visible part in either programme is a question for further investigation, together  with an investigation into the risks and best practices relating to the establishment of special  purpose ad‐hoc task forces and their interaction with existing entities of government with broader  and longer‐lasting roles.  A second set of implications arises with regard to the reform priorities for the Australian Public  Service, which were enunciated by the ‘Ahead of the Game’ report (2010). One of the key objectives  outlined in this report was to enhance the APS’s ‘strategic policy capability’. This objective is not at  all disconnected from the events which frame the HIP case, since then Prime Minister Rudd, when  launching the reform process, used the way the APS developed its response to the 2008 financial  crisis to exemplify what he meant by such a capability. ‘Strategic policy capability’ is also clearly  linked to responsiveness:  ‘…responsiveness… is not only a matter of providing timely advice, ensuring implementation  of key programs and policies, or drawing together input across portfolios. …there is also a  clear expectation that the Australian Public Service will increasingly focus its efforts on  providing a greater level of strategic advice. …(t)o help us better perform this role and deliver  on the government’s priorities, a structure which bolsters our strategic policy capability has  been put in place (Moran, 2011).’  This work suggests that the concept of strategic policy capability needs to be carefully nuanced –  that the strategic level needs always to be well‐connected to the implementation reality; and that  the power of the various actors needs always to be well‐balanced so that voices (and risks) are not  stifled. In particular, there should be well‐established mechanisms that make it much harder to  ignore countervailing considerations or inconvenient realities and ensure that there is some  recognition of a need to respond to them rather than merely letting them become someone else’s  problem.  Finally, some investigation is indicated into the relationship between budgeting and planning  procedures and the definition and handling of risks. The establishment of a large‐scale or long‐term  program implies setting boundaries that determine how risks are defined and managed, and which  attach resources and administrative or legislative powers to actions and policies. However, many  programmes (the SIHIP and the HIP are no exception) are implemented in conditions where the  outcomes are not certain and where contextual change is almost certain to occur during the life of  the program. Some of the rigidities and inflexibilities which lead to externalised risk might be  avoided by either adopting more limited policy time horizons, or by building in phased‐in  implementation processes with appropriate review points that enable learning and adjustment to  changing circumstances.  This analysis has added to and in some respects confirmed the conclusions of the previous two  studies. It proposes that there is some value in looking beyond the competence or otherwise of  specific individuals or governments in policy failure. It also goes beyond the suggestion of Lewis  (2010) that applying well‐understood policy design practices could have avoided this sort of failure,  in the sense that it asks the question as to what actions might be taken at an organisational and  policy level to enable these practices. In this sense, it is hoped that the work offers a perspective  which is at some level practical and useful.  19   

  2010. Ahead of the Game: Blueprint for the reform of Australian Government Administration.  Canberra.  Auditor‐General. 2010. Audit Report No. 12 2010‐11 Performance Audit. In A. N. A. Office (Ed.).  Canberra: Commonwealth of Australia.  Britton, G. 2011. What falls between the cracks: boundary‐spanning and risk in a complex public  programme, 15th Annual Conference of the International Research Society for Public  Management IRSPM XV. Dublin, Ireland.  Britton, G. M. 2010. Infrastructure Risk as a clash of voices: the expression of a crisis in an Australian  Indigenous housing programme, 14th Annual Conference of the International Research  Society for Public Management IRSPM XIV. Bern, Switzerland.  CIU. 2006. About the CIU, Vol. 2012.  Hawke, D. A. 2010. Review of the Administration of the Home Insulation Program.  Lewis, C. 2010. The Home Insulation Program Policy Debacle: Haste Makes Waste. Public Policy, 5(2):  83‐100.  Macintosh, A., Wilkinson, D., & Denniss, R. 2010. Climate Change. In C. Aulich, & M. Evans (Eds.), The  Rudd Government: Australian Commonwealth Administration 2007‐2010: 199‐220.  Canberra: ANU ePress.  Moran, T. 2011. All about PM&C: What we do and how we do it. In D. o. P. M. a. Cabinet (Ed.).