Apr 10, 2012 - Upgrade offices, restrooms and student support space. ⢠Repair damaged parapets and exterior concrete s
WILLIAM O. EDDY HALL REVITALIZATION April 10, 2012 EXECUTIVE SUMMARY: The Eddy Building is a 69,457gsf building located on the academic spine of Main Campus. It houses classrooms, lecture halls and faculty offices for the English, Philosophy, Foreign Languages and Literature, and Communication Studies departments in the College of Liberal Arts. This revitalization project would prioritize life safety, ADA and energy efficiency upgrades, while improving the overall building aesthetics. Integral components of the revitalization would include:
Upgrade main building entrance and entry plaza Upgrade offices, restrooms and student support space Repair damaged parapets and exterior concrete stairs New floor finishes throughout the building Paint/patch exterior walls and replace lecture hall roof Installation of a fire sprinkler system and upgrades to fire alarm system Tie‐in to campus chilled water system to replace aging chiller, now that District Cooling Plant #2 is online Asbestos abatement including floor tiles as well as mechanical and plumbing insulation Installation of new mechanical and plumbing fixtures Refurbish elevator Replace windows
JUSTIFICATION: William O. Eddy Hall was built in 1963 and has had only limited upgrades over the years. The building is home to approximately 157 faculty, staff and graduate students and over 10,500 students (average of last 3 semesters) have classes in the building each week. A capital renewal project was submitted to the State in 2008 to address the deferred maintenance needs. It received cash fund spending authority, but was not funded. A portion of the 2010 classroom upgrade bonds were earmarked for new furniture and cosmetic upgrades to the heavily used general assignment classrooms in the building. These funds helped improve appearances, but building systems, offices and deferred maintenance items were not addressed. The Eddy building is a heavily used building that provides vital classroom and office space, with deferred maintenance needs that we should not continue to ignore.
William O. Eddy Hall Revitalization 4/10/2012 Project Budget
Estimated Costs
Remarks
Professional Services Site Survey, Geotechnical Consultants - Architects, Engineers, Vibration, Acoustics
$
-
$
700,000
$
1,000
CSU Facilities Project Management
$
140,000
Independent Code Review/Commissioning
$
50,000
Total Professional Services
$
891,000
Revitalization - 69,457sqft @$72/sqft
$
5,000,904
Site Work Service/Utilities
$
58,096
Site Improvements/Landscaping
$
200,000
$
5,259,000
CSU Communications/AV
$
50,000
Total Equipment and Furnishings Costs
$
50,000
Relocation and temporary space
$
-
Total Miscellaneous Costs
$
-
Advertisements
Construction
High Performance Certification Program Subtotal Construction Costs Equipment & Furnishings Fixed Equipment Moveable Equipment
Miscellaneous
Subtotal Project Cost
$
6,200,000
Project Contingency10% for building revitalization
$
700,000
Total Contingency
$
700,000
$
6,900,000
$
99
Project Contingency
Total Budget
Total Project Cost / sqft
COLORADO STATE UNIVERSITY Facilities Planning Design and Construction
10% of construction cost
121
111 110
113
112
119
120
108
101
103 124
109 102
115 118
107
106
104
123
116 122
117
114 105
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124