Dec 28, 2017 - Bids were opened on December 13 for the Lake James to Fontenelle Park ... OmahaCSO.com. Clean Solutions f
Quarterly Report | 2017 Q4 October–December 2017
Omaha Combined Sewer Overflow Control Program Implementation Phase
CSO Project tours were given after Nebraska Department of Environmental Quality informational meetings on October 23, including the Leavenworth Lift Station (above). Small businesses and general contractors met at the REACH event on November 16 (right).
CONTENTS HIGHLIGHTS . . . . . . . . . ii PROGRAM OVERVIEW . . . . . . . . . . . 1 GOAL REVIEW . . . . . . . . . . . . . . 2
Fourth Quarter Highlights
• Construction continues on the South Interceptor Force Main (SIFM) North
Segment. Substantial completion is expected in January 2018. The force main installation was completed on December 6, 2017. • Bids were opened on December 13 for the Lake James to Fontenelle Park Sewer Separation Project. There were four bids opened and two were less than the engineer’s estimate. Bids will be evaluated and the lowest and best bid will be forwarded on to City Council for construction contract award. • Design work continues on the revised Saddle Creek Retention Treatment Basin. Discussions have begun regarding a contractor industry day to be held this spring as well as a contractor prequalification process prior to the expected construction bid in late fall 2018. These activities are intended to increase competition by making more potential bidders aware of the project. • The bid advertisement date for the Burt-Izard Lift Station is still pending, tentatively planned in early 2018. Contractor outreach activities were held in November that included site visits and discussions to help mitigate risks relating to the replacement of the existing isolation gates. • A consultant team was selected for the design of CSO 119 South Barrel Conversion Project and the contract negotiations are underway. This design work will start in early 2018. • The CSO Annual Report required by the Nebraska Department of Environmental Quality for the period ending September 30 was completed. This report is available on the CSO website, www.OmahaCSO.com. ON THE COVER: (Clockwise from left) Missouri River Water Resource Recovery Facility odor control system fans, part of the new odor control system that use biofilters, which will replace the existing chemical scrubber system; concrete placement in SIFM North Shaft 1 at Heartland of America Park; and John Creighton Boulevard and Miami Sewer Separation completed project, looking west on Corby toward 36th Street.
ii
Omaha Combined Sewer Overflow Control Program | Implementation Phase
PROJECT SPOTLIGHT . . . . . . . . . . 6 BUDGET DETAILS . . . . . . . . . . . . . 9 PROJECTS UNDER CONSTRUCTION . . . . 10 KEY ACTIVITIES . . . . . 12 APPENDIX . . . . . . . . . . A1
For additional information regarding the Omaha CSO Program, please visit www.OmahaCSO.com or call the CSO Program Hotline at 402-341-0235.
A City of Omaha Public Works Initiative
PROGRAM OVERVIEW
PROGRAM MISSION
The Program Management Team’s job is to save money for City ratepayers and do what is best for the community as we meet the objectives and requirements of the Clean Water Act.
Goal 1: Regulatory Compliance. Meet specific regulatory requirements as identified by the Environmental Protection Agency and Nebraska Department of Environmental Quality. • Complete implementation of CSO projects within schedule identified. • Reduce pollutant discharge to the Missouri River and Papillion Creek.
Goal 2: Economic Affordability. Minimize cost impact to ratepayers by completing CSO projects within or under budget.
Program Schedule The Program schedule is shown below. Final implementation is targeted for 2027. Program project types are categorized into two groups: major projects and sewer separation projects. The project implementation approach was selected based on its positive effect on water quality, supporting development, construction sequencing, and cost. Schedules were further coordinated to allow for concurrent construction. A list of projects by Long Term Control Plan phase is located in the Appendix.
CSO Solutions
Goal 3: Community Acceptance. Maintain continuous public dialogue, provide information and pursue opportunities for multiple benefits in CSO projects.
2020
CURRENT CSO PERMIT IS VALID THROUGH OCTOBER 2020
The CSO permit was approved by Nebraska Department of Environmental Quality in September 2015 with refined requirements that lower the City’s costs in support of Omaha’s Program. The permit was modified in June 2017.
www.OmahaCSO.com
Clean Solutions for Omaha Quarterly Report | Fourth Quarter 2017
1
Goal 1: Regulatory Compliance Regulatory Compliance includes two items: 1) implement projects within the identified schedule, and 2) reduce pollutant discharge to the Missouri River and Papillion Creek.
SCHEDULE
The following charts show implementation milestones, with a list of project phases located in the Appendix. A significant update to the Program permit recently occurred; the charts below reflect this permit modification. All regulatory milestones have been met to-date.
Phase
Deep Tunnel System/Missouri River Retention Treatment Basin Nearing the completion of the Project Definition Task effort, with the Executive Summary and supporting documents to be completed in first quarter, 2018.
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
MAJOR PROJECTS
Missouri River Water Resource Recovery Facility Schedule B2 construction completion nears 75%, and the contractor is on schedule.
Description of Phase
–
Missouri River Water Resource Recovery Facility Improvements
–
South Interceptor Force Main
2
Saddle Creek Basin
4
Deep Tunnel System/Missouri River Retention Treatment Basin, and others Notice to Proceed to Consultant for Final Design
Notice to Proceed to Constructor
Current Status Project Phase
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
SEWER SEPARATION PROJECTS
Phase 1 Phase 2 Phase 3
Nearing final completion of the Gilmore Avenue Project, which will complete this phase. CSO 210 Sewer Separation Design request for proposal will be issued in first quarter, 2018 to kick off this phase.
*
10
Study & Design Projects
Phase 4 Phase 5 Phase 6 Phase 7 Commence Bidding
All Construction Projects Complete
25
Bid/Construction/ Complete Projects
26
Future Projects
*As part of adaptive management, 38 Long Term Control Plan projects have been removed, combined, or pooled; this includes 13 that were eliminated due to the change in the
2
Minne Lusa permit modification in June 2017.
Omaha Combined Sewer Overflow Control Program | Implementation Phase
PROGRAM OVERVIEW: GOAL 1
STATISTICS
61
Estimated Program Construction Costs, through December 2017,**
Deliver ed
*
gh rou th
Long Term Control Plan projects
has been paid out for construction activities.
$120M Construction
80
value of projects in bid or current construction
Construction Packages Multiple packages provide more opportunities for local contractors and efficient delivery.
$195M
$287M
Construction value Construction value of projects completed (construction dollars paid out) of projects in design ** E xcludes RNC projects and continues to include Minne Lusa Basin funding for individual projects that will be identified after the re-evaluation.
100 90
Completion of Deep Tunnel System Projects
CSO Bacteria Loading Reduction (%)
80
Completion of Saddle Creek RTB Project and sewer separation
CSO Load Reduction
70
12/31/2017 Completion of Riverview Lift Station and sewer separation projects
60 Completion of Phase One Major Projects and sewer separation
50
REGULATORY COMPLIANCE
Completion of Leavenworth Lift Station and some MRWRRF upgrades
40 30
Completion of SOIA Projects and sewer separation
20
www.OmahaCSO.com
2028
2027
2026
2025
2024
2023
2022
2021
2020
2019
2018
2017
2016
2015
2014
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
0
2002
10
The graph (at left) indicates the estimated reduction of bacterial loading in CSOs as projects are completed. This chart is from the Annual Report, which was submitted on December 28, 2017 to the Nebraska Department of Environmental Quality.
Clean Solutions for Omaha Quarterly Report | Fourth Quarter 2017
3
PROGRAM OVERVIEW: GOAL 2
Goal 2: Economic Affordability
Economic Affordability is the minimization of the cost impact to the ratepayers. Construction costs have been contained as shown in the following metrics.
RIVERVIEW LIFT STATION VALUE ENGINEERING The Riverview Lift Station Replacement project underwent a Value Engineering (VE) effort to review and evaluate construction costs to identify savings. The project also had a VE effort at the 30% design submittal. The VE effort identified over $1 million of construction costs savings at 30% and an additional $1 million of construction cost savings at 60%. All projects have cost and VE reviews at specific stages in the project design and these will continue for this project to provide the best project for the cost, while achieving the stated project goals.
Budget Amount
Bid Award
CONSTRUCTION BID AWARD COMPARISON
The figures show that the CSO Program Construction Project Bid Awards, of sewer separation projects in construction, are about 10% below the initial 2009 Program budget amount, indicating potential cost savings to the Program in each projects’ initial construction costs.
RATEPAYER ASSISTANCE
When the Long Term Control Plan was approved, it marked the start of a ratepayer assistance plan to help low income and fixed income households with sewer rate increases necessary to fund the Program. Ratepayers are eligible if they receive Low Income Heat and Energy Assistance (LIHEAP) from their utility. This has kept administrative costs to a minimum and provided the maximum benefit to those who need it. For assistance or to apply for Nebraska LIHEAP, call 800-383-4278.
4
From January through December 2017, over $
1,687,383
has been provided in assistance; for a total of
7,144,244
$
from inception (May 2011) through December 2017.
Omaha Combined Sewer Overflow Control Program | Implementation Phase
PROGRAM OVERVIEW: GOAL 3
Goal 3: Community Acceptance Community Acceptance provides continuous open dialogue with the public along with timely and accurate project information. The Program is also providing additional neighborhood benefits, beyond the improved sewer system and water quality enhancements.
PUBLIC ENGAGEMENT OPPORTUNITIES The CSO Program provides opportunities for the public to engage with project teams during key stages of design and construction. The public is typically engaged for the: • Project design kick-off meeting • Project 30% design informational meeting with surrounding neighborhood associations • Project 60–80% design open house • Engagement of neighborhood champion(s) for neighborhood enhancements when appropriate • Project pre-construction meeting In addition, the CSO Program is partnering with the Omaha Chamber’s REACH Program, to inform potential bidders and small business of subcontracting opportunities on CSO construction projects. During the bid period for the Lake James to Fontenelle Sewer Separation project, an outreach meeting was held on November 16 by the City, Program Management Team, and REACH.
ADDITIONAL PUBLIC BENEFITS
In addition to the over 56,000 feet of sewer pipe constructed and/or rehabilitated, Program projects allowed for the reconstruction of adjacent infrastructure. This provided a total community benefit value of over $38 million, as identified below.
374
equivalent blocks of replaced street
763
impacted driveway approaches replaced
452
76
acres of enhanced park/ open space
1,040
ADA compliant curb ramps constructed
equivalent blocks of replaced sidewalk
7,043 linear feet of new trails
136,000
1,887
linear feet of upgraded gas and water utility infrastructure
new trees
Includes 23 completed or underway projects as of second quarter, 2017, since the inception of the Program.
www.OmahaCSO.com
Clean Solutions for Omaha Quarterly Report | Fourth Quarter 2017
5
South Interceptor Force Main Project
North Segment Construction
View of excavated tunnel as it is being constructed between Marcy Street and Heartland of America Park.
The existing South Interceptor Force Main (SIFM) was constructed in the early 1960s and has remained in continuous operation for more than 50 years. Its current condition makes it unreliable for continued long term use and replacement is necessary to convey increased dry and wet weather flows to the Missouri River Water Resource Recovery Facility (MRWRRF). The new SIFM under construction will provide greater reliability and maximize flow capacity for conveyance to the new MRWRRF headworks.
6
Construction of South and Central Segments began in January 2014 and were complete in November 2015. Construction of the North Segment started in January 2015 and consists of approximately 4,500 feet of 48-inch pipe. It begins near Lewis and Clark Landing, south of I-480, and continues south to Pierce Street. A significant portion of the alignment, approximately 3,500 feet, is being constructed in bedrock nearly 80 feet beneath Heartland of America Park, the ConAgra campus, and the Breakers Building.
Omaha Combined Sewer Overflow Control Program | Implementation Phase
PROJECT SPOTLIGHT A tunnel boring machine (TBM) was used to bore through bedrock and construct a tunnel for the new force main of the North Segment. In 2016, the TBM encountered an unexpected geologic anomaly consisting of an area of sand, boulders, and groundwater instead of bedrock. The TBM was not equipped to handle this material and was unable to proceed and finish tunnel boring. Additionally, this anomaly threatened to flood the tunnel with water, endangering workers.
After evaluating many options to complete tunnel construction, use of a micro-tunnel boring machine was selected to mine gravel and boulders and complete the remaining 900 feet of tunneling. In July 2017, workers built a rescue shaft for the original TBM, just beyond where it became stuck in Heartland of America Park. The micro-tunnel boring machine completed tunnel excavation in August 2017. Both the TBM and microtunnel boring machine were removed from the project
South Interceptor Force Main extending from the newer surface into the tunnel. Cross section schematic of the tunnel. UPRR Crossing
Rescue Shaft Heartland of America Park
ConAgra Campus
Approximate Top of Bedrock 900’
Rock Tunnel 1,924’
The Breakers Building
Tunnel Shaft #3 Leavenworth Lift Station
Tunnel Shaft #2
80’
Tunnel Shaft #1
25’
Lewis & Clark Landing
731’
(Continued on page 8.)
www.OmahaCSO.com
Clean Solutions for Omaha Quarterly Report | Fourth Quarter 2017
7
(Clockwise from top left) North tunnel shaft in Heartland of America Park; completed connection of the force main through the rescue shaft; old TBM breaking into the rescue shaft.
site and pipe is being installed through the tunnel. By January 2018 the project will be substantially complete and the new SIFM will pump sewage to the City’s MRWRRF. This project allows Omaha to reduce the volume of sewage that is released into the Missouri River as part of CSOs, advancing the City toward meeting
8
federal mandates. Restoration of Heartland of America Park will be complete by spring 2018. Removal of the TBM ended a 14-month construction delay and safely solved a series of engineering challenges.
Omaha Combined Sewer Overflow Control Program | Implementation Phase
BUDGET DETAILS The Combined Sewer Overflow (CSO) Program is maintaining overall schedule and budget to meet current regulatory and financial expectations.
Regulatory Progress PROGRAM BUDGET STATUS In 2015 dollars
2009
2027
2.304 B $ 2.171 B $
expected funding
includes dollars from sewer rates, outside grants, and other sources
$580.2M actual cost
Estimated Complete:
Spent to Date:
While there is still much work to be done, a significant amount of progress has been made toward Program implementation and the Program continues to meet all regulatory milestones.
CSO Program Elements: Program Management:
Management and administration of Programrelated activities
Sewer Separation:
PROGRAM CAPITAL ALLOCATION $1.1 B
Sewer projects that will reduce flows to the combined sewer system Facilities
Conveyance1:
South Interceptor Force Main (SIFM) Minne Lusa Stormwater Sewer
$1 B $900 M
Facilities1:
$800 M
Deep tunnel, Missouri River Water Resource Recovery Facility (MRWRRF), high rate treatment, lift station, and storage structure projects
Sewer Separation
$700 M $600 M
Miscellaneous:
$500 M
Miscellaneous study-related projects
Conveyance
1
$400 M $300 M $200 M $100 M
Program Mgmt.
$51.6 M
$0 Actual Cost
www.OmahaCSO.com
$229.2 M
$192.5 M
T he combination of conveyance and facilities constitutes most of the major projects.
Misc. Projects
$99.8 M $7.1 M Total Capital Cost (2015 Dollars)
Clean Solutions for Omaha Quarterly Report | Fourth Quarter 2017
9
PROJECTS UNDER CONSTRUCTION FIGURE 1
BRIDGE STREET Mi
sso
CC
iR
ive
r
24th St
72nd St
Carter Lake
tD
r
MINNE LUSA
30th St
COLE CREEK
ur
Ab b
ot
Maple St
BURT-IZARD
PAPILLION CREEK NORTH k Cre e le dd Sa
10th St
24th St
42nd St
LEAVENWORTH
Center St
Mis
er Riv
LEGEND Current Projects Completed Projects North Segment
72nd St
CSO Study Basins
SADDLE CREEK 42nd St
TSOUTH INTERCEPTOR
City Council District 1 City Council District 2 City Council District 3
DD
PAPILLION CREEK Q Street SOUTH
City Council District 4
J OHERN/ MONROEZ
Figure 1 and corresponding table to the right identify project details and completed projects. 10
ri sou
Q
Dodge St
L Street
Eppley Airfield
Omaha Combined Sewer Overflow Control Program | Implementation Phase
City Council District 5 City Council District 6 City Council District 7
CURRENT CONSTRUCTION
KEY
J
Q
CONSTRUCTION CONTRACTS
CONSTRUCTION MANAGER’S CURRENT ESTIMATE AT COMPLETION
Missouri River Water Resource Recovery Facility – Schedule B2
South Interceptor Force Main – North Segment
51,220,953
$
73% Complete 32,486,888
$
97% Complete 320,210
Tunneling, pipe installation completed.
$
Spring Lake Park, Landscaping
76% Complete
T Missouri Avenue/ Spring Lake Park Sewer Separation Phase 2
6,513,539
Achieved substantial completion August 22, 2017.
$
0% Complete 10,600,000
Gilmore Avenue Sewer Separation Phase 1 and 2
$
Notice to Proceed November 1, 2017.
98% Complete
Z
315,000
Gilmore Avenue Landscape Improvements
CC
Masonry work on new chemical building completed; exterior painting commencing.
$
72% Complete
Fontenelle Park Lagoon Improvements
7,800,303
$
77% Complete 2,406,536
$
42nd and Q Street Sewer Separation
Work on final punch list items continues. Awaiting spring planting. Park area restoration continues. Notice to Proceed spring 2018.
0% Complete
DD
Hitchcock Park Green Infrastructure
$
425,925
Two-year maintenance period started October 2017.
97% Complete
* Shaded bars indicate the progress toward completion of each project. www.OmahaCSO.com
Clean Solutions for Omaha Quarterly Report | Fourth Quarter 2017
11
KEY ACTIVITIES Below is a list of key activities for the current and upcoming quarter. A full list is included in the Appendix.
2017 FOURTH QUARTER KEY ACTIVITIES
Regulatory • Continued discussion with the Nebraska Department of Environmental Quality regarding a revised Consent Order. • On October 23, 2017, the City of Omaha staff, with assistance from Program Management Team, provided an overview of the CSO Program to approximately 19 individuals with the Nebraska Department of Environmental Quality and the Nebraska Department of Health and Human Services. The overview included a presentation on the history of the Omaha collection system, the status of implementation of the CSO Long Term Control Plan, its positive impact on water quality, and an overview of the work being done at several CSO projects sites. A tour of several CSO project sites was conducted after the overview. Program • Coordination efforts continued with Omaha Metro agencies to track upcoming large construction bid opportunities. This benefits all owners by allowing adequate time to prepare bids and encouraging responses from multiple construction companies. • The Technical Assessment for Cost Savings task continued as the Program Management Team is finalizing the draft report, which includes identification of significant Program cost saving measures to be submitted for City review in the first quarter, 2018. • The Deep Tunnel Project Definition effort continued, with expected completion in the first quarter of 2018. Workshops were held with the City to discuss cost, alternative project delivery, construction contract packaging and project risk. • Updates continued with the City rate consultant, Stantec on the financial capability assessment and rate model update. 12
• The Program Risk Management Plan update
commenced this quarter with a kickoff meeting. Workshops are scheduled in first quarter, 2018 to review the Program Risk Registers. Projects • Construction Notice to Proceed for Missouri Avenue/ Spring Lake Park Sewer Separation Phase 2 was given on November 1. This construction project is expected to take approximately two years to complete. • EmNet continued the evaluation of Real Time Controls opportunities on the City’s combined sewer system, which utilizes existing infrastructure. The final report is expected in the first quarter, 2018.
UPCOMING 2018 FIRST QUARTER KEY ACTIVITIES
Regulatory • Hold quarterly meeting with Nebraska Department of Environmental Quality and Environmental Protection Agency to discuss Program progress. Program • Continue to look for ways to save money for the ratepayers while still meeting objectives and requirements of the Clean Water Act. Projects • Bid advertisement for the Burt-Izard Lift Station is expected to be in the first quarter, 2018. • The Monroe Lift Station conceptual design contract is expected to be approved with CDM Smith in first quarter, 2018. • A request for proposals will be issued in the first quarter, 2018 for Papillion Creek North Sewer Separation Project and 18th and Fort Flow Reduction Project. • The CSO 110 South Barrel Conversion Project conceptual design contract is expected to be approved in the first quarter, 2018.
Omaha Combined Sewer Overflow Control Program | Implementation Phase
This page intentionally left blank.
Printed February 2018