Aswan high dam - Distributed control system ... station service transformers
attached ... Power plant and control system maintenance routines are simpler.
Aswan high dam - Distributed control system AUTOMATION
ASWAN HIGH DAM - HYDROPOWER PLANT - POWER GENERATION & DISTRIBUTION SYSTEM - “AHD” in Aswan, Egypt
Power System Overview Aswan High Dam (AHD) - Hydro Power Plant was erected and commissioned in 1972. At the time it was the world's greatest, as well as it's 450 km long, artificial, Nasser lake. The powerplant and the dam contribute overall Egypt's development in many ways. Most important are: maintaining constant level of the Nile river (floods protection, agricultural needs…), and stabile power supply during all seasons.
Most outstanding AHD power plant's features are it's size and fast synchronization response. It takes 1 minute from “standstill” till “synchronization” and additional minute to reach the full load. Owing to these qualities, AHD power plant is appointed the leading role in the region's power generation and distribution system covering Egypt, Libya, Syria, Jordan, and Lebanon. It's task is to maintain grid's stabile frequency (50 Hz) and required voltage level (480-525 kV).
INTEA d.d. - AUTOMATION
- Av. V. Holjevca 27, HR-10020 Zagreb, CROATIA
tel: +385 1 3436 200 ♦ fax: +385 1 7898 860 ♦ e-mail:
[email protected]
♦
http: //www.intea.hr
ASWAN HIGH DAM - HYDROPOWER PLANT - POWER GENERATION & DISTRIBUTION SYSTEM - “AHD” in Aswan, Egypt
Power System Overview At full power, AHD power plant generates 2100 MW. It consists of 12 units, divided in 4 blocks. That enables simultaneous connection of 3 units to the grid. Each unit comprises: • turbine (Frances type, max. gross head 74m), • generator (60 pole, 100rpm, 180 MW max, 15.75 kV) • unit transformer (500kV). There are 2 switchyards: • 500 kV (2 exit lines) • 132kV (4 exit lines and 2 feeders)
There are 2 auto-transformers reducing the voltage from 500 kV to 132 kV and 6 kV. Internal power supply is additionally secured with 2 station service transformers attached to units 1 and 7.
INTEA d.d. - AUTOMATION
- Av. V. Holjevca 27, HR-10020 Zagreb, CROATIA
tel: +385 1 3436 200 ♦ fax: +385 1 7898 860 ♦ e-mail:
[email protected]
♦
http: //www.intea.hr
ASWAN HIGH DAM - HYDROPOWER PLANT - POWER GENERATION & DISTRIBUTION SYSTEM - “AHD” in Aswan, Egypt
Controls upgrade project Upgrade Project Controls upgrade project was started in 2000. Main reasons for implementation of a new distributed control system were: 1) expensive and difficult maintenance of old, relay logic based control system 2) need to improve overall performance and efficiency of AHD hydro power plant: control, post-trip analyzing, trend recording, protection, etc.
Scope • Control system (DCS) • Central control room, mimic board and electrical room • Automatic and manual synchronization device • Transducers, transmitters and instruments • Information management system (IMS) • Protection system • Power and control cables and cable trays • Air conditioning system
INTEA d.d. - AUTOMATION
- Av. V. Holjevca 27, HR-10020 Zagreb, CROATIA
tel: +385 1 3436 200 ♦ fax: +385 1 7898 860 ♦ e-mail:
[email protected]
♦
http: //www.intea.hr
ASWAN HIGH DAM - HYDROPOWER PLANT - POWER GENERATION & DISTRIBUTION SYSTEM - “AHD” in Aswan, Egypt
Controls upgrade project
Outcome Since implementation of the project, reliability and operation safety are significantly increased. Units response time is improved. Supervision and control are simple and user-friendly. Power plant and control system maintenance routines are simpler. Life-time of primary equipment is increased. Post-trip analysis is efficient and accurate. All the improvements will further strengthen AHD power plant's leading position in Egypt and the region.
INTEA d.d. - AUTOMATION
- Av. V. Holjevca 27, HR-10020 Zagreb, CROATIA
tel: +385 1 3436 200 ♦ fax: +385 1 7898 860 ♦ e-mail:
[email protected]
♦
http: //www.intea.hr
ASWAN HIGH DAM - HYDROPOWER PLANT - POWER GENERATION & DISTRIBUTION SYSTEM - “AHD” in Aswan, Egypt
Automation and control system Equipment Power generation and distribution in “AHD" is monitored and controlled by ABB Advant products family equipment: • Process controllers - AdvantController 450 (17 units) • Operator stations - AdvantStation 500 OS - (3 units) • Operator stations - Windows NT based PC application (2 units) • Information Management Station - PC based application - (2 units) • Local Viewers - PC based application - (26 units) • Control network MasterBus 300, Plant Network TCP/IP, MODBUS serial links etc. • Event/alarm printers, hardcopy printers and report printers.
Controller cabinet
AC 450 INTEA d.d. - AUTOMATION
Hardcopy - Av. V. Holjevca 27, HR-10020 Zagreb, CROATIA
AS 500OS
AS 500IMS
tel: +385 1 3436 200 ♦ fax: +385 1 7898 860 ♦ e-mail:
[email protected]
♦
http: //www.intea.hr
ASWAN HIGH DAM - HYDROPOWER PLANT - POWER GENERATION & DISTRIBUTION SYSTEM - “AHD” in Aswan, Egypt
Main ABB DCS equipment configuration Network Switch
Powerhouse
Unit 1
Screen
AC450 red. I/O Rack
DCS room
Industrial PC
AC450 M DI: 384 DO: 96 AI: 128 (4..20mA) AO: 16 PT100:155
IMS A
IMS B
AC450 T&M&G
AC450 T&M&G HA DBS DSV
AC450
... same for
HA DBS DSV
AC450
Units 2,...,12
CCR
500 kV
Operator Station 1 Operator Station 2 AS530 AS530 OS 3 Remote I/O Racks
I/O Rack AC450 red.
Controllers room
Shift room
Workstation 1
Workstation 2 Network Switch AC450 red.
I/O Rack
Remote I/O Rack
AC450 red.
INTEA d.d. - AUTOMATION
- Av. V. Holjevca 27, HR-10020 Zagreb, CROATIA
I/O Rack
tel: +385 1 3436 200 ♦ fax: +385 1 7898 860 ♦ e-mail:
[email protected]
♦
http: //www.intea.hr
ASWAN HIGH DAM - HYDROPOWER PLANT - POWER GENERATION & DISTRIBUTION SYSTEM - “AHD” in Aswan, Egypt
Distributed Control System Requirements
ABB AHD DCS acts as a single and integral system regardless of it’s complexity and equipment distribution.
DCS controls and supervises:
Main tasks of ABB DCS in AHD power plant are: •
12 12 2 2 360 10200 500
INTEA d.d. - AUTOMATION
generators unit transformers reactors autotransformers breakers physical I/O signals serial I/O signals.
- Av. V. Holjevca 27, HR-10020 Zagreb, CROATIA
• •
•
Supervision & control of all major power system equipment from control room. Ensuring voltage and frequency stability. Ensuring coordination of generators, optimizing and fault finding tools (reports, trends, process overviews, event & alarm lists, system status, system list, ...). Local viewers support (local PC based process monitoring and display)
tel: +385 1 3436 200 ♦ fax: +385 1 7898 860 ♦ e-mail:
[email protected]
♦
http: //www.intea.hr
ASWAN HIGH DAM - HYDROPOWER PLANT - POWER GENERATION & DISTRIBUTION SYSTEM - “AHD” in Aswan, Egypt
Automation and control system Scope
Features
Entire power system is controlled by process controllers and runs fully automatic. Each part can be controlled and monitored from any operator station. Control includes: turbines, generators, breakers, transformers, subsystems etc.
• Control
logic in AC450 related to each generating unit includes: start & stop sequence, unit's circuit breaker handling, active & reactive power control, temperature control, MODBUS communication with protection system (generator protection unit GPU2000R, transformer protection unit TPU2000R), energy calculation, light and annunciation system.
• Generating
unit can be controlled from operator stations or control console in central control room and from LHMI or manual controls on unit control cubicle.
• Unit
synchronization devices synchrotact 5202 (automatic) synchrocheck 5100 (manual).
are: and
ABB ABB
• New control system was adjusted with existing excitation (auxiliary generator & thyristor excitation) and turbine (“Woodward” governor) systems that were not changed.
INTEA d.d. - AUTOMATION
- Av. V. Holjevca 27, HR-10020 Zagreb, CROATIA
tel: +385 1 3436 200 ♦ fax: +385 1 7898 860 ♦ e-mail:
[email protected]
♦
http: //www.intea.hr
ASWAN HIGH DAM - HYDROPOWER PLANT - POWER GENERATION & DISTRIBUTION SYSTEM - “AHD” in Aswan, Egypt
Automation and control system
Features • Supervision and handling of circuit breakers (synchronization) is possible from operator station process displays and mimic board (hard-wired backup) in control room. • Actual positions of earthing switches and isolators are presented on process displays. • Remote control from dispatching center in Cairo is supported. • Automatic reports, post-trip analysis and 1 year data storage for process data from AC450 controllers.
Other Features Other DCS features include: redundancy (processors and communication), MODBUS serial links, GPS time sinchronization, long term data storage, data logging and trend displays, ...
INTEA d.d. - AUTOMATION
- Av. V. Holjevca 27, HR-10020 Zagreb, CROATIA
tel: +385 1 3436 200 ♦ fax: +385 1 7898 860 ♦ e-mail:
[email protected]
♦
http: //www.intea.hr
ASWAN HIGH DAM - HYDROPOWER PLANT - POWER GENERATION & DISTRIBUTION SYSTEM - “AHD” in Aswan, Egypt
Operator's screen example
INTEA d.d. - AUTOMATION
- Av. V. Holjevca 27, HR-10020 Zagreb, CROATIA
tel: +385 1 3436 200 ♦ fax: +385 1 7898 860 ♦ e-mail:
[email protected]
♦
http: //www.intea.hr
ASWAN HIGH DAM - HYDROPOWER PLANT - POWER GENERATION & DISTRIBUTION SYSTEM - “AHD” in Aswan, Egypt
Intea’s contribution Scope - general • •
• • •
• •
• • • •
Scope - sections
controller's cabinets design, specification and manufacturing supervision power plant distributed control system design (process logic functional description, site survey…) process controllers application design (signals database, programs, type circuits, testing) operator stations application design and customizing (process displays, dialogs) factory acceptance test with client (demonstration of system capabilities, changes implementation) site acceptance test commissioning (wiring supervision, I/O check, synchronization, transducers adjusting and installation, control logic commissioning…) unit & switchyard circuit breakers synchronization start-up training (operation and maintenance personnel) DCS modifications, extensions and maintenance
INTEA d.d. - AUTOMATION
- Av. V. Holjevca 27, HR-10020 Zagreb, CROATIA
Intea was responsible for configuration and application software in all Process Controllers, Operator Stations and Information Management Controllers, except for LHMI communication support software.
Duration and results January 2001 – September 2001, 6 Intea’s engineers worked in Alstom, Denver on project design, cubicle production supervision and FAT-s. October 2001 – November 2003, 6 Intea’s engineers worked on site (in shifts) until successful handover. INTEA’s work was recognized, by ALSTOM project management and end-user HPGC, as outstanding and highly professional. Post start-up projects: 2005-2010., DCS HW and SW deliveries: extensions, modifications, site activities and commissioning due to scheduled overhauls and modernization of generating units by Voith-Siemens. Total of 17 orders for various Aswan DCS equipment and works awarded to INTEA since 2001, testify of the client's satisfaction. tel: +385 1 3436 200 ♦ fax: +385 1 7898 860 ♦ e-mail:
[email protected]
♦
http: //www.intea.hr